Inquiry #1: We inadvertently advertised as a "contractor looking for help" twice. Please delete one of our entries. Thank you.
Inquiry submitted 02/15/2019

Response #1:
(#1)-The duplicated entry has been deleted.
Response posted 02/15/2019




Inquiry #2: The lane closure charts state that " No vehicles with 2 or more axles may enter/exit the work area..." Every vehicle has 2 axles. Was it your intent to state "No vehicles with more than 2 axles may enter/exit the work area" or are you stating that no vehicles may enter/exit the work area between the hours shown on the lane closure chart.
Inquiry submitted 02/21/2019

Response #1:(#2)-Your inquiry has been received and is being reviewed.
(#2) See Addendum No.1

Response posted 02/22/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019.
Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #3: Drainage System #6 seems to be lacking some detail. The layout as shown on sheet #6 of 65 is missing some details with regards to what currently exists in the planned location. It appears that the run of pipe sits in alignment with an existing rolled curb & gutter. However, there is no details or bid items that deal with the sawcut, removal, or replacement of the curb & gutter, as well as the HMA patching. Please take a look at this, and give some direction.
Inquiry submitted 02/27/2019

Response #1:
(#3) - Your inquiry has been received and is being reviewed.
Response posted 02/28/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019. Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #4: Addendum #1 did not include a response to inquiry #2 as stated. Please provide a response to inquiry #2.
Inquiry submitted 03/04/2019

Response #1:
(#4)-An addendum is being prepared to address bidder inquiry #2.
Response posted 03/04/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019.
Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #5: Please clarify seed mix rates for Erosion Control Type 1 and Type 2. Two different application rates are listed and only one seed mix is provided. In addition, sheet ECL-1 references Sheet EC-3, which is not included in the plan set. Please advise.
Inquiry submitted 03/04/2019

Response #1:
(#5)-Your inquiry has been received and is being reviewed.
Response posted 03/04/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019.
Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #6: Bid item #45 calls out a quantity of 350 lf of 12" CSP (.064" Thick). I cannot find it in the plan sheets, nor is it shown in the drainage quantities. Please clarify.
Inquiry submitted 03/05/2019

Response #1:
(#6)-Your inquiry has been received and is being reviewed.
Response posted 03/05/2019


Response #2:
Please see Legend on sheet L-1, and sheets L-3, L-4, and Downdrains Quantities table on sheet Q-2.
Response posted 03/11/2019




Inquiry #7: There are some discrepancies on the Drainage Quantities Sheets with regards to what is shown on the plans, and what is shown in the description area. Drainage Systems 3-K, 4-A, and 8-F have conflicting information with regards to pipe sizes, and amounts. Please review and clarify.
Inquiry submitted 03/05/2019

Response #1:
(#7)-Your inquiry has been received and is being reviewed.
Response posted 03/06/2019


Response #2:
(#7)-Your inquiry has been received and is being reviewed.
Response posted 03/06/2019


Response #3:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019.
Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #8: What is the break up for the mulch and tack in the Erosion Control BFM?
Inquiry submitted 03/06/2019

Response #1:
(#8)-Your inquiry has been received and is being reviewed.
Response posted 03/06/2019


Response #2:
Please see section 21-2.02J of 2018 Standard Specifications for the relationship between the tackifier and fiber of the Bonded Fiber Matrix.
Response posted 03/07/2019




Inquiry #9: Layout Sheets L-1 and L-2 (sheets 4 & 5 of the plans) make reference to a "Biofiltration Strip". This work seems to be displayed prominently. However, I cannot find any details on it, nor can I find anything on the quantities sheets. Please clarify what work if any is to be done in these areas.
Inquiry submitted 03/07/2019

Response #1:
(#9)-Your inquiry has been received and is being reviewed.
Response posted 03/08/2019


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 08, 2019.
Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #10: Please provide additional detail for Drainage System No. 8. It appears there is AC Dike and Guardrail that needs to be removed and replaced to accommodate installation.
Inquiry submitted 03/11/2019

Response #1:
(#10)-Please bid per the current contract documents.
Response posted 03/11/2019




Inquiry #11: Currently pole procurement is approximately 20-22 weeks after submittal approval. The project does not seem to have sufficient time to accommodate the entire submittal, procurement and installation process. Please clarify.
Inquiry submitted 03/12/2019

Response #1:
(#11)-All items of work should be completed within the working days provided. Contract suspension may be requested for delays due to material procurement after all other contract items are completed.
Response posted 03/12/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.