Viewing inquiries for 02-1J4604

Submit new inquiry for this project


Inquiry #1: Will the emergency project within the location 1 limits be completed prior to the beginning of this project?
Inquiry submitted 11/23/2020

Response #1:
(BI#1)-Your inquiry has been received and is being reviewed.

Response posted 11/24/2020


Response #2:
(BI#1)-We anticipate the emergency work within the Location 1 limits will be completed. Bid per current contract documents.
Response posted 11/25/2020




Inquiry #2: There are a total of 82 MRI segments above a 135 MRI, and Cal Trans design for FULL WIDTH SEGMENT CORRECTION AND PARTIAL WIDTH SEGMENT CORRECTION only addresses 31 of them .

Does Cal Trans think the following design for SEGMENT CORRECTIONS in the bid item list along with the 4 foot wide pavement failure area repairs is sufficient enough to meet the Specifications for MRI and Area of Localized roughness ?

Will Cal Trans be adding anymore SEGMENT corrections to address smoothness concerns?

Inquiry submitted 11/30/2020

Response #1:
(BI#2)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.

Response posted 11/30/2020


Response #2:(BI#2)-For Smoothness acceptance and payment adjustments on segments without bid item correction treatment the Bidder's attention is directed to Section 39-2.01A(4)(i)(iii)(C) Acceptance Criteria using Percent Improvement of the project Special Provisions.
Response posted 12/02/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.