Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 03-1G2504

Submit new inquiry for this project


Inquiry #1: Can you please submit Supplemental data for NB Lane 1 as well.
Inquiry submitted 04/06/2020

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 04/06/2020


Response #2:
The second file has uploaded and It is on-line now.
Response posted 04/07/2020




Inquiry #2: Sheet Q-1 states there is 1,740 CY of Replace AC Surfacing. Below the chart, there is a note that states exact limits to be determined by the engineer. Without knowing the total approximate quantity of locations (Digouts), dimensions, and where those digouts fall within the project limits, it is impossible to have representative bids. Please provide additional details on the size, quantity, and location of the Replace AC Surfacing Item.
Inquiry submitted 04/16/2020

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 04/16/2020


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Monday, April 27, 2020. Please bid per the current contract documents.
Response posted 04/27/2020




Inquiry #3: The plans for GR are showing reconstruct GR ( steel posts). Wanting to confirm that reconstruct is not for Midwest GR. Midwest GR needs the rail punched at 3'1.5 spacing not 6'3" like the style up now. Reconstruct is to reuse rail and put new posts and blocks in. I assume we are installing the reconstruct at the 29" GR?
Inquiry submitted 04/27/2020

Response #1:
(#3)-Your inquiry has been received and is being reviewed.
Response posted 04/27/2020


Response #2:
Please bid per the current contract documents.
Response posted 04/29/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.