Inquiry #1: There are a lot of trees that needs to be removed and none are shown on the plans or has been mentioned for the removal on the special provisions. There are no bid item for tree removal and it is not clear to us if Caltrans is removing these trees or the contractor? Please provide information about the numbers, types & sizes of each tree if contractor is responsible for this work In the IH handout page 120 of the 141 OF IH booklet this paragraph explains the tree removal work:
"Upland Trees: Approximately 115 upland trees are expected to be removed on the
westbound side of SR 20 to attain the additional road width required for the project
objective. These trees include coast redwood (Sequoia sempervirens), Douglas-fir
(Pseudotsuga menziesii) and California bay laurel (Umbellularia californica)."

Inquiry submitted 09/06/2019

Response #1:
(#1)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.
Response posted 09/09/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, September 13, 2019. Please bid per the current contract documents.
Response posted 09/13/2019




Inquiry #2: In reference to the tree removals, we are getting information there is up to 3 weeks of tree and stump removal prior to starting any excavation or grading. This seems to make the 45 maximum number of working days not enough time to build the project. Will Caltrans increase the allowable maximum number of days to something more reasonable given the time restrictions on the trees and drainages?
Inquiry submitted 09/12/2019

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 09/12/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, September 13, 2019. Please bid per the current contract documents.
Response posted 09/13/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.