Viewing inquiries for 02-1H5704

Submit new inquiry for this project


Inquiry #1: Bid Item 137 THERMOPLASTIC PAVEMENT MARKING (ENHANCED WET NIGHT VISIBILITY) (RECESSED)- Plan Sheets PDQ-1 through PDQ-3 reference notes within the descriptions/comments that refer to the "NOTES:" on PDQ-1. These notes reference different item #'s that correspond to crosswalks, limit lines, legends & symbols which all fall under bid item 137. Caltrans only has a specification & detail for recessing crosswalks & limit lines only and does not have a detail or specification for recessing legends & symbols. Are the legends & symbols also being recessed or just the limit lines and crosswalk bars? If the Legends & symbols are also being recessed can Caltrans please provide a detail on how to perform that work? As there is no viable equipment on the market to recess word legends or arrow symbols or bike symbols. Also if the word legends or arrow symbols or bike symbols are not being recessed will Caltrans please consider adding an additional line item for NON-RECESSED EWNV MARKINGS?
Inquiry submitted 09/30/2022

Response #1:(BI#1)-Your inquiry has been received and is being reviewed.

Response posted 10/03/2022


Response #2:(BI#1)-Refer to Addendum #1, dated October 25, 2022.

Response posted 10/25/2022




Inquiry #2: Bid Item #30 - Roadway Excavation lists the bid quantity as 340 CY. This quantity appears to only include the Roadway Excavation at station "A" 43+98 - "A" 44+81.

Sheets C-1 through C-32 list Roadway Excavation at every curb ramp, driveway and spandrel.

What is the pay mechanism for the Roadway Excavation at location listed on sheets C-1 through C-32?

Inquiry submitted 10/04/2022

Response #1:(BI#2)-Your inquiry has been received and is being reviewed.

Response posted 10/04/2022


Response #2:(BI#2)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #3: What is the depth of Roadway Excavation at the areas listed on C-1 through C-32?

What is the section of Class II AB and HMA to be placed at these same areas?

The current bid quantities do not appear to include quantities for Roadway Excavation, Class II AB or HMA in these areas.



Inquiry submitted 10/04/2022

Response #1:(BI#3)-Your inquiry has been received and is being reviewed.

Response posted 10/04/2022


Response #2:(BI#3)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #4: Is there a GeoReport for the box culvert area for shoring the highway?
Inquiry submitted 10/10/2022

Response #1:(BI#4)-Your inquiry has been received and is being reviewed.

Response posted 10/10/2022


Response #2:(BI#4)-There is a Soil Evaluation Report provided for Trenchless Culvert Replacement in the Information Handout. The Department doesn’t anticipate shoring for box culvert work
for project 02-1H5704. The contractor may be confusing this project with 02-0H5704

Response posted 10/11/2022




Inquiry #5: Can the AASTHO M326 pipeliner that conforms to DIB 83-4 per section 71-3-09 be used in place of 22" Welded steel pipeliner, bid item 0092?
Inquiry submitted 10/13/2022

Response #1:(BI#5)-Your inquiry has been received and is being reviewed.

Response posted 10/13/2022


Response #2:(BI#5)-The successful bidder may propose substitutes under section 4-1.07 VALUE ENGINEERING of the Standard Specifications. Please bid per the current contract documents.

Response posted 10/14/2022




Inquiry #6: Based on the Plan Takeoff of about 40,000 Square Yards for the Stress Absorbing Membrane Interlayer, Bid Items 35,36,37, and 38 do not have enough quantity to complete the work.

The quantities should be close to these below based on the SY and Specification requirements for the SAMI:

35 - Sand Cover - 80 tons
36 - Asphalt Rubber Binder - 92 tons
37 - Asphaltic Emulsion (Flush Coat) - 10 tons
38 - Precoated Aggregate (Seal Coat) - 650 tons

Please clarify.

Inquiry submitted 10/14/2022

Response #1:(BI#6)-Your inquiry has been received and is being reviewed.

Response posted 10/14/2022


Response #2:(BI#6)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #7: For the 22" Welded Steel Pipeliner at drainage system 68.71, does the department require the contractor to install pressurized grout between the existing 24" culvert and the outside of the 22" Welded Steel Pipeliner? If this is the case, is there an item and quantity for the pressurized grout?
Inquiry submitted 10/14/2022

Response #1:(BI#7)-Your inquiry has been received and is being reviewed.

Response posted 10/14/2022


Response #2:(BI#7)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #8: The quantities for minor concrete (minor structure) do not match between the special provisions and the drainage quantity sheets. Please advise.
Inquiry submitted 10/14/2022

Response #1:(BI#8)-Your inquiry has been received and is being reviewed.

Response posted 10/14/2022


Response #2:(BI#8)-The total quantity for minor concrete (minor structure) of 3.1 CY comprises 1.2 CY from the drainage quantity sheets and 1.9 CY from the roadway quantities table on sheet Q-2. Bid per current bid documents.
Response posted 10/14/2022




Inquiry #9: Bid Item 137 THERMOPLASTIC PAVEMENT MARKING (ENHANCED WET NIGHT VISIBILITY) (RECESSED). the bid item quantity of 10,700 SF seems to be double what's shown on plan sheets PD-1 through PD 48. (Example PDQ-3 lines 1 & 2 shows that there is 1,775 SF to be installed on plan sheet PD-35; however, PD-35 only shows the following: 5-each Bike Symbols w/Arrows total 52.5 SF, 3-each Left Arrows total 45 SF, 2-each Bike Loop Detectors total 4 SF and 200 SF of Crosswalks. The total of all SF being installed on PD-35 is 301.5 SF which 1, 473.5 SF less than that shown on PDQ-3.) Can Caltrans please double check the pavement marking quantities for bid item 137? As there is not 10,700 SF shown on these current plan sheets.
Inquiry submitted 10/18/2022

Response #1:(BI#9)-Your inquiry has been received and is being reviewed.

Response posted 10/18/2022


Response #2:(BI#9)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #10: The plans for this project call for a Stress Absorbing Membrane Interlayer (SAMI). Per Section 37-2.05A:
Section 37-2.05 includes specifications for placing stress absorbing membrane interlayers (SAMI).
Comply with section 37-2.04 except a flush coat is not required.
Traffic must not be allowed on a SAMI.

Question: Will Traffic be allowed on the SAMI since the quantities include a Flush Coat (Items 35 and 37) or should these items be removed from the Bid List?

Inquiry submitted 10/18/2022

Response #1:(BI#10)-Your inquiry has been received and is being reviewed.

Response posted 10/18/2022


Response #2:(BI#10)-Refer to Addendum #1, dated October 25, 2022.
Response posted 10/25/2022




Inquiry #11: When does Caltrans expect to answer all the questions?
Inquiry submitted 10/25/2022

Response #1:(BI#11)-Your inquiry has been received and is being reviewed.

Response posted 10/25/2022




Inquiry #12: Can you confirm that the quantities for Items: 15 - Rain Event Action Plan, 16 - Storm Water Sampling and Analysis Day, and 17 - Storm Water Annual Report are correct? The bid quantities seem excessive for a project that is to be completed within 130 working days.
Inquiry submitted 10/25/2022

Response #1:(BI#12)-Your inquiry has been received and is being reviewed.

Response posted 10/25/2022


Response #2:(BI#12)-Refer to Addendum #2, dated October 27, 2022.
Response posted 10/27/2022




Inquiry #13: Typical Cross Section Sheets X-1 & X-3 show the location of the 12" PPP Underdrain located under the edge of pavement. The Underdrain Backfill Detail on Sheet DD-11 shows the underdrain trench capped with 0.45' of Shoulder Backing. Please clarify if the underdrain will be located under the edge of pavement or outside the edge of pavement in the shoulder.
Inquiry submitted 10/25/2022

Response #1:(BI#13)-Your inquiry has been received and is being reviewed.

Response posted 10/25/2022


Response #2:(BI#13)-The 0.45’ of shoulder backing is for areas where the underdrain is outside the edge of pavement. Please bid per the current contract documents.
Response posted 10/26/2022




Inquiry #14: Regarding Roadway Excavation, HMA, and Class 2 AB Quantities.

There is still quantity missing or not accounted for. For example, the concrete sidewalk, curb and gutter from approximately station 421+80 to 430+56 (Lt). Addendum Number 1 does not appear to contain a quantity for Roadway Excavation or HMA for all the curb, gutter and sidewalk in this area. It appears the quantities are only given for the the areas shown on the Construction Details.

Furthermore, the Class 2 AB quantities are not correct. For example, the base section under the concrete is 0.5'. The sidewalk section is 0.33'. Yet the base quantity is exactly the same as the concrete sidewalk quantity. The base quantity should be more because there is base under the curb, gutter, and sidewalk and the section is thicker.

Will the state please review their quantities again?

Inquiry submitted 10/26/2022

Response #1:(BI#14)-Your inquiry has been received and is being reviewed.

Response posted 10/26/2022


Response #2:(BI#14)-An addendum will be forthcoming to address this inquiry.
Response posted 10/27/2022


Response #3:(BI#14)-Refer to Addendum #6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #15: Sheet E-1 Note 6
Indicates the contractor is to install a Non Invasive Pavement Sensor, the special provisions do not have a section for the sensor.
Is the sensor to be furnished by the contractor or is this to be furnished by Cal Trans?

Inquiry submitted 10/27/2022

Response #1:(BI#15)-Your inquiry has been received and is being reviewed.

Response posted 10/27/2022


Response #2:(BI#15)-Please refer to section 6-1.02 of the special provisions.
Response posted 10/27/2022




Inquiry #16: The bid spec call out for a GlenMartin Tower,this manufacturer is no longer in business.
Please advise if a Great Plains Tower DT-MHLT3012.

Inquiry submitted 10/27/2022

Response #1:(BI#16)-Your inquiry has been received and is being reviewed.

Response posted 10/27/2022


Response #2:(BI#16)-Please see addendum#6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #17: Sheet ED-2
Please confirm the air temp/relative humidity sensor is contractor furnished.
If so please provide specifications.

Inquiry submitted 10/27/2022

Response #1:(BI#17)-Your inquiry has been received and is being reviewed.

Response posted 10/27/2022


Response #2:(BI#17)-Refer to Addendum #8, dated December 7, 2022.
Response posted 12/08/2022




Inquiry #18: On Sheets L-29 to L-39 there are multiple locations listed as Place Hot Mix Asphalt (Miscellaneous Area), the current bid quantity does not seem to include these areas.

Will the placement in these areas be paid as Place Hot Mix Asphalt (Miscellaneous Area) as shown on the plans, or will the areas only be paid as Hot Mix Asphalt (Type A)?

Inquiry submitted 10/29/2022

Response #1:(BI#18)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted, please bid per the current contract documents.

Response posted 10/31/2022


Response #2:(BI#18)-Please see addendum#6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #19: Based on the plan takeoff, the current bid quantity for Cold Plane Asphalt Concrete Pavement does not include the conforms for driveways/road connections throughout the project. Please advise.
Inquiry submitted 10/30/2022

Response #1:(BI#19)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted, please bid per the current contract documents.

Response posted 10/31/2022


Response #2:(BI#19)-Please see addendum#6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #20: Item #139, 140, and 141
Is Type 1 or Type 3 conduit to be installed in the controller cabinet and nips tower foundations?

Inquiry submitted 11/09/2022

Response #1:(BI#20)-Your inquiry has been received and is being reviewed.

Response posted 11/09/2022


Response #2:(BI#20)-Please see addendum#6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #21: The Department's response to inquiry #14 states "An addendum will be forthcoming to address this inquiry", to date an addendum has not been issued. Furthermore, there are multiple questions that have not been answered sufficiently.

Does the Department anticipate issuing an addendum soon or will the bid date be postponed again?

Inquiry submitted 11/10/2022

Response #1:(BI#21)-Your inquiry has been received and is being reviewed.
Response posted 11/10/2022


Response #2:(BI#21)-Please see addendum#6, dated November 29, 2022.
Response posted 11/30/2022




Inquiry #22: The CA High Design Manual Section 850-34 dated December 30th, 2015 warns against specifying plastic pipe in areas with a potential for fire. This project lists Alternative Pipe Culvert in the Bid Schedule. Will Caltrans still allow for plastic pipe to be used on this project?
Inquiry submitted 12/05/2022

Response #1:(BI#22)-Your inquiry has been received and is being reviewed.
Response posted 12/06/2022


Response #2:(BI#22)-Please select Alternative Pipes per the table on Drainage Quantities sheet DQ-6. Plastic Pipe is not listed as an alternative.
Response posted 12/06/2022




Inquiry #23: The post miles listed on lane closure Chart K2 appear to be incorrect.

Is chart K2 meant to address the multilane portion in Burney as indicated in the closure limit description?



Inquiry submitted 12/05/2022

Response #1:(BI#23)-Your inquiry has been received and is being reviewed.
Response posted 12/06/2022


Response #2:(BI#23)-Due to the short time period before bid opening next week there may not be time to respond to this inquiry.
If no additional response is posted, please bid per the current contract documents

Response posted 12/09/2022




Inquiry #24: Addendum #1 updated the bid quantity for item 30 roadway excavation from 340 cy to 550 cy. Addendum #6 continues to list the same bid quantity of 550 cy on the bid item list, however quantity sheet Q-1 updated per addendum #6 shows a new quantity roadway excavation at 638 cy.

What quantity should potential bidders use to accurately price the work?

Inquiry submitted 12/08/2022

Response #1:(BI#24)-Your inquiry has been received and is being reviewed.
Response posted 12/08/2022


Response #2:(BI#24)-Due to the short time period before bid opening next week there may not be time to respond to this inquiry.
If no additional response is posted, please bid per the current contract documents

Response posted 12/09/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.