Inquiry #1: DQ sheets missing footages of Down Drains, removals, and maybe more? Please fix.
Inquiry submitted 08/19/2022

Response #1:Submitted for consideration.
Response posted 08/19/2022


Response #2:Granite Rock Company submitted Bidder Inquiry #2 to disregard their Bidder Inquiry #1 as the answer to their original question is on DQ sheets 9-16.
Response posted 08/23/2022




Inquiry #2: DQ sheets 9-16 has DD quantities. Disregard previous question.
Inquiry submitted 08/23/2022

Response #1:Submitted for consideration.
Response posted 08/23/2022


Response #2:Granite Rock Company submitted Bidder Inquiry #2 to disregard their Bidder Inquiry #1 as the answer to their original question is on DQ sheets 9-16.

see Inquiry #1/Response #2.
Response posted 08/25/2022




Inquiry #3: The Soil Investigation Report states the upper 2’ of material generated at Loc 5-1-2 & Loc 5-3 is classified as a California hazardous waste (high levels of nickel). Please state what Caltrans intends to do with this material. There is no bid item for hazardous waste disposal.
Inquiry submitted 08/26/2022

Response #1:Submitted for consideration.
Response posted 08/26/2022


Response #2:The location where regulated levels of nickel are found is project location 3, from AS Line station 1058+00 to 1075+00. The management of this material is specified in special provision 14-11.09 Minimal Disturbance of Regulated Material Containing Aerially Deposited Lead or Nickel. The excavated soils containing the naturally occurring high levels of nickel are to be used as backfill in the excavation of origin or left in the immediate area of excavation.
Response posted 08/26/2022




Inquiry #4: There is a bid item for “Remove Concrete (Miscellaneous)” – to remove concrete inlet depressions; quantity is 4 CY. However there is no bid item for “Remove Concrete Curb” - identified on the Summary of Quantities (sheet Q-1); quantity is 67.1 CY. Should we bid the latter concrete removal under the same item?
Inquiry submitted 08/26/2022

Response #1:Submitted for consideration.
Response posted 08/26/2022


Response #2:See Item 95, Remove Concrete Curb in Addendum 1.
Response posted 09/07/2022




Inquiry #5: Traffic Handling Plan Note 2 does not allow us to install Temp Railing (Type K) on the Left & Right shoulders simultaneously. However, we cannot install the WSP Trenchless Culverts and MSW PVC Pipeliners that cross the traffic lanes unless we have pits/access on the Left & Right shoulders simultaneously. Please address/rectify this matter.
Inquiry submitted 08/26/2022

Response #1:Submitted for consideration.
Response posted 08/26/2022


Response #2: Please bid per the current contract documents.
Response posted 08/30/2022


Response #3:
Response posted 09/21/2022


Response #4:
Response posted 09/22/2022


Response #5:See Notes in revised plan sheet TH-1 in addendum 6 (Dated 10/14/2022) for temporary barrier where work is required at culvert crossings.
Response posted 10/18/2022




Inquiry #6: Please provide a detail for connecting the 18” WSP Trenchless Culvert (Drainage System 25c) to the existing downstream Drain Inlet.
Inquiry submitted 08/26/2022

Response #1:Submitted for consideration.
Response posted 08/26/2022


Response #2:Per Addendum 6 (Dated 10/14/2022), See revised sheet DD-2, CONCRETE COLLAR PIPE CONNECTION TO EXISTING INLET OR MANHOLE.
Response posted 10/18/2022




Inquiry #7: Can other alternative pipeliners that conform to DIB 83-4 per section 71-3-09 and AASHTO M326 be used in place of MSW PVC PIPELINER (EXPANDABLE DIAMETER)? These liners have many advantages including environment as well as can be installed in live stream without the need for by-pass. Line items 72-77.
Inquiry submitted 08/26/2022

Response #1:Submitted for consideration.
Response posted 08/27/2022


Response #2:The Contractor can submit a RFI to request review and approval for other alternative pipeliners. Caltrans would consider other alternative pipeliners that meet and/or exceed the project requirements based on product specifications.
Response posted 08/29/2022




Inquiry #8: There are no bid items to remove/replace concrete barrier where the pipe crosses through it (i.e. – DS 1b, 1d, 1e, 3k) or where bore & jack pits & new drain inlets are installed (i.e. – 17a, 18a, 19a, 24a, 25b). How are we compensated for this work?
Inquiry submitted 08/31/2022

Response #1:Submitted for consideration.
Response posted 08/31/2022


Response #2:Caltrans does not plan to remove/replace the barrier. Please bid for the existing concrete barrier not being removed or replaced. See Section DD-5 in Addendum 6 (Dated 10/14/2022).
Response posted 10/18/2022




Inquiry #9: There is an existing concrete slab that runs along the face of the existing concrete barrier. It needs to be removed in order to install the new pipe and drain inlets (i.e. – DS 1b, 1e, 3k, 4d, 4f, 5a, 5c, 5d, 17a, 18a, 19a, 24a, 25a, 25b). Please provide a typical cross section of it. Does it project beneath the concrete barrier? Does it contain reinforcing steel? How are we compensated for this work?
Inquiry submitted 08/31/2022

Response #1:Submitted for consideration.
Response posted 08/31/2022


Response #2:See Sheet revised L-5, L-6, L-7, Q-1, & DD-5 of Addendum no. 6 (Dated 10/14/2022). For payment see Item 97, REMOVE CONCRETE PAVEMENT (CY) in Addendum 6.
Response posted 10/18/2022




Inquiry #10: Hello,

We are inquiring about the seed mix pounds per live seed per acre measurements. We believe that the seeding rates might be incorrect as our vendor believes that the seeding rates are too high on the specifications for two of the seeds. They believe that "Baccharis pilularis" and "Mimulus aurantiacus", which have a 4 pounds per live seed per acre measurement, to be 0.4 pounds per live seed per acre Please advise.

Inquiry submitted 09/02/2022

Response #1:Submitted for consideration.
Response posted 09/02/2022


Response #2:Proposed Response: Per addendum 6 (Dated 10/14/2022), sheet ECL-1, the Live seed per acre is changed to 0.4 pounds per live seed per acre
Response posted 10/18/2022




Inquiry #11: On Sheet No. 84/170

Note on CONCRETE COLLAR PIPE CONNECTION TO EXISTING INLET OR MANHOLE reads as follows:
“BEND Existing Reinf INTO COLLAR AND CUT TO FIT. IF NO Reinf AVAILABLE IN THE Exist WALL, USE #4 @ 12” C-C DOWELS. DRILL AND EPOXY NEW DOWELS INTO Exist Conc.”

Drilling and Epoxy New Dowels into existing structures adds significant cost to the concrete collars.

Is there any more information available to help the contractor determine how many of the existing structures have Reinforcement that can be bent?

Inquiry submitted 09/07/2022

Response #1:Submitted for consideration.
Response posted 09/07/2022


Response #2:No, there is no additional information available to help the contractor determine how many of the existing structures have reinforcement that can be bent.
Response posted 09/07/2022




Inquiry #12: When constructing the new concrete collar pipe connections to the existing inlets (see detail on DD-2) the resulting excavation will undermine the existing concrete gutter depressions and they will have to be removed. Will new concrete gutter depressions be required and paid for as part of the 12" slab in bid in bid item 81 (Minor Concrete - Misc Construction), or in bid item 83 (Minor Concrete - Gutter Depression)?
Inquiry submitted 09/07/2022

Response #1:Submitted for consideration.
Response posted 09/07/2022


Response #2:Please bid per the current contract documents.
Response posted 09/14/2022




Inquiry #13: Location 4, where is the access to get under the bridge?
1. Can we get access to under the bridge through the Hetch Hetchy property and come in from the top and access at the gate?
2. do we have to lower everything from the freeway with a crane? Are there anchor points to tie off our equipment to do the work on the abutment slope or do we have to build our own anchors to tie off equipment.
please clarify contractors access to do the work and any potential tie off points for equipment?

Inquiry submitted 09/07/2022

Response #1:Submitted for consideration.
Response posted 09/07/2022


Response #2:Please be aware access is possible to the work under the bridge, from Crystal Springs Road. Concerning access from the top, please see revised sheet L-17 of addendum 6 (Dated 10/14/2022) for the revised ESA WILDLIFE EXCLUSION FENCE (TYPE FROG), WILDLIFE EXCLUSION FENCE. It is also possible to lower equipment from the bridge with a crane. Please be aware that there are not tie off points on the bridge. Access through the gate from outside State right of way has not been arranged by Caltrans.
Response posted 10/18/2022




Inquiry #14: system 23, the boring machine will have to be placed in the off ramp to the Vista Point. Can you provide a closure chart for that?

typical boring unit is approx. 36 ft long, clarify what contractor is supposed to do at the locations where the concrete barrier and slab are at approx. 25-28 ft from white line to barrier. we also need room to place the krail!

Inquiry submitted 09/07/2022

Response #1:Submitted for consideration.
Response posted 09/07/2022


Response #2:Please bid per the current contract documents
Response posted 09/21/2022




Inquiry #15: Is the pipe to be removed Bituminous coated?
Inquiry submitted 09/08/2022

Response #1:Submitted for consideration.
Response posted 09/08/2022


Response #2:Assume that the pipe is bituminous coated.
Response posted 09/21/2022




Inquiry #16: System 1b, c,d, and e (54 in pipe remove and replace) looks like it maybe under or behind the existing concrete barrier with slab. The quality of the plans is not good enough quality to tell what is going on there, and if so where does the removal and replacement of this barrier get paid for? Do we remove it and not replace it?
please clarify what is going on there?

Inquiry submitted 09/09/2022

Response #1:Submitted for consideration.
Response posted 09/09/2022


Response #2:Caltrans does not plan to remove/replace the barrier. Please bid for the existing concrete barrier not being removed or replaced. See Section DD-5 in Addendum 6 (Dated 10/14/2022).
Response posted 10/18/2022




Inquiry #17: Concrete Invert Paving Detail shown on sheet 86/170 calls for Grout Ports at 5 & 7 O'clock @ 8' Spacing.

What is the estimated quantity for the Grout?
How is the contractor compensated for this work?

Inquiry submitted 09/15/2022

Response #1:Submitted for consideration.
Response posted 09/15/2022


Response #2:The quantity for the grout will be the actual quantity of grout that is installed. Refer to Special Provisions Section 71-3.02 for when grout should be used to fill voids and the contractor’s responsibility to record and submit grout quantity.
Filling the voids around the culvert with grout is paid for as a change order work.
Response posted 09/19/2022




Inquiry #18: Is Section 19-17.01D(5)(b) Pavement Smoothness Monitoring required for this project?
Inquiry submitted 09/16/2022

Response #1:Submitted for consideration.
Response posted 09/16/2022


Response #2:Yes, the section 19-17.01D(5)(b) Pavement Smoothness Monitoring is required for this project.
Response posted 09/20/2022




Inquiry #19: Is Section 19-17.01D(5)(d) Subsurface Displacement Monitoring required for this project?
Inquiry submitted 09/16/2022

Response #1:Submitted for consideration.
Response posted 09/16/2022


Response #2:Yes. The Section 19-17.01D(5)(d) Subsurface Displacement Monitoring is required for this project.
Response posted 09/20/2022




Inquiry #20: Is Section 19-17.01D(5)(c) Ground Surface Displacement Monitoring required for this project?
Inquiry submitted 09/16/2022

Response #1:Submitted for consideration.
Response posted 09/16/2022


Response #2:Yes, Section 19-17.01D(5)(c) Ground Surface Displacement Monitoring is required for this project.
Response posted 09/20/2022




Inquiry #21: There are a lot of critical bidder inquiries that need to be addressed and the bid opening is less than one week away. When can we expect addendum addressing the outstanding issues?
Inquiry submitted 09/22/2022

Response #1:Submitted for consideration.
Response posted 09/22/2022


Response #2:Please be aware the bid opening date has changed to 10/27/2022. See addendum 5.
Response posted 09/26/2022




Inquiry #22: The response to Bidder Inquiry #19 states Section 19-17.01D(5)(d) Subsurface Displacement Monitoring is required for this project. However, none of the scenarios described can be accomplished on this project – the 18” & 24” WSP runs only have 5.8’ (avg) cover above the crown of the culvert. If we place the monitoring equipment above the culvert alignment as described it will be suspended above the road surface. Please address accordingly.
Inquiry submitted 09/26/2022

Response #1:Submitted for consideration.
Response posted 09/26/2022


Response #2:No, please see 19-17.01D(5)(d) Subsurface Displacement Monitoring in the specifications, where the bore diameter is not greater than 48 inches.
Response posted 10/18/2022




Inquiry #23: The Soils Investigation Report provided with Addendum No.1 states that NOA will be found in 9 of the 18 work sites, bores indicate clasts of serpentine. What volume of dirt spoils should we assume will contain NOA? The quantity of spoils which contains NOA will have a bearing on hauling & disposal costs? Can this material be left onsite or within Caltrans right of way? Which bid/pay item accounts for the cost of transport & disposal. The excavations on this project are being backfilled with slurry so the excavated dirt material cannot be reused on the job.
Inquiry submitted 09/26/2022

Response #1:Submitted for consideration.
Response posted 09/27/2022


Response #2:There are no hauling and disposal for the excavated materials, per special provision, 14-11.10, Naturally Occurring Asbestos (NOA). The special provision directs that the excavated NOA-containing materials be used as backfill where possible (e.g., downdrain excavations in the median) or left near the area of excavation/disturbance (e.g., soils from roadway shoulder excavations for culverts put in the unpaved median).
Response posted 11/09/2022




Inquiry #24: If rock, serpentine/greenstone clasts, is encountered in the trench which bid item accounts for the cost of excavation & removal. Many of the trenches are new trenches and judging from the soils investigation & geotechnical report encountering rock is likely.
Inquiry submitted 09/26/2022

Response #1:Submitted for consideration.
Response posted 09/27/2022


Response #2:See Special Provision Section 14-11.10 for Naturally Occurring Asbestos (NOA). Concerning rock, per the Geotech report rock is present, please bid items that including excavation, accordingly.
Response posted 10/18/2022




Inquiry #25: 3. The Soils Investigation Report indicates that we will be excavating regulated California Hazardous waste in some locations. What volume of dirt spoils should we assume will be regulated? The quantity of spoils which are hazardous will have a bearing on hauling & disposal costs? Can this material be left onsite or within Caltrans right of way? Which bid/pay item accounts for the cost of transport & disposal. The excavations ont his project are being backfilled with slurry so the excavated dirt material cannot be reused on the job.
Inquiry submitted 09/26/2022

Response #1:Submitted for consideration.
Response posted 09/27/2022


Response #2:There are no hauling & disposal for the excavated materials. See Special Provision Section 14-11.10, Naturally Occurring Asbestos (NOA). See the response to bidder inquiry 23.
Response posted 11/09/2022




Inquiry #26: Bid item 135 Vegetation Control (Shale), Does the state have a local source for this material, or is it the intent to truck this material to the job from the Valley or Northern California. Please Clarify.
Inquiry submitted 10/17/2022

Response #1:Submitted for consideration.
Response posted 10/17/2022


Response #2:There is no Item 135, Vegetation Control (Shale). Is this inquiry for a different project? If not kindly clarify the question.
Response posted 10/20/2022




Inquiry #27: The CA High Design Manual Section 850-34 dated December 30th, 2015 warns against specifying plastic pipe in areas with a potential for fire. This project lists Alternative Pipe Culvert in the Bid Schedule. Will Caltrans still allow for plastic pipe to be used on this project?


Inquiry submitted 10/20/2022

Response #1:Submitted for consideration.
Response posted 10/20/2022


Response #2:Yes. See sheet DQ1.
Response posted 11/09/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.