Inquiry #1: Will you please provide the elevation for the bottom of footing for Abutment #2 on the Bridge Foundation Plan?
Inquiry submitted 08/16/2018

Response #1:Submitted for consideration.
Response posted 08/17/2018


Response #2:No further information will be provided. Please bid per current contract documents.
Response posted 08/21/2018




Inquiry #2: Section 14-12.05 requires a Diversion and Dewatering plan in conformance with the Central Coast Regional Water Quality Control Board’s regulations and PLACs included in the information handout.
Temporary Creek Diversion Systems are not included in the Plan Sheets.
Is a Temporary Creek Diversion required or anticipated, and if so, how is payment made for the Temporary Creek Diversion work?

Inquiry submitted 09/07/2018

Response #1:Refer to Section 5-1.01, Section 9-1.03, and the contract PLACs.

A Temporary Creek Diversion is anticipated to complete the work and, per the specifications referenced, payment is included in the bid items involved.

Response posted 09/10/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.