Viewing inquiries for 03-1H1004
Submit new inquiry for this projectInquiry #1: Are the steel column casings to be painted?
Inquiry submitted 06/21/2021
Response #1:(BI#1)-Your inquiry has been received and is being reviewed.
Response posted 06/21/2021
Response #2:(BI#1): No, steel column casings are not to be painted. Bid per the current contract documents.
Response posted 06/22/2021
Inquiry #2: Are the steel column casings to be painted?
Inquiry submitted 06/21/2021
Response #1:(BI#2)-Your inquiry has been received and is being reviewed.
Response posted 06/21/2021
Response #2:(BI#2): No, steel column casings are not to be painted. Bid per the current contract documents.
Response posted 06/22/2021
Inquiry #3: What are the State's right of ways under all the bridges on the project? Can we work in those right of ways under the bridge?
Inquiry submitted 06/21/2021
Response #1:(BI#3)-Your inquiry has been received and is being reviewed.
Response posted 06/21/2021
Response #2:(BI#3)-Your attention is directed to Note 1 on sheet U-1 for right-of-way information. You may work under the bridges within Caltrans right-of-way.
Please bid per current contract documents.
Response posted 06/22/2021
Inquiry #4: The As Built plans are missing ramp C5 L0L (BR. 24-4305) Would you please provide us the missing plans?
Inquiry submitted 07/13/2021
Response #1:(BI#4)-Your inquiry has been received and is being reviewed.
Response posted 07/13/2021
Response #2:(BI#4)-Your attention is directed to section 2-1.06B of the Standard Specifications for information regarding as-builts. Please bid per current contract documents.
Response posted 07/13/2021
Inquiry #5: Bit Item 18 Temporary Construction Roadway, drawing C-1 shows where the roadway is to be install. What is the thickness required of the HMA?
Inquiry submitted 07/14/2021
Response #1:(BI#5)-Your inquiry has been received and is being reviewed.
Response posted 07/14/2021
Response #2:(BI#5)-Your attention is directed to Standard Plan T67 for additional details regarding the construction of a Temporary Construction Roadway.
Response posted 07/15/2021
Inquiry #6: We respectfully request the current Bid Date of July 21th, be extended by 4 weeks in order to prepare a complete and comprehensive bid. We make this request on behalf of our own resources and select subcontractors, vendors and material suppliers. We trust in your understanding of our request and await a favorable reply.
Inquiry submitted 07/15/2021
Response #1:(BI#6)-A change to the bid opening date is not a consideration at this time. Please bid per current contract documents.
Response posted 07/15/2021
Inquiry #7: After careful review of the bidding documents, we respectfully request a bid extension of 2 weeks in order to properly prepare for this bid.
Inquiry submitted 07/15/2021
Response #1:(BI#7)-A change to the bid opening date is not a consideration at this time. Please bid per current contract documents.
Response posted 07/15/2021
Inquiry #8: Please clarify the "Working Days Bid" process. Is the amount calculated part of the final bid amount? How does it get paid to the contractor? And is payment made for the actual number of days per fixed daily price? Thank you.
Inquiry submitted 07/21/2021
Response #1:(BI#8)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.
Response posted 07/21/2021
Response #2:(BI#8)-The monetary value associated with days bid is used for bid comparison only. It puts a monetary value to the days bid portion so bid items and bid days can be added into one total. That value will determine the lowest bidder. Once the bid is awarded, the dollar amount for days bid is of no value. The contractor is still obligated to complete the work in the number of days they bid, but they only get paid for the bid items in the estimate.
Response posted 07/21/2021
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.