Viewing inquiries for 01-0E0004

Submit new inquiry for this project


Inquiry #1: There is no apparent Bid Item for clear and grubbing or tree removal, that's required for the detour area. In which Bid Item(s) will that effort be compensated?
Inquiry submitted 12/06/2019

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 12/06/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Thursday, December 30, 2019. Please bid per the current contract documents.
Response posted 12/30/2019




Inquiry #2: On sheet 514 of 522, under Informational Quantities, it states that the reinforcement be epoxy coated. Is this Green (A775), or Purple (A934).
Inquiry submitted 12/06/2019

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 12/06/2019


Response #2:
Reference is directed to section 52-2.03A(1) of the special provisions, "Epoxy coat all reinforcement, except the reinforcement inside the CISS piling and median abutment backwalls, at the following locations: 1. Bridge No. 04-0313L 2. Bridge No. 04-0024R 3. Bridge No. 04-0023R". Section 52-2.03A(1) specifies epoxy-coated prefabricated reinforcement (purple, ASTM A934).
Response posted 12/09/2019




Inquiry #3: Item 45 Plant establishment period, Lump Sum. There are no days listed as to how many days for this period, in the notice to bidders.
Please clarify this . Thank you

Inquiry submitted 12/09/2019

Response #1:
(#3)-Your inquiry has been received and is being reviewed.
Response posted 12/09/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Thursday, December 12, 2019. Please bid per the current contract documents.
Response posted 12/20/2019




Inquiry #4: According to the ADL Site investigation Report and Section 14-11.08, preparation of the sub-grade for the detour embankment will encounter the same ADL-Type Z-2 soil designated in the Structure Excavation Item #38. How will the disposal of the Z-2 soil found outside of the structure excavation paylines be paid?
Inquiry submitted 12/10/2019

Response #1:
(#4)-Your inquiry has been received and is being reviewed.
Response posted 12/11/2019


Response #2:
Please bid per the current contract documents.
Response posted 12/30/2019




Inquiry #5: In bid inquiry #2, you have stated that the rebar be purple (A934). Purple rebar is not intended to be bent or rebent. On sheet 68 of 71, note 2 it states the stirrups may be bent in the field to match the cross slope. Can we use green epoxy (A775) for these stirrups?
Inquiry submitted 12/10/2019

Response #1:
(#5)-Your inquiry has been received and is being reviewed.
Response posted 12/11/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Thursday, December 30, 2019. Please bid per the current contract documents.
Response posted 12/30/2019




Inquiry #6: Addendum # 1 addressed Plant establishment period. " The Bidder must submit its bid with a minimum price for plant establishment work." See section 2-1.09 Which states : Submit a bid based on the item quantities shown on the bid item list. ITEM 45 PLANT ESTABLISHMENT WORK LS LUMP SUM has no quantities, such as DAYS. How many days / QUANTITIES is this period for? We can submit a bid once we have quantities to base the bid on! Key word for this Item is PERIOD/ time frame .
Inquiry submitted 12/10/2019

Response #1:
(#6)-Your inquiry has been received and is being reviewed.
Response posted 12/11/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Thursday, December 12, 2019. Please bid per the current contract documents.
Response posted 12/20/2019




Inquiry #7: On Page 7 of 17 of the Project Drawings, it states "Minimum 3'-0"" Casing and shows Inside Diameter. However the indicator lines on the Drawing illustrate that it should be the Outside Diameter. Please confirm the required Steel Casing should be 36" Outside Diameter, or state what or provide the required Outside Diameter.
Inquiry submitted 12/11/2019

Response #1:
(#7)-Unless an Addendum is issued, please bid per current contract documents.
Response posted 12/11/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Thursday, December 30, 2019. Please bid per the current contract documents.
Response posted 12/30/2019




Inquiry #8: Section 14-6.03D(1) of the Special Provisions requires that the Contractor Supplied Biologist "inspect and document the ESA's and ESA fence daily...." . Can you please confirm that the quantity of 30 days is correct for Bid Item 29 Contractor Supplied Biologist?
Inquiry submitted 12/11/2019

Response #1:
(#8)-Your inquiry has been received and is being reviewed.
Response posted 12/11/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Thursday, December 12, 2019. Please bid per the current contract documents.
Response posted 12/20/2019




Inquiry #9: Sheet Q-1 refers to Sheet SCQ-1 for the 10 CY of Remove Base and Surfacing Item. SQC-1 doesn't include the Item, nor can we determine where the removal is to occur on any of the Stage Construction drawings. Can you please clarify where the Remove Base and Surfacing Item occurs?
Inquiry submitted 12/12/2019

Response #1:
(#9)-Your inquiry has been received and is being reviewed.
Response posted 12/12/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Thursday, December 30, 2019. Please bid per the current contract documents.
Response posted 12/30/2019




Inquiry #10: On Jacoby Creek Bridge (Left)(Replace), we are unable to determine how the 4" future conduit is to be connected to the installed conduit beneath the approach slabs and back wall once the superstructure has been slid into its final position. Can you please provide a detail of the 4" conduit connection through the backwall?
Inquiry submitted 12/26/2019

Response #1:
(#10)-Your inquiry has been received and is being reviewed.
Response posted 12/27/2019


Response #2:
Please bid per the current contract documents.
Response posted 01/06/2020




Inquiry #11: Please clarify stage approach to paving: the stations for stages 2 and 3 seem to overlap.
Inquiry submitted 12/31/2019

Response #1:
(#11)-Your inquiry has been received and is being reviewed.
Response posted 01/03/2020


Response #2:
Please bid per the current contract documents.
Response posted 01/07/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.