Inquiry #1: CDFW Stream Alteration Agreement Reporting Measure 4.4 (Annual Monitoring Reports) implies monitoring the two wildlife undercrossings with camera trap stations for three years following project completion. This requirement does not appear to be written elsewhere including in the description for annual monitoring report in Section 14-6.03D(1) pertaining to Contractor-Supplied Biologist . Does Caltrans intend for camera trap monitoring and reporting of results to be the responsibility of the Contractor-Supplied Biologist?
Inquiry submitted 12/02/2021

Response #1:(BI#1)-Your attention is directed to section 14-12.04C of the Special Provisions for details regarding work to be performed. The Department will monitor wildlife as described in Measure 4.4.

Response posted 12/02/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.