Viewing inquiries for 04-2G4614

Submit new inquiry for this project


Inquiry #1: Will the Department pay for Rain Event Action Plan, Storm Water Sampling And Analysis Day, and Storm Water Annual Report?

Inquiry submitted 11/14/2022

Response #1:Submitted for consideration.
Response posted 11/14/2022


Response #2:This project disturbs less than 1 ACRE area and is not a subject to Construction General Permit. For projects that require SWPPP, depending on the risk level requirement, Caltrans pays for those Items. For this project those Items are not required.
Response posted 11/16/2022




Inquiry #2: Can a contractor with only a C-10 license bid this job as a prime contractor?
Inquiry submitted 11/18/2022

Response #1:Submitted for consideration.
Response posted 12/07/2022


Response #2:No, only 7.58% of the work can be performed with a C-10 License only. Please bid per current contract documents.
Response posted 12/07/2022




Inquiry #3: Does the department anticipate pushing this job to bid after the holiday? The current bid date will make the post-bid paperwork due right after the December 26th Christmas holiday. Firms will likely be short –staffed and possibly even closed for the holiday week, making it difficult to obtain written DBE confirmations. Please consider a bid date change giving contractors the proper amount of time to submit responsive post-bid paperwork.
Inquiry submitted 12/09/2022

Response #1:Submitted for consideration.
Response posted 12/12/2022


Response #2:No, the Department is not considering moving the date beyond the holidays and new year and will maintain the current bid open date of 12-22-2022.
Response posted 12/16/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.