Viewing inquiries for 01-0C1104

Submit new inquiry for this project


Inquiry #1: 1)Section 99-075423 TPO roofing asks for R35 min rigid insulation and the Drawing A7-10 shows a R30 rigid insulation. Can you please clarify the R-Value required?

2)Drawing A1-10 detail A & B and A1-11 detail F note calls out 'TPO roof over cover board over rigid insulation' but detail doesn't show rigid insulation going up parapet slope. Is this a miss print or is rigid insulation required on the parapet slope?

3)Drawing M-4.08 detail 2 does not show a detailed duct support. The duct supports should be supported on a wood curb or sleeper a min of 8" above finished roof. The curb or sleeper should have a metal cap similar to M-4.04 detail 2.

Inquiry submitted 01/11/2022

Response #1:(BI#1)-1.Total R-value must be R-35 per section 99-075423 - THERMOPLASTIC POLYOLEFIN (TPO) ROOFING of the Special Provisions.
2.Regarding drawing A1-10 details A & B, rigid insulation is along partial slope of parapet as shown in detail A. Regarding drawing A1-11 detail F, rigid insulation is along entire parapet slope as shown. Please bid per current contract documents.
3.Submit duct support system for approval per item 1.3 in section 99-233100 DUCTWORK of the Special Provisions after Contract award. Please bid per the current contract documents.

Response posted 01/12/2022




Inquiry #2: Plan sheet A1-15 Interior Elevation item 2 shows an obscured glass window in the Lactation room that is not on the window schedule. What is the intent for this window? Provide details and specs on the frame and glass.
Inquiry submitted 01/18/2022

Response #1:(BI#2)-Provide window with obscure glass in the Lactation Room as shown. Refer to details 6A and 6B on plan sheet A7-04 for similar framing details. Refer to sections 99-08520B(3) Windows and 99-08810B(2) Glazing of the Special Provisions for frame and glass specifications.

Response posted 01/18/2022




Inquiry #3: 2Plan sheet A1-06 Roof Plan, the Mechanical Roof plans, and structural seem to have differing roof framing identified. A1-15 indicates a full perimeter of framed crickets and then tapered insulation for water diversion to the roof drains. Plan sheets MP1-04, M-302, and MP1-04 do not show these. Please clarify the location, intent and provide details for the wood framed roof top crickets
Inquiry submitted 01/18/2022

Response #1:(BI#3)-Follow structural plans for locations and details of wood roof framing.

Response posted 01/18/2022




Inquiry #4: Plan sheet A1-06 Roof plan indicates an exterior Aluminum ladder from the office roof to the lab roof. It appears these ladders are landing on a 12:12 wood framed cricket. The details provided on plan sheet A7-09 do not seem to be applicable to this. Please clarify in detail how this area, landings, and ladder are to be assembled.
Inquiry submitted 01/18/2022

Response #1:(BI#4)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheets A1-06 and A7-09 have been revised.

Response posted 01/18/2022




Inquiry #5: Plan sheet A1-06 Roof plan does not indicate any walking mats to access the roof top Mechanical units. Are walking mats required for the TPO roof?
Inquiry submitted 01/18/2022

Response #1:(BI#5)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A1-06 has been revised.

Response posted 01/18/2022




Inquiry #6: Plan sheet A1-06 indicates the Roof Hatch landing in/on a tapered insulation roof cricket. This will not provide a safe level landing area to step to/from the Roof Access ladder. How are we to proceed at this location?
Inquiry submitted 01/18/2022

Response #1:(BI#6)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A1-06 has been revised.



Response posted 01/18/2022




Inquiry #7: Plan sheet A7-06, detail 6 Exterior Wall Section indicates the sectional details at the interior walls. Is a moisture barrier required where the drywall is going to be in contacts with the concrete curb? How shall the drywall attach in this location?
Inquiry submitted 01/18/2022

Response #1:(BI#7)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-06 have been revised

Response posted 01/18/2022




Inquiry #8: Plan sheet A7-02, Window Schedule state “Install Horizontal Aluminum Blinds” at the Type A windows. What Gauge Aluminum blinds do you want?
Inquiry submitted 01/18/2022

Response #1:(BI#8)-Refer to Addendum No. 1 dated January 28, 2022. Section 99-12510 HORIZONTAL BLINDS of the Special Provisions has been revised.

Response posted 01/18/2022




Inquiry #9: Plan sheet A7-01, Interior Finishes and Color, Floor, Type F- states “Concrete with sealer and hardener”. Is this to be a grind and polished floor, or just smooth troweled and sealed? Please provide clarification and specification for this.
Inquiry submitted 01/18/2022

Response #1:(BI#9)-Type F-1 floor is to be smooth troweled and sealed. Refer to section 99-03300 of the Special Provisions.



Response posted 01/18/2022




Inquiry #10: Plan sheet A6-02 Guardrail Detail show the intended assembly methods for the rails but does not qualify what the material should be. Is this iron or stainless steel? Is it to be hot dipped galvanized? Is it to be powder coated or painted?
Inquiry submitted 01/18/2022

Response #1:(BI#10)-Refer to Addendum No. 1 dated January 28, 2022; section 99-05500 BUILDING MISCELLANEOUS METAL of the Special Provisions has been revised. Guardrail is to be painted per plan sheet A7-07.

Response posted 01/18/2022




Inquiry #11: Plan sheet A7-08 Roof Access Detail indicate how the Fixed Interior Metal Wall ladder to the Roof is to be mounted and installed. Detail 5 shows the anchor point for attachment to a full height wall. Based on the plan sheet A1-08, A Building Section, it does not appear that the wall this ladder is to mount to is full height. Please clarify in detail the intent at this location.
Inquiry submitted 01/18/2022

Response #1:(BI#11)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheets A1-08 and A1-12 have been revised.



Response posted 01/18/2022




Inquiry #12: Plan sheet A1-05, room 207 calls for 8 recessed light fixtures to be oriented perpendicular to the exterior wall. The ceiling framing as identified on plan sheet ST1-2 will not allow the fixtures to be recessed in this orientation. What is the intent at these locations?
Inquiry submitted 01/18/2022

Response #1:(BI#12)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet ST1-2 has been revised.



Response posted 01/18/2022


Response #2:

Response posted 01/18/2022




Inquiry #13: Plan sheets A1-08 thru A1-13 show many of the interior non-bearing wall not running to the bottom of the trusses. Will any of these walls require racing to the roof diaphragm? If so, please provide details.
Inquiry submitted 01/18/2022

Response #1:(BI#13)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet ST1-10 has been revised.

Response posted 01/18/2022




Inquiry #14: What is the intent for the exposed vertical seems at the interior finished APA Interior Grade A-C, Group 1, Exposure 1 plywood areas?
Inquiry submitted 01/18/2022

Response #1:(BI#14)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-01 has been revised.



Response posted 01/18/2022




Inquiry #15: The Concealed spaces created in the wood framed roof crickets may be required to have fire sprinklers in them. These areas will need to be accessible for service and inspection. What is the intent for this access if the sprinklers are required?
Inquiry submitted 01/18/2022

Response #1:

Response posted 01/18/2022


Response #2:(BI#15)-Fire sprinklers are not required in these spaces.



Response posted 01/18/2022




Inquiry #16: Please confirm all furnishings (desks, cubicles, etc..) are not to be supplied by the contractor.
Inquiry submitted 01/18/2022

Response #1:(BI#16)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A1-02 have been revised.

Response posted 01/18/2022




Inquiry #17: 1. Detail 1/M-4.08 is calling out “steel beam” under the prefab HVAC curbs at roof. Please forward specific information for the steel beam (size, attachment details, etc..) as no information is found on the mechanical or structural drawings.
2. Walkway Framing Plan/ST1-4 is calling out beam at gridlines G/1 as “6x4”, seems to be error, please clarify.
3. Details 2 & 5/A7-10 calls out “prefabricated aluminum coping”, details J/A1-12 and P/A1-13 call out “metal coping”, please clarify metal coping material and finish (aluminum, galvanized, prefinished, painted?)
4. Plans do not show any inwall blocking requirements for casework, lockers, metal shelving, etc.. Please clarify blocking/framing clip requirements if required.
5. Building Section 2/ST1-6 is calling out 2x8 ceiling framing and ledger, the Reflected Ceiling Plan/ST1-2 is calling out 2x6 and 2x12 ceiling framing only, please clarify.
6. Roof Framing Plan ST1-3 calls out numerous 6x16 collector beams, please clarify where these beams break (not available full length) and framing requirements at each break point.
7. Longitudinal Building Section ST1-5 calls out “2x4 bridging per manufacturer, typ.”Please provide details showing on-center and attachment requirements for this bridging.

Inquiry submitted 01/18/2022

Response #1:(BI#17)-1.No steel beam. Refer to structural drawings for roof framing and additional support assembly.
2.Refer to Addendum No. 1 dated January 28, 2022. Plan sheet ST1-4 has been revised.
3.Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-10 and Section 99-07410 METAL ROOF AND SIDING of the Special Provisions have been revised.
4.Refer to the following sections of the Special Provisions for anchorage requirements: 99-123615 METAL LABORATORY CASEWORK; 99-10501 WARDROBE AND BIKE LOCKERS; and 99-10670 FREE STANDING STEEL SHELVING.
5.Refer to Addendum No. 1 dated January 28, 2022. Plan sheet ST1-6 has been revised.
6.Refer to Addendum No. 1 dated January 28, 2022. Plan sheet ST1-14 has been revised.
7.Pre-engineered joist truss manufacturer to provide bridging details.






Response posted 01/18/2022




Inquiry #18: Please confirm all furnishings (desks, cubicles, etc..) are not to be supplied by the contractor.
Inquiry submitted 01/18/2022

Response #1:(BI#18)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A1-02 have been revised.

Response posted 01/18/2022




Inquiry #19: Question:
Is there a specific cut off date and time for Pre-Bid Requests for Information? Please Advise.

Inquiry submitted 01/19/2022

Response #1:(BI#19)-The Department prefers no bidder inquiries within 5 days of the bid open date.
Response posted 01/19/2022




Inquiry #20: What is the projected start date for this project?
Inquiry submitted 01/19/2022

Response #1:(BI#20)-Prior to the start of construction of any project there is a process of awarding the contract after bid opening date. Refer to section 3 of the standard specifications for awarding the contract. After award an approval date is determined based on the requirements in section 8-1.04B of the Standard Specifications. Due to the variability of these two processes there is no projected start date.

Response posted 01/19/2022




Inquiry #21: Is there an Existing TOPO Map available for the site? If so, how may it be obtained?
Inquiry submitted 01/19/2022

Response #1:(BI#21)-Please refer to the section 2-1.06B of the special provisions for supplemental project information. There is no “topo map” but section 2-1.06B make available:
1. Digital Terrain Model
2. Alignments and Profiles
3. Cross Sections
4. Digital Design Model
5. Target Lines.


Response posted 01/19/2022




Inquiry #22: Sheet A7-01 Interior Finish Schedule calls out sheet carpet. Sheet A7-04 detail 2 calls out carpet tile. Please specify if we are to install sheet carpet or carpet tiles.
Inquiry submitted 01/20/2022

Response #1:(BI#22)-Refer to section 99-09680 CARPETING of the Special Provisions for carpet requirements.

Response posted 01/20/2022




Inquiry #23: I have found some information regarding warranty period in the Standard Specifications, but can you confirm the warranty time for this project?
Inquiry submitted 01/24/2022

Response #1:(BI#23)-Refer to section 5-1.47 of the standard specifications
Response posted 01/24/2022




Inquiry #24: Sheet A1-10 calls out Lanced Metal Soffit Panels in details 2, A, and E. We have been unable to locate the specifications for these panels in the project specifications. Please provide specifications for the lanced metal soffit panels.
Inquiry submitted 01/24/2022

Response #1:(BI#24)-Refer to Addendum No. 1 dated January 28, 2022. Section 99-07410 METAL ROOF AND SIDING of the Special Provisions has been revised.

Response posted 01/24/2022




Inquiry #25: 1. Access Control and Intrusion must be integrated into the Departments Security management System – what is that system?
2. What is the preferred Access Control and Intrusion systems for Caltrans?
3. Confirming Caltrans is providing and installing all Network Switches, Wireless Access Points, UPS’s, and workstations?

Inquiry submitted 01/25/2022

Response #1:(BI#25)-1.Access control and intrusion detection systems are stand alone. The Department has no integrated system. Please refer to Addendum No. 1 dated January 28, 2022; section 99-281000 - ACCESS CONTROL SYSTEMS (ACS) of the Special Provisions has been revised.
2.Access control and detection intrusion systems must meet the requirements of the plans and specifications. Submit equipment cutsheets and shop drawings for approval after contract award.
3.There is no UPS. Workstations are not part of contract. Please refer to Addendum No. 1 dated January 28, 2022; plan sheets EE-2.10 and EE-3.00 have been revised.

Response posted 01/25/2022




Inquiry #26: Drawing A1-11 detail F does not show the rigid insulation on the framed in 12"/12" crickets (wall support)under the eyebrow vent but is noted to include it. The drawing also shows batt insulation under the wood framed crickets. With the batt insulation under the wood framed cricket there wouldn't be a need to add rigid insulation on top of the framed cricket. Can you please clarify if the rigid insulation is required on the upper part of the framed cricket.
Inquiry submitted 01/25/2022

Response #1:(BI#26)-For A1-11 detail F, rigid insulation is along entire parapet slope as shown. Please bid per current contract documents.

Response posted 01/25/2022




Inquiry #27: Interior elevation A1-16 has wall base as 6” and A7-04 shows 4” please clarify want is wanted.
Inquiry submitted 01/25/2022

Response #1:(BI#27)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-04 has been revised.
Response posted 01/25/2022




Inquiry #28: Will the answers to all of these Pre-Bid RFI's be posted to the Builders' Exchange, and if so, when?


Inquiry submitted 01/26/2022

Response #1:(BI#28)-Please refer to the Notice to Bidders for the website where bidder inquiries and responses are posted

Response posted 01/26/2022




Inquiry #29: Wall Types W-1 and W-2 on Finish Schedule A7-01 simply call for “Gypsum Board Painted” and Wall Types W-4 and W-5 call for “Water Resistant Gypsum Board”. However, Materials Section 99-0-250B(3) in the drywall specs list Water Resistant Gyp Bd only. Are we to assume that ALL gyp bd in the entire project is to be Water Resistant Gyp?
Inquiry submitted 01/26/2022

Response #1:(BI#29)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-01 has been revised; wall types W-1 and W-2 are to be water resistant gypsum board.



Response posted 01/26/2022




Inquiry #30: Interior Wood Paneling and Wood Trims (Interior Elevations and Finish Carpentry Spec.)
There does not seem to be a specific detail or size given for the running trim at interior paneling. Can a specific size be given? Also, there is no trims called out at outside or inside corners. Is the intent to provide trims at all inside and outside corners? Please provide specific sizes and or details. Finishes to be per W3 on Finish Schedule

Inquiry submitted 01/27/2022

Response #1:(BI#30)-Refer to Addendum No. 1 dated January 28, 2022. Plan sheet A7-01 has been revised.

Response posted 01/27/2022




Inquiry #31: Plan sheet EE-1.11, Indoor Lighting Fixture Schedule indicates to provide Alternate costs for the Lighting fixtures. How are we to identify the Alternates in our bid?
Inquiry submitted 01/27/2022

Response #1:(BI#31)-Provide either Alt #1, Alt #2, or equal.



Response posted 01/27/2022




Inquiry #32: Sheet EE-2.10 calls out a push button door operator for the overhead door in room 209. I have been unable to locate a spec for the door operator in the project specifications. Please provide door operator specifications and a list of overhead doors that require electric operators.
Inquiry submitted 01/27/2022

Response #1:(BI#32)-The overhead door in room 209 is the only overhead door that requires an electric operator as shown on plan sheet EE-2.10. Provide submittals for approval after contract award. Please bid per the current contract documents.

Response posted 01/27/2022




Inquiry #33: There are about 20 unanswered pre-bid RFI's to date, that are critical to bidding this project properly. This project bids in less than a week, should we request a bid extension or will all of these be answered in adequate time to properly bid?
Inquiry submitted 01/27/2022

Response #1:(BI#33)-Your attention is directed to Addendum #1 posted January 28, 2022 which provides responses to the approximate “20 unanswered pre-bid RFI’s.

Response posted 01/27/2022




Inquiry #34: Section 7-1.06B, Item 3 states that all insurance must be with an insurance company with an AM best Financial Strength Rating of A- or better and a Financial Size Category of VII or better. Contractor's Construction Workers Compensation coverage is through State Fund, which is not rated by AM Best. Please confirm this is acceptable and compliant and would be approved by Caltrans to allow the contractor to submit their proposal.

· Contractor's current ROM estimate is $11.7M. Section 7-1.06D(2) states that bids totaling $10M to $25M require a $2M/$4M for GL with $15M in Umbrella/Excess Liability limits. Contractor currently maintains a $1M/$2M for GL with a $10M Umbrella. Increasing the primary GL limits to $2M/$4M will be costly and subject to the carrier’s approval. It may be more cost effective to place a 2nd Excess Liability policy over the existing program to satisfy the total limit requirements ($17M/$19M). To meet this limit requirement, we would need to place a $7M Excess. Please confirm this is acceptable and compliant and this would be approved by Caltrans to allow the contractor to submit their proposal?

· Section 7-1.06E(2) states that the $15M Umbrella/Excess Liability requirement stipulated in Section 7-1.06D(2) also applies to Auto Liability. Per the comments above, the contractor currently maintains a $10M Umbrella so we would need to place a 2nd Excess Liability policy over our existing program to meet this requirement. Please confirm if this would be required, if so, and if this requirement was to be met, would the contractor be approved and would Caltrans allow the contractor to submit our proposal?

Inquiry submitted 01/27/2022

Response #1:(BI#34)-There will be no change to insurance requirements in section 7-1.06 of the Revised Standard Specifications dated 10-15-21.

Response posted 01/28/2022




Inquiry #35: Plan sheet A1-19, Interior Elevation 5 Mech/Elec Room 2 (212) call for finished exposed plywood. Does this plywood need to be Fire Treated?
Inquiry submitted 01/27/2022

Response #1:(BI#35)-The plywood paneling shown in detail 5 on plan sheet A1-19 does not need to be fire treated. Please bid per the current contract documents.
Response posted 01/28/2022




Inquiry #36: Plan sheet A2-01 1 Floor Plan indicates casework installed in 301 Nuclear Storage Room.
Plan sheet A1-20, Interior Elevations for this space does not show any. How are we to proceed in these locations?

Inquiry submitted 01/27/2022

Response #1:(BI#36)-No casework per plan sheet A1-20.

Response posted 01/28/2022




Inquiry #37: Plan sheet A7-05, Details 4, 5, and 6 indicate a depressed slab for the mortar bed in the Tiled Restrooms. The structural drawings do not represent this condition. How are we to proceed at these locations?
Inquiry submitted 01/27/2022

Response #1:(BI#37)-Follow details 4, 5, and 6 on plan sheet A7-05 for dropped slab in tiled restrooms. Refer to detail 6 on plan sheet ST-2 for similar dropped slab details.

Response posted 01/28/2022




Inquiry #38: Regarding responses to contractors inquiries and Cal Trans' statement of 5 days being needed to properly respond as stated in BI # 19.:
"Response #1:(BI#37)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents." This is one sided and is improper.
I see 18 unanswered question posted on or before Jan 26. All within the requisite 5 days prior to bid. Many more since.
Now while some of these BI's may be answered in your Addendum 1; we are only given 3 days to digest, price check, recalculate and properly execute a bid. Not a great start to a working relationship.

Inquiry submitted 01/28/2022

Response #1:(BI#38)-Refer to Addendum #2, dated February 1, 2022.

Response posted 01/29/2022




Inquiry #39: There seems to be multiple unanswered Pre-Bid RFI's not answered in Addendum 01. Will there be an Addendum 02?
Inquiry submitted 01/31/2022

Response #1:(BI#39)-Refer to Addendum #2, dated February 1, 2022.

Response posted 01/31/2022




Inquiry #40: Question:
Would Cal Trans consider changing the bid form to lump sum bid?
Considerations:
1. The project is more similar to an building structure project than a roadway project.
2. There are 96 bid items listed for this project. Some are fairly straight forward but others are vague in description. An example may be 2" domestic water and 6" fire water utilities. These are not listed on the bid form. Do these two items go in the building lump sum?
Please consider revising the bid form to lump sum or clarifying site items not listed.

Inquiry submitted 02/02/2022

Response #1:(BI#40)-There will be no change in the bid item list. Unless otherwise noted, the work shown on the Building plans is included in the building lump sum and covered under section 99 of the Special Provisions. Please bid per the current contract documents.
Response posted 02/02/2022




Inquiry #41: We received a notification from our engineered Floor Joist product supplier stating that the 24" deep roof trusses at 48" o.c., seem to be overloaded as shown on sheet ST1-3.
Can this be reviewed please?
At this time product quotes are based on the following:
1. 32" deep roof trusses at 48" o.c. (quote based on)
2. 24" deep roof trusses at 32" o.c. (additional cost quoted)

Inquiry submitted 02/02/2022

Response #1:(BI#41)-Refer to Addendum #3, dated February 10, 2022.

Response posted 02/02/2022




Inquiry #42: CONFLICTS OR CONCERNS:
1. No specified manufacturer or model numbers provided for products shown
2. Toilet Tissue Dispenser (Specified/ Not Shown)
3. Sanitary Napkin Disposal (Specified/Not Shown)
4. Paper Towel Dispenser (Specified/Not Shown)
5. Waste Receptacle (Specified/Not Shown)
6. ASI Stainless Steel Soap Dispenser and Shelf (Specified/Not Shown)

Bidding as "Bobrick" - standard/typical

Inquiry submitted 02/02/2022

Response #1:(BI#42)-Manufacturers or model numbers are not provided. Refer to section 99-10801 TOILET AND SHOWER ACCESSORIES of the Special Provisions for requirements.



Response posted 02/02/2022




Inquiry #43: Regarding roofing and wall panel, please provide manufacturer and product to be used on the project.
Inquiry submitted 02/02/2022

Response #1:(BI#43)-Manufacturers and product numbers are not provided for roofing and wall panels. Refer to section 99 of the Special Provisions for requirements.

Response posted 02/02/2022




Inquiry #44: 1. AD #3 Is the 180 days part of the 230 work days?
2. Will Caltrans pay for material on hand after material submits have been approved?

Inquiry submitted 02/10/2022

Response #1:(BI#44)-1.The 180 days is the maximum delayed start from Contract Approval to the first working day. It is separate from the working days required for this contract.
2.Material on hand payments are allowed as stated in section 9-1.16 of the revised standard specifications.

Response posted 02/10/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.