Viewing inquiries for 02-0J1604

Submit new inquiry for this project


Inquiry #1: Does the Stress Absorbing Membrane Interlayer go between the existing asphalt and the Hot Mix Asphalt Leveling Course? Or is it between the leveling course and the HMA Type A?
Inquiry submitted 01/07/2020

Response #1:
(#1)-The Stress Absorbing Membrane Interlayer (SAMI) is placed between the Leveling Course and the HMA (Type A). Bidder's attention is directed to plan sheet X-1 (Typical Cross Sections), C-1 (Construction Details), and C-2 (Construction Details).
Response posted 01/08/2020




Inquiry #2: Would the state consider changing standard specification 37-2.05A General Section 37-2.05 includes specifications for placing stress absorbing membrane interlayers (SAMI). Comply with section 37-2.04 except a flush coat is not required. Traffic must not be allowed on a SAMI
Inquiry submitted 01/08/2020

Response #1:
(#2)- Your attention is directed to Special Provisions Section 37-2.05. Please bid per current contract documents.
Response posted 01/08/2020




Inquiry #3: Based on the pavement thickness of the bid items for: Replace Asphalt Concrete Surface(0.25), HMA Type A(0.15), and HMA Leveling(0.04). The standard specifications will require the contractor to create and verify 3 different mix designs. In lieu of doing this would it be acceptable to use the Mix design from the Type A in the Replace Asphalt Concrete Surface Bid item, or will we be required to create a 3/4" mix design for such a small quantity.
Inquiry submitted 01/15/2020

Response #1:
(#3)-Please bid per the current contract documents.
Response posted 01/16/2020




Inquiry #4: 39-2.01A(4)(i)(iii)(C) Acceptance Criteria using Percent Improvement and determining the target MRI for Smoothness Acceptance. The NB lane average MRI is a 205.20 in/mi. and the SB lane average MRI is a 208.61 in/mi.. With leveling and chip seal not being an opportunity for smoothness, how does the state propose a contractor to achieve a 53% improvement by 1 single 0.15’ lift of asphalt? With normal paving practices, this is not possible without accruing 400k in diamond grinding and smoothness dis-incentives.
In addition, the road falls into a canyon from mile post 5.0 to 8.3 and is very twisting and curvy. Smoothness may or may not be achievable without the curve radius data that has not been provided for this contact. Is it safe to assume the IRI smoothness specification will be waived from MP 5.0 to 8.3.

Inquiry submitted 01/27/2020

Response #1:
(#4)-Your inquiry has been received and is being reviewed.
Response posted 01/27/2020


Response #2:
Please bid per the current contract documents.
Response posted 01/28/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.