Viewing inquiries for 04-2J7504

Submit new inquiry for this project


Inquiry #1: Will Caltrans allow the use of Zoneguard steel barrier in lou of the temporary barrier type K listed in the specs?

Thank you,

Inquiry submitted 06/16/2019

Response #1:Submitted for consideration.
Response posted 06/17/2019


Response #2:No. Bid per plans and specs.
Response posted 06/18/2019




Inquiry #2: Column Casings - Section 59 - Are the column casings receiving finish coats or a final coat?
Inquiry submitted 06/19/2019

Response #1:Submitted for consideration.
Response posted 06/20/2019


Response #2:Your bidder inquiry is under review. Unless an addendum is issued, please bid per current contract documents.
Response posted 06/27/2019




Inquiry #3: Column Casings - Section 59 - Are the column casings receiving finish coats or a final coat?
Inquiry submitted 06/20/2019

Response #1:Same question as above (BI#2).
Response posted 06/20/2019




Inquiry #4: We are requesting a delay to the bid opening due to the effect of the July 4th holiday weekend.
Inquiry submitted 06/25/2019

Response #1:Submitted for consideration.
Response posted 06/25/2019


Response #2:Bid opening will not be delayed.
Response posted 07/02/2019




Inquiry #5: Would the State please check their quantities for Bid Item 7, Temporary Railing (Type K)? Listed quantities appear to be extreme.
Inquiry submitted 06/25/2019

Response #1:Submitted for consideration.
Response posted 06/26/2019


Response #2:The quantity of the temporary railing (type K) includes/covers the lateral shifting of the K rail during the construction. The contractor will need to shift the temp K-rail when installing the steel casing around the bridge columns.
Response posted 06/27/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.