Inquiry #1: With the resent Camp Fire in the area, will this job still be bidding on 1/8/19?
Inquiry submitted 12/18/2018

Response #1:
(#1)-Bids will be opened as scheduled.
Response posted 12/18/2018




Inquiry #2: The plans call for the Alternative In-Line Terminals (item 112) to be stained under item 93 Stain Galvanized Surfaces. The terminal systems are proprietary items and the manufacturers will not approve that stain on the terminals. How should we bid this item?
Inquiry submitted 12/19/2018

Response #1:
(#2)-Please bid per the current contract documents.
Response posted 12/20/2018




Inquiry #3: SP 12-3.32C Indicates PCMS locations as shown and in advance of the first warning sign.

Sheet 29 shows 4 PCMS signs. Are 2 additional PCMS signs required in advance of sign A for a total of 6 EA?

Inquiry submitted 12/26/2018

Response #1:
(#3)-Your inquiry has been received and is being reviewed.


Response posted 12/27/2018


Response #2:
Please bid per the current contract documents.
Response posted 01/03/2019




Inquiry #4: Sheet No. 111 of 120 calls out 3/8x4 stiffeners at the HP12 beams. Section A-A on Sheet No. 115 of 120 calls out x4 stiffeners. Which is correct?
Inquiry submitted 12/28/2018

Response #1:
(#4)-Your inquiry has been received and is being reviewed.
Response posted 12/31/2018


Response #2:
Please refer to Section 5-1.02 Contract Components, point 3 Detail drawing governs over a general drawing. The correct dimension for the stiffeners at the HP12 beams is x 4, as shown in Section A-A on Sheet No. 115 of 120.
Response posted 01/03/2019




Inquiry #5: Ref. Special Provision Section 48-6.02B(3) Structural Steel; As this is a temporary bridge, does Standard Specification Section 6-3.05B Source Inspection Expense Deductions apply to this project?
Inquiry submitted 12/28/2018

Response #1:
(#5)-Your inquiry has been received and is being reviewed.
Response posted 12/31/2018


Response #2:
Yes. Source inspection is required for Structural Steel components of the temporary bridge.

Response posted 01/03/2019




Inquiry #6: The D1 line leaves the M1 line as it ramps down to the temporary bridge. A portion of the existing M1 line is removed for the detour excavation item. There does not appear to be a quantity on Q1 or SCQ1 to account for the embankment necessary to reconstruct the portion of the M1 line removed by the detour excavation.

1. Please provide this embankment quantity.
2. Please specify what item should include this cost.

Thank you

Inquiry submitted 01/02/2019

Response #1:
(#6)-
1. Please refer to the second paragraph of section 16-1.03.
2. Please refer to section 19-2.04. Embankment is included in the various items of Roadway Excavation.
Response posted 01/03/2019




Inquiry #7: Please provide the SMARA published mine/quarry name(s) and location(s) for the rock source that meets the specified materials listed under special provision 72-2.02.
Inquiry submitted 01/03/2019

Response #1:
(#7)-The Department does not provide this information. Please refer to section 5-1.01 and section 6-1.03.
Response posted 01/04/2019




Inquiry #8: Please provide the final grading plan for Item 37, Roadway Excavation (Detour Removal).
Inquiry submitted 01/03/2019

Response #1:
(#8)-There is no grading plan specific to this item. Please refer to section 16-1.03.
Response posted 01/04/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.