Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 02-3E7404

Submit new inquiry for this project


Inquiry #1: For the SAMI-R, there are 2 missing bid items:

Item Code 370120 Asphalt Rubber Binder
Item Code 374044 Asphaltic Emulsion (Flush Coat)

Also what base asphalt does Caltrans want to use for the Asphalt Rubber Binder?


Inquiry submitted 05/07/2018

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 05/08/2018


Response #2:
Item Code 370120 Asphalt Rubber Binder:
An addendum will be issued to add Item 370120_Asphalt Rubber Binder to the plans and estimate.

Item Code 374044 Asphaltic Emulsion (Flush Coat):
This item is not applicable, see Revised Standard Specifications 37-2.05A_General.

Also what base asphalt does Caltrans want to use for the Asphalt Rubber Binder?:
Please see Revised Standard Specifications 37-2.04B(2)_Asphalt Binders and Special Provision 39-2.03B(3)(a).
Response posted 05/15/2018




Inquiry #2: For the SAMI-R, there are 2 missing bid items:

Item Code 370120 Asphalt Rubber Binder
Item Code 374044 Asphaltic Emulsion (Flush Coat)

Inquiry submitted 05/07/2018

Response #1:
(#2)-SEE RESPONSE TO BI #1.
Response posted 05/08/2018




Inquiry #3: For the SAMI-R, there are 2 Bid Items missing:

Item Code 370120 ASPHALT-RUBBER BINDER
Item Code 374004 ASPHALTIC EMULSION (FLUSH COAT)


Inquiry submitted 05/07/2018

Response #1:
(#3)- SEE RESPONSE TO BI #1.
Response posted 05/08/2018




Inquiry #4: Re: Wet Night striping item #84. First there is not spec's for wet night stating the 90 mil or 100 mil thickness , beads etc. But the main problem is all wet night in the state have always had separate line items for 6" solid , 6" broken, 8". Not lumped together like paint or sprayable because payment through measurement will become impossible later and break all the rules of the standard plans and spec's. Please try to fix this problem.
Inquiry submitted 05/16/2018

Response #1:(#4)-Your inquiry has been received and is being reviewed.
Response posted 05/17/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Thursday, May 31, 2018.
Please bid per the current contract documents.
Response posted 06/01/2018




Inquiry #5: Will the State please provide embankment quantities and/or an electronic finish grade surface?
Inquiry submitted 05/24/2018

Response #1:
(#5)-Your inquiry has been received and is being reviewed.

Response posted 05/24/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Thursday, May 31, 2018.
Please bid per the current contract documents.
Response posted 05/24/2018




Inquiry #6: Can Plastic Pipe be used for the 8" underdrain outlets and risers? Or, will Perforated Plastic Pipe actually be allowed for the 8" Alternate Pipe Underdrain?

Standard Specification Section 68-2.02A, say "For alternative pipe underdrain, do not mix types of pipe in the same installation."
In addition, Standard Specification Section 68-2.02E say "Underdrain outlets and risers must be fabricated from the same material as the underdrain pipe or from corrugated metal pipe."

Bid item 42, 8" Corrugated Steel Pipe, is the bid item and quantity for payment of the underdrain risers and outlets.

Plan Sheet 65 list Perforated Plastic Pipe as an allowable material for underdrains. However, Bid Item 42 only allows for one type of material forcing the use of Perforated Steel Pipe for the underdrains.

Inquiry submitted 05/24/2018

Response #1:
(#6)-Your inquiry has been received and is being reviewed.

Response posted 05/24/2018


Response #2:1a- The project plans require underdrain outlets and risers to be constructed out of corrugated steel pipe, see sheet DQ-4.
1b- The plans allow alternative pipe to be used for the underdrains, see sheet DQ-4.
3- True statement. Your attention is directed to Standard Specifications Section 5-1.02 Contract Component.
4- True statement.
5- True statement. Your attention is directed to Standard Specifications Section 5-1.02 Contract Component.
Response posted 05/30/2018




Inquiry #7: The plans appear to not have variable depth cold planing and paving where it occurs. Without this, it can only be expected to return the same smoothness of the existing road. Please consider allowing variable cold planing and paving in order to maximize improvements.
Inquiry submitted 06/04/2018

Response #1:
(#7)-Your inquiry has been received and is being reviewed.
Response posted 06/04/2018


Response #2:
Please bid per the current contract documents.
Response posted 06/05/2018




Inquiry #8: Could you please provide PPF smoothness profiles so that a smoothness analysis can be done on sections in which mill and fill will take place.
Inquiry submitted 06/04/2018

Response #1:
(#8)-Your inquiry has been received and is being reviewed.
Response posted 06/04/2018


Response #2:
Please bid per the current contract documents.
Response posted 06/05/2018




Inquiry #9: The existing GR in a number of spots has concrete footings with a pase plate steel post. The extra cost for installation and purchase of these fall under the GR item or is this going to be change order work?
Inquiry submitted 06/11/2018

Response #1:
(#9)-Your inquiry has been received and is being reviewed.
Response posted 06/12/2018


Response #2:
Please bid per the current contract documents.
Response posted 06/13/2018




Inquiry #10: The F Dike on this project, is it going to be 4" or 6"? According to C-9 there is a 6" or 4" type F dike. Important to know for GR so contractors know what size block they need, a 6x8 or 6x12.
Inquiry submitted 06/12/2018

Response #1:
(#10)-Your inquiry has been received and is being reviewed.
Response posted 06/12/2018


Response #2:
Your attention is directed to contract plan sheets 35, 78 and 80, as well as RSP A87B and RSP A77L2.
Response posted 06/15/2018




Inquiry #11: In regards to the response to Inquiry#1, If the Asphaltic Emulsion (Flush Coat) is not applicable, why is there Item" 21 "Sand Cover (Seal)?

Is it the intent for no public traffic to be allowed on the SAMIper Section 37-2.05A?

Inquiry submitted 06/13/2018

Response #1:
(#11)-Your inquiry has been received and is being reviewed.
Response posted 06/14/2018


Response #2:
Per Section 37-2.05A of the Revised Standard Specifications, a flush coat is not required for the Stress Absorbing Membrane Interlayer. The Sand Cover (Seal) bid item is associated with the Full Depth Reclamation, see Full Depth Reclamation quantity table on plan sheet Q-1 (77 of 139).
Per Section 37-2.05A of the Revised Standard Specifications, ?Traffic must not be allowed on a SAMI?.

Response posted 06/15/2018




Inquiry #12: Bid Items 42 and 44. What is the preferred method of connecting the Plastic Underdrain to the Steel Risers? Should the Wye or Tee be Steel or Plastic?
Inquiry submitted 06/18/2018

Response #1:
(#12)-Your attention is directed to contract documents for typical connection details of the underdrain and risers. Refer to Section 68-2.02 of the Standard Specification, the Wye or Tee must be fabricated from the same material as the underdrain (do not mix types of pipe in the same installation).
Response posted 06/19/2018




Inquiry #13: Bid Items 39 and 40, is 24" bell and spigot HDPE acceptable for both bid items?
Inquiry submitted 06/18/2018

Response #1:
(#13)-For item 39, refer to APC table on project plan sheet 65. HDPE is not one of the alternatives allowed for Alternative Pipe Culvert.
For item 40, refer to Section 64-2.02 of the Standard Specifications regarding HDPE used as Plastic Pipe.

Response posted 06/19/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.