Submit new inquiry for this projectInquiry #1: Did cal-trans intentionally leave out the new pavement markers on this project? There is an item to remove 76,700 existing markers but no item to install new RPMs. Also is there any traffic contrast stripe black paint on this project or not?
Inquiry submitted 01/31/2018
Response #1:Your inquiry has been received and is being reviewed.
Response posted 01/31/2018
Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Monday, February 5, 2018.
Please bid per the current contract documents.
Response posted 02/06/2018
Inquiry #2: In the Expedite Bid, the Additional Subcontractor List #2 and #3 show up as Red Folders when nothing has been typed within those fields. Please advise if I will be able to submit a bid if these folders continue to show as red.
Inquiry submitted 02/14/2018
Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 02/14/2018
Response #2:
Yes, you will be able to submit your bid if the Subcontractor List #2 and #3 are red.
Response posted 02/14/2018
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.