Viewing inquiries for 02-1J8304

Submit new inquiry for this project


Inquiry #1: Traffic Chart K5 requires 24/7 continuous flagging from 3-1-2023 until 8-1-2023 (or for however long Stages 1 and 2 last).

There are no bid items for a temporary signal system. AFADs require personnel on-site to operate.

Will a temporary portable signal system be allowed? Or is 24/7 manned flagging a strict requirement for the Cow Creek Bridge?

Inquiry submitted 05/19/2022

Response #1:(BI#1)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 05/20/2022


Response #2:(BI#1)-Bid per current bidding documents.
Response posted 05/20/2022




Inquiry #2: Morgan Road Over-crossing Location 8 has four concrete barrier transitions to be build and installed. But there is no temporary protection shown in the plans for this locations. How the does the state foresee protecting these barrier transitions during construction.
Inquiry submitted 05/23/2022

Response #1:(BI#2)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 05/23/2022


Response #2:(BI#2)-Bid per current bidding documents.
Response posted 05/23/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.