Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 04-2G4604

Submit new inquiry for this project


Inquiry #1: What is the pay item for the excavation subbase to put back 280 CUYD of the aggregate base?
Inquiry submitted 09/23/2020

Response #1:Submitted for consideration.
Response posted 09/24/2020


Response #2:See Addendum 2.
Response posted 10/05/2020




Inquiry #2: With regards to survey services, is there is project control to establish the alignment and stationing?
Where and what BM’s did Caltrans tie into for vertical?

Inquiry submitted 09/30/2020

Response #1:Submitted for consideration.
Response posted 09/30/2020


Response #2:Construction Survey group will provide the necessary horizontal to establish alignment and offset as well as Vertical control points at the beginning of construction.
Response posted 10/05/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.