Viewing inquiries for 03-3H93U4

Submit new inquiry for this project


Inquiry #1: Bid Item #9 Type III has a quantity 73 each on the bid item lists, only see 22 each on plan quantities.
(12 each on THQ-1 & 10 each on THQ-2)
Bid Item #12 Plastic Traffic Drums has a quantity 600 each on the bid item lists, only see 98 each on plan quantities.
(98 each on THQ-1)

Inquiry submitted 05/04/2021

Response #1:(BI#1)-Your inquiry has been received and is being reviewed.

Response posted 05/05/2021


Response #2:(BI#1)-Please bid per current contract documents.
Response posted 05/05/2021




Inquiry #2: The Bit Item 119(F) Isolation Casing has a value of 11,661 lb. on the Bid Item List and in the Plans the value given is 43,660 lb.. Please clarify.
Inquiry submitted 05/18/2021

Response #1:(BI#2)-Your inquiry has been received and is being reviewed.

Response posted 05/19/2021


Response #2:(BI#2)-An addendum has been issued in response to this inquiry. See addendum #1, date May 19, 2021.
Response posted 05/19/2021




Inquiry #3: The quantity for the import borrow seems to be over stated for stages 1A and 1B. After adding in the quantity for subsidence stated in the special provisions section 19-7.04 of 6,274 CY, then subtracting the roadway ex for these stages, the import borrow is overstated by about 7,500 CY. Please adjust the quantity for import borrow accordingly in the bid and on the summary of quantities, plan sheet 208(Q-1).
Inquiry submitted 06/04/2021

Response #1:(BI#3)-Your inquiry has been received and is being reviewed.

Response posted 06/04/2021


Response #2:(BI#3)-Bid per current contract documents.
Response posted 06/07/2021




Inquiry #4: On sheet 136 stage 2a construction item 1 it describes for the contractor to perform "wedge pave on "S" line from STA 109+50 TO 273+42" There is no indication of where exactly the "wedge paving" is to be placed, there is no detail or any indication of quantities for "wedge paving", can you please clarify what the wedge paving consists of?
Inquiry submitted 06/10/2021

Response #1:(BI#4)-Your inquiry has been received and is being reviewed.

Response posted 06/11/2021




Inquiry #5: The bid documents do not say how long the plant establishment period is. How long is the plant establishment period for this project?
Inquiry submitted 06/11/2021

Response #1:(BI#5)-Your inquiry has been received and is being reviewed.

Response posted 06/11/2021


Response #2:(BI#5)-An addendum has been issued in response to this inquiry. See addendum #4, dated June 14, 2021.
Response posted 06/14/2021




Inquiry #6: The Central Valley Flood Protection Board ( Permit # 19540 BD), page 4 of 5, condition 25 that states “ No construction work of any kind shall be done during the flood season from November 1 to April 15 without prior approval of the Board.”
Will we be able to work in the flood zone during this timeframe?


Inquiry submitted 06/11/2021

Response #1:(BI#6)-Your inquiry has been received and is being reviewed.

Response posted 06/11/2021


Response #2:(BI#6)-Per condition TWENTY-FIVE of the Central Valley Flood Protection Board, Permit 19540BD, you can work during the flood season from November 1 to April 15 as long as you have approval from the Board. A Time Variance Request must be submitted to the Board at least 10 working days prior to the start of work during the flood season.
Response posted 06/14/2021




Inquiry #7: A letter from NOAA dated April 9, 2019 to CT that states “ Work is estimated to take 494 working days and would occur only between June 30 and October 31 when listed species are least likely to occur. Equipment will be removed between work seasons.”

Is the intent to have the contractor on work during Jun 30 to October 31 in the flood plane?

Inquiry submitted 06/11/2021

Response #1:(BI#7)-Your inquiry has been received and is being reviewed.

Response posted 06/11/2021




Inquiry #8: On Sheet L-1 there is no transition for the WB lanes into the current two way traffic. When traffic is switched into Stage 3 (There is no traffic handling plans for this either) the WB traffic goes into a tree.
Inquiry submitted 06/11/2021

Response #1:(BI#8)-Your inquiry has been received and is being reviewed.

Response posted 06/11/2021


Response #2:(BI#8)-Please bid per current contract documents.
Response posted 06/14/2021




Inquiry #9: Stage 1a says to build DS # 2 (12’ x 12’ x 51.2’ Box Culvert). Traffic is shown going over DS # 2 in Stage 1a,b,c,d and Stage 2. Stage 3 shows DS # 2 being constructed but traffic is shown going over the top of it. Please provide clarification as to how and when DS # 2 is to be constructed. Or does the State want 24 Hour traffic control for the entire construction the DS # 2, which the traffic charts does not allow.
Inquiry submitted 06/14/2021

Response #1:(BI#9)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 06/14/2021




Inquiry #10: ON page 217 Erosion Control Legend, Erosion Control Type 3 "Ditch Area" Step 1A, In the remarks it refers to 5-3-2. On the Notes at the top of the page it only has 1-2. Where do I find Note 3-4-5?
Inquiry submitted 06/15/2021

Response #1:(BI#10)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 06/15/2021




Inquiry #11: Section 13 states the project's risk level is 1. Risk Level 1 projects do not require Rain Event Action Plan (Bid Item 21) or Storm Water Sampling And Analysis Day (Bid Item 22).
Inquiry submitted 06/15/2021

Response #1:(BI#11)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 06/15/2021


Response #2:(BI#11)-Your attention is directed to addendum #3, dated June 9, 2021. Please bid per current contract documents.
Response posted 06/15/2021




Inquiry #12: There is a chart shown in the Special Provisions on Page 20 showing Pacific Gas & Electric Company Season 1 and Season 2 conflict areas 1-16 for Utility Relocation. Where are these areas/locations shown on the plans?
Inquiry submitted 06/15/2021

Response #1:(BI#12)-Your inquiry has been received.  However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response.  If no additional response is posted please bid per the current contract documents.

Response posted 06/15/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.