Viewing inquiries for 03-2G3904

Submit new inquiry for this project


Inquiry #1: Can you please check the accuracy of your PPF data for NB Lane #4?

1. The MRI's are considerably high compared to that of the other lanes which is causing the deduction to be extremely high (in the $100,000) based on certain percentage of improvement.

2. The second portion of the #4 Aux lane starts from Fulton Ave and ends at the 244 Ramp cut off. That section is only about 3300 LF. Not sure how you came up with over 1.5 miles of data for that section?

Inquiry submitted 01/24/2022

Response #1:(BI#1)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 01/24/2022




Inquiry #2: There is not a bid item for street sweeping (item code 130730) or mobilization (item code 999990). How will the Contractor be paid for these items? Please revise bid schedule.
Inquiry submitted 01/26/2022

Response #1:(BI#2)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 01/27/2022




Inquiry #3: With the recent bid date push, could you please consider adding bid items for mobilization and sweeping?
Inquiry submitted 01/27/2022

Response #1:(BI#3)-Refer to Addendum #3, dated 1/28/2022. A bid item for mobilization will not be added.

Response posted 01/27/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.