Viewing inquiries for 04-2Q2504

Submit new inquiry for this project


Inquiry #1: The majority of the HFST on this contract is the 2 layer application. Section 37-7.03B(2) of the special provisions states that additional layers of HFST must be applied within 4 hours of the previously cured layer. The restrictive lane closure hours on the traffic charts provided do not allow for ample time to set traffic control, prepare the surface, apply HFST, sweep, place the 2nd layer, cure, final sweep and re-open the work area to traffic.
Will Caltrans consider revising the traffic charts to expand allowable nightly multiple lane closure hours, or alternatively allow traffic on intermediate layers of HFST for a maximum of 24 hours, subject to surface preparation of the existing layer?

Inquiry submitted 10/26/2022

Response #1:Submitted for consideration.
Response posted 10/26/2022


Response #2:See Addendum #5, ‘In the Special Provisions, Section 12-4.02C(3)(g), Chart No. G4 and G5 are added as attached.’
Response posted 11/07/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.