Viewing inquiries for 05-0C7324

Submit new inquiry for this project


Inquiry #1: Will Caltrans release XML or DGN files for the existing ground data
Inquiry submitted 06/06/2022

Response #1:XML file posted with Addendum 1, posted July 8, 2022.
Response posted 06/06/2022




Inquiry #2: Bid item 191 Metal Barrier Mounted Signs, there is no detail for the barrier mounted signs.
Plan sheet 141 note 7 refer to SD-5 for detail, but SD-5 is a detail for overhead sign panel OS5-2.

Inquiry submitted 06/07/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/07/2022


Response #2:Note 7 has been deleted per Addendum 1, posted July 8, 2022.
Response posted 07/12/2022




Inquiry #3: new design line work is missing from Layout Sheets L3 thru L5 at the CL and the shoulders. There are notes and leaders but no clear new construction line work. Please revise.
Inquiry submitted 06/09/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/09/2022


Response #2:Sheets L3 thru L5 have been replaced with revised sheets provided in Addendum 1, posted July 8, 2022.
Response posted 07/11/2022




Inquiry #4: Plan Sheet 125 is very poor quality and barely visible would you provide a new sheet with darker print
Inquiry submitted 06/17/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/17/2022


Response #2:Sheet 125 has been replaced with revised sheet provided in Addendum 1, posted July 8, 2022.
Response posted 07/11/2022




Inquiry #5: On sheet 338 of 375, the height of the top panel is shown as 1'-11" to 3'-11", the bottom and middle panels are panels 3'-11". The table on sheet 336 of 375 shows the overall panel heights, in 21 cases (after we subtract the barrier slab and lower panels) will show a dimension less than 1'-11" (1-3/8" to 1'-10-1/2"), how do we address this?
Inquiry submitted 06/17/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/17/2022


Response #2:Your attention is directed to Note 1 on sheet 338. Bid per contract documents.
Response posted 07/12/2022




Inquiry #6: All the questions listed below are in reference to Plan Sheet 25 Temporary Railing Type K:
1. 1,730 LF of k-rail is identified in Stage 0 provide plan sheets or details on the intent of this quantity.
2. Clarify the scope of work identified on K Line 316+71 to 320+72, to be capped or not? Note the following:
-Plan Sht 125 states 316+71 to 320+72-400 LF Type K
-Plan Sht 114 states
Station 316+71 Beg Temp Railing Type K Beg CAPPED STAKES
Station 317+00 Beg CAPPED STAKES
Station 318+49 End CAPPED STAKES
Station 320+72 End Temp Railing Type K
3. Listed on the summary sheet K 334+66 to 335+31 LT is not reflected on the plans, please identify.
4. Summary sheet identifies K Line 314+79 to 319+00 RT-420 LF of Type K but the plans sheets are not clear Plan Sht 114 states 314+79 to be capped stakes and 319+00 implies it is only Temp K, is this run to be capped or not?
5. Stage 2 Station 270+27 to 334+51 6,860 LF confirm your quantity. 6,860 LF vs 6,424 LF.
6. S Line 312+44 to 312+45- 40 LF this quantity is less than 1 stick of k-rail is this correct or what is CalTrans intent?


Inquiry submitted 06/17/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/17/2022


Response #2:Item 1, 3 and 5 still pending, but addendum #3, dated July 22, 2022, addressed items 2 and 4.

Item 6: Railing to be placed perpendicular to “S” Line (Soquel) and parallel to Chanticleer Ave


Response posted 08/02/2022


Response #3:Items 1, 3, and 5 are addressed as part of addendum #5, posted August 4, 2022.
Response posted 08/04/2022




Inquiry #7: Bid Item #99-Cold Plan Asphalt Pavement will you please show the locations on the plan sheets as they are listed on the summary of quantities on Plan Sheet 169
Inquiry submitted 06/17/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/17/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 08/02/2022




Inquiry #8: What is the angle of internal friction for the CIDH at Sound Wall No. 1?
Inquiry submitted 06/20/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/20/2022


Response #2:The angle of internal friction for the CIDH at Sound Wall No. 1 is 30º, per Table 7 of the Geotechnical Design Materials Report, found in the Information Handout.
Response posted 06/30/2022




Inquiry #9: BID ITEM 173 Discrepancy – Clarification needed for bid items requiring staining
1. Spec 78-4.07A, states “apply the stain to all visible galvanized surfaces of Midwest guardrail system.”
2. Plan page L-1, it states “applying Natina stain to galvanized posts for MGS, trans railing and in-line terminal systems.”
3. Natina provided a quote to Caltrans on 4/2/22 for 180EA steel posts at $28.00, which is listed in the spec 78-4.07B. Spec price date of 1/24/22 is incorrect


Inquiry submitted 06/22/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/22/2022


Response #2:1. Special Provisions section 78-4.07 has been revised per Addendum 1, posted July 8, 2022.
2. Note 9 has been deleted from plan sheet L-1 per Addendum 1, posted July 8, 2022.
3. Updated Natina quote with pricing valid until April 2, 2023, is provided in revised Information Handout provided as part of Addendum 1, posted July 8, 2022.

Response posted 07/11/2022




Inquiry #10: ITEM #207, CONCRETE BARRIER, TYPE 60MGF- 210 LF:
The Concrete Barrier Quantity Chart on Q-3, 168 of 375, shows two (2) runs of 103 LF each. Construction Details sheet C-3, 23 of 375, shows the 60MGF from 317+18.50 to 318+20.99. Revised Standard Plan A77F, for CB60MGF indicates that the pay length is Station to Station, not the length of each side. This means that the actual pay length should be 103 LF. Item # 207 is not a Final Pay Item, so this would be a large under-run of quantity. Will CDOT correct the Bid item to the correct quantity?

Inquiry submitted 06/22/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/23/2022


Response #2:Addendum 1 revises the quantity of bid item # 207, concrete barrier (Type 60MGF) on the bid item list, and in the concrete barrier table on plan sheet Q-3, posted on July 8, 2022.
Response posted 07/11/2022




Inquiry #11: ITEM#208, CONCRETE BARRIER, TYPE 60MSC MOD 3:
Plan C-31, 51 of 375 gives some details for this Barrier. Please provide additional dimensioning for top-width and total height.

Inquiry submitted 06/23/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/23/2022


Response #2:Additional dimensioning provided for barrier on revised sheet C-31 of addendum 3.
Response posted 07/24/2022




Inquiry #12: Minor concrete (Stamped concrete) provide a detail. Plans refer to the specifications but those do not provide any information regarding sections.
Inquiry submitted 06/24/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/24/2022


Response #2:Stamped concrete pattern provided on revised sheet C-31 of addendum 3.
Response posted 07/24/2022




Inquiry #13: Is the AASHTO M326 HDPE pipeliner an acceptable culvert repair method for bid items 104? As it has been successfully used by other Caltrans Districts in the past. Thank you.
Inquiry submitted 06/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/27/2022


Response #2:No. Alternative storm drain materials will not be considered. Bid per contract documents.
Response posted 07/13/2022




Inquiry #14: In accordance with Topic 857 – Alternative Materials, in the Caltrans Highway Design Manual (HDM), 857.1 Basic Policy, will alternative storm drain materials be considered given STD Detail A62F?
Inquiry submitted 06/27/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 06/27/2022


Response #2:No. Alternative storm drain materials will not be considered. Bid per contract documents.
Response posted 07/13/2022




Inquiry #15: When will Caltrans respond to inquiry #3? This inquiry is nearly 4 weeks old. The linework for the proposed new work is missing from the layout sheets L3-5. This is needed to understand the proposed work and to verify quantities. If this is not provided soon, Caltrans will need to push the bid date.
Inquiry submitted 07/05/2022

Response #1:Your comments are noted.
Response posted 07/05/2022




Inquiry #16: What sheet shows the section for the POC approach? Sheet 7 refers you to Sheet 10 which does not have any information.
Inquiry submitted 07/10/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/11/2022


Response #2:Refer to sheet 352 of 375 “Retaining Wall Details” for the section for the POC approach. Refer to the notes on sheet 342 of 375 “General Plan” and abutment construction sequence on sheet 346 of 375 “Abutment Construction Sequence” for information on POC approach retaining walls.
Response posted 07/24/2022




Inquiry #17: ITEM #173, STAIN GALVANIZED SURFACES,EA- 180 EA:
Answers to Bidder's Inquiry #9, and Addendum #1 do not seem to meet the requirements of the Special Condition Section 78-4.07. Addn.#1 states "Apply stain to all visible surfaces of midwest guardrail system." The Natina Quote included in the Addn. #1 Information handout only includes steel posts.
Are MGS steel posts the only thing the Engineer wants stained?

Inquiry submitted 07/11/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/11/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #18: The permanent steel casing and cast-in-drilled-hole piling are the same diameter. Is it acceptable to install oversized permanent steel casing so that the pile can be drilled at the designed diameter of 66"?
Inquiry submitted 07/11/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/12/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022


Response #3:
Response posted 07/24/2022




Inquiry #19: Can corrugated steel pipe be used in lieu of the 3/8" permanent steel casing? If not, please specify the type of permanent steel casing required for the 66" cast-in-drilled-hole piling.
Inquiry submitted 07/12/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/12/2022


Response #2:No. Refer to section 49-3.02 of the Standard Specifications and page 17 of the Foundation Report for Chanticleer Avenue POC included in the Information Handout as described in section 2-1.06B. Please bid per the current contract bid documents.
Response posted 07/25/2022




Inquiry #20: Item Code 610103 AND 610108: 12" and 18" Alternative Pipe Culvert. What is the Allowable material and gauge if required.
Inquiry submitted 07/12/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/12/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #21: Drainage System #21 j --> 223 LF 18" RCP with conc backfill and System #21g--> 100 LF of 18" RCP with conc backfill but the information does not match up, isn't captured on the drainage quanties, confirm if these runs require conc backfill or not.
Inquiry submitted 07/13/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/13/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022


Response #3:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #22: The irrigation plans show a 2 inch master valve. However, the is no bid item for the master valve.
Please clarify under what item is the 2" master valve paid.

Inquiry submitted 07/13/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/13/2022


Response #2:The Irrigation Plan reflects the correct information. The 2" master valve is accounted for under "2" remote control valve (#206565) and IQ-1 (addendum #5 dated August 4, 2022).
Response posted 08/04/2022




Inquiry #23: Bid Item#99-Cold Plane AC for 1,780 SY captures the area for the rumble strip removal and per plan sheet C-25 it states that the rumble strip width is 4', which is not reflected accordingly in your summary of quantity sheet Q-4, clarify. The other cold planing areas are clearly identified as 0.17' at respective locations.

In addition to the cold plane areas it appears that the RHMA and HMA related to the removal of the rumble strip does not align with the quantities in the summary of quantities sheet Q-1, clarify.

Inquiry submitted 07/13/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/13/2022


Response #2:Sheet 166 (Q-1) and 169 (Q-4) are replaced in Ad3.
Response posted 07/29/2022




Inquiry #24: The Special Provisions on page 70 calls for a 16 station rain master eagle per the quote included. Bid item 70 and the plans, however, shows a 40-48 station irrigation controller.
Please clarify what how many stations are require for the controller. What controller is required?

Inquiry submitted 07/13/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/13/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #25: Bid item 62, Wood Mulch and 64, Shredded Mulch (6"), call for 1,850 and 1,030 CY of mulch, respectively. The drawings show both mulches at the same location.
Please clarify where does the two types of mulches will be install. Are they on top of the other?

Inquiry submitted 07/13/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/13/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #26: Per your Summary of Quantities on Sheet Q-1 Pavement Structure Quantities for
Sht L1-L2 (Pavement to be placed from rumble strip removal) Sta 259+96 to 271+12 states a total of 1,521 TN of RHMA please confirm the tonnage. Per the detail provided rumble strip is 4' wide.

Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Sheet 166 (Q-1) is replaced in Ad3.
Response posted 07/29/2022




Inquiry #27: Per the summary of quantities under the pavement edge treatment confirm the stationing for the last areas from K 335+08 to 348+59 job limits do not go to 348+59, clarify
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #28: Per the summary of quantities under the pavement edge treatment confirm the stationing for the last areas from K 335+08 to 348+59 job limits do not go to 348+59, clarify
Inquiry submitted 07/14/2022

Response #1:Duplicate of inquiry #27. See response to bidder inquiry #27.
Response posted 07/14/2022




Inquiry #29: Bid Item 133-Concrete backfill for 480 CY captures all of the work as shown on the detail on Plan Sheet DD-1 there is a total of 23 runs but not all of them are identified on the plan sheet confirm the qty of conc backfill and also 2 runs on System 21 are not aligning between the profile drawings and drainage summary quantities.
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022


Response #3:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #30: What is the specification for Bid Item 240 Water Meter Charges? What cost should be included in this item? (notes: 1-1/2" water meter shows on Plan Sheet IP-7, Soquel Water District charges ~ $90 k for new 1-1/2" water meter, no reference in project special provisions or standard specifications. Is this a new meter?

Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #31: What are the size, location and number of trees to be removed?


Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #32: Special Provision section 78-4.07A states that stain is to be applied to all visible galvanized surfaces of the Midwest guardrail system. This work is paid in item 173- Stain Galvanized Surfaces (EA). Per Item 197- Midwest Guardrail system (Steel Post) is paid by the lineal foot. There appears to be a discrepancy between the two items. How does the EA of item 173 relate to the LF of item 197?


Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #33: Please refer to Plan Sheet 76 (DD-4) for Transition Structure (RCB), please provide wall, slab and roof dimesions for transitions structures. Please also provide connection details between the transition structures and new/ existing RCP and existing 4'x4' RCB.



Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #34: Please refer to Plan Sheet 76 (DD-4) for Transition Structure (RCB), please provide theoretical span distance for transitions structures for rebar details.



Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #35: Please confirm the project will be awarded by 8/23/22 to meet the environmental requirements in the project.




Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Please place your bid in accordance with the current bid documents
Response posted 08/02/2022




Inquiry #36: Please detail the sequence of the of the fill/settlement platform work for Retaining Wall No. 2. Will the settlement be accomplished similar to the settlements required for Bridge No. 36-0124 (construct wall, fill, settle, construct wall to grade/barrier slab)?
Will the concrete quantity for Bridge No. 36-0124 be increased by the amount of the concrete required to pour to grade after the settlement at the approach walls? How is the additional length of rebar to be accounted for?

Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:There is no special sequence required, soldier piles for wall will not settle. The settlement period is meant for the fill behind the wall.

The quantities for structural concrete (retaining wall) and bar reinforcing steel (retaining wall) for the retaining wall “S” and retaining wall “N” do not reflect the unknown settlement. Section 12.3.1 “Settlement Under Embankments” of the Chanticleer POC Foundation Report provides the anticipated settlement. Bid the project accordingly.

Response posted 07/28/2022




Inquiry #37: Aside from the (2) trees identified for removal on Chanticleer within the project documents reference is made to the removal of an additional 33 trees, where is this quantity captured and paid shown on the plans.
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #38: Please confirm that the Miscellaneous Metal is to be painted to match color 14090 (green) in accordance with Section 59-3.
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Miscellaneous Metal (Bridge) and Isolation Casing do not need to be painted under standard specification 59-3. The bid opening date is 07/27/22. It is unlikely an addendum will be issued. Please bid under the current contract bid documents.
Response posted 07/21/2022




Inquiry #39: Clarify the clearing & grubbing limits, they are not clearly defined in the project plans.
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #40: Removal of DTBB is to take place in what Stage of construction?
Inquiry submitted 07/14/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/14/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #41: Bid Item 125 - 560218 Furnish Sign Structure - Are walkways required on the Static Sign Structures SD-1 & SD-3 (excludes CMS Sign)? A directive by Caltrans was issued removing walkways from most overhead sign structures however this has to be clarified job-by-job if walkways are needed or not.
Inquiry submitted 07/15/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/15/2022


Response #2:Walkways are not required.
Response posted 07/28/2022




Inquiry #42: It appears that there is a discrepancy on Plan Sheet Q-1 for HMA, error in the total. Confirm
Inquiry submitted 07/15/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/15/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #43: Per plan sheet DD-1 detail for adjust inlet to grade states "See Note 3" but there is no Note 3, provide Note 3. Also on sheet DD-1 there is a detail identified as Section A-A with a concrete cap identify which system this is associated with.
Inquiry submitted 07/15/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/17/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022




Inquiry #44: Per Section 59 (page 85) of the contractors specifications it indicates to clean and paint the new steel bridge where is the pay item for this scope of work?
Inquiry submitted 07/16/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/17/2022


Response #2:Refer to the table in section 59-2.01A(1) of the special provisions. Item 131, 590120 Clean and Paint Steel Soldier Piling, is the bid item for this scope of work. No further information will be provided. Please bid per the current contract bid documents
Response posted 07/21/2022




Inquiry #45: Under the summary quantities roadway embankment ADL material it is shown as a non paid embankment item @ 15,224 CY and yet you state is has to be disposed of at Class 1 facility is that material intended to go into an embankment as it is indicated in the summary of quantities or does this material have to be disposed of at a Class 1 facility.
Inquiry submitted 07/16/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/17/2022


Response #2:Plans and quantity show correct. The non-paid embankment item is at 3898 CY for (Type R-1)(ADL). The quantity at 15,220 CY is for roadway excavation of (Type R-1)(ADL), some of which will be used for embankment. On Sheet C-30, Note 1 states only "(Type Z-2)(ADL) is to be disposed at a class I disposal facility
Response posted 07/24/2022




Inquiry #46: Per your summary of drainage quantities final pay items #115-Structural Conc-Junction Structure is a total of 18 CY and Bid Item #116-Structural Conc-Box Culvert is 3 CY it appears the quantities stated are incorrect, revise.
Inquiry submitted 07/17/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/17/2022


Response #2:Plans and quantity are correct. The quantity for bid item 115, (F) - STRUCTURE CONCRETE, JUNCTION STRUCTURE on the Bid Item List is 10 CY. It is consistent with the STRUCTURE CONCRETE, JUNCTION STRUCTURE quantities on the Junction Structure Quantities table provided on Sheet D6. The quantity for bid item 116, (F) - STRUCTURAL CONCRETE, BOX CULVERT on the Bid Item List is 21 CY. It is consistent with the STRUCTURAL CONCRETE, BOX CULVERT quantities on the Drainage Quantities table provided on Sheet D6.
Response posted 07/19/2022


Response #3:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #47: Whale cutout Details Sheet 373 depicts whale sizes up to 26 ft in length and up to 8 ft in height. Since 3/8" Aluminum plates cannot be processed to accommodate these sizes, can these shapes be fabricate in separate pieces and butt jointed in the field (multiple pieces to make up the full cutout) or the pieces must be fully welded along joints in the shop to create one uniform integral unit shipped to the jobsite.
Inquiry submitted 07/18/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:Refer to plan sheets 372 and 373 of 375 and section 83-2.10 “Pedestrian Railing and Whale Cutouts” of the contract special provisions. Shop drawing submittals are specified and are submitted after contract award. Please bid per the current contract documents.
Response posted 07/24/2022


Response #3:Reference plan sheet 373. Reference revised special provision 83-2.10 in Addendum No. 5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #48: Provide cross sections for the 2,526 CY to be placed on the K-Line per the summary of quantities on Plan Sheet 166.
Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.

No additional typical cross sections will be provided, 2526 cy embankment is correct. Bid per current contract


Response posted 08/02/2022




Inquiry #49: Plan sheet SC-1 shows the temporary paving section of 0.33' HMA over 1.0' Class 2 ab. Plan sheets SC-4 & SC-7 show the temporary paving section as 0.50' HMA over 0.66' Class 2 ab. Please confirm which paving section the contractor should use.

Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022


Response #3:
Response posted 07/24/2022




Inquiry #50: Standard Specification section 19-5.03B Relitive Compaction requires 95% compaction to 2.5' below finish grade. Will this specification be required for the temporary pavement section?


Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:95% compaction to 2.5’ below finish grade is required for temporary pavement.
Response posted 07/27/2022




Inquiry #51: Sheet D-2 of the DRAINAGE PLANS, please clarify if Caltrans intends to have the DRAINAGE SYSTEM 2 installed without KRail.  Starting at STATION 270+60 of the “K” Line, Northbound side of edge of pavement, Drain Inlet TYPE GO (labeled as B) through Drain Inlet TYPE GO (labeled as J) are not showing on Sheet TH-2 of the STAGE 1 plans to be behind TYPE K Railing.



Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #52: Quantities shown on Sheet DQ-1 for Concrete Backfill (Pipe Trench) for Drainage System #2 & #5 quantities do not match actual backfill quantities needed to cover trench detail on Sheet DD-1 for Concrete Backfill.  Please confirm the quantity on Bid Item #133 is correct for the concrete backfill.




Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/19/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022.
Response posted 07/24/2022


Response #3:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #53: Plan sheet SC-1 shows the temporary paving section of 0.33' HMA over 1.0' Class 2 ab. Plan sheets SC-4 & SC-7 show the temporary paving section as 0.50' HMA over 0.66' Class 2 ab. Please confirm which paving section the contractor should use.

Inquiry submitted 07/19/2022

Response #1:Duplicate inquiry. See previous response.
Response posted 07/19/2022




Inquiry #54: Standard Specification section 19-5.03B Relitive Compaction requires 95% compaction to 2.5' below finish grade. Will this specification be required for the temporary pavement section?


Inquiry submitted 07/19/2022

Response #1:Duplicate inquiry. See previous response.
Response posted 07/19/2022




Inquiry #55: Sheet D-2 of the DRAINAGE PLANS, please clarify if Caltrans intends to have the DRAINAGE SYSTEM 2 installed without KRail.  Starting at STATION 270+60 of the “K” Line, Northbound side of edge of pavement, Drain Inlet TYPE GO (labeled as B) through Drain Inlet TYPE GO (labeled as J) are not showing on Sheet TH-2 of the STAGE 1 plans to be behind TYPE K Railing.



Inquiry submitted 07/19/2022

Response #1:Duplicate inquiry. See previous response.
Response posted 07/19/2022




Inquiry #56: Quantities shown on Sheet DQ-1 for Concrete Backfill (Pipe Trench) for Drainage System #2 & #5 quantities do not match actual backfill quantities needed to cover trench detail on Sheet DD-1 for Concrete Backfill.  Please confirm the quantity on Bid Item #133 is correct for the concrete backfill.




Inquiry submitted 07/19/2022

Response #1:Duplicate inquiry. See previous response.
Response posted 07/19/2022




Inquiry #57: Bid Item 118 - Precast Concrete Panels - indicates a Pay Quantity of 3,962 Sf [Final Pay]. Based on the "Pile Data Table" on Plan Sheet 336 of 375 we get a calculated Pay Quantity of 4,778 Sf. We realize this Bid Item is Final Pay but by our calculations this Item is an overrun of 816 Sf. or 20.6%. Without an adjustment of this Pay Item to something close to what is intended on the Plan Sheet we will have a grossly overstated cost for this Bid Item. Beyond that issue is the potential for a Bidder to take Caltrans pay quantity as reasonably accurate and significantly under price the actual intended work. Please revise this quantity to accurately reflect what is expected by Caltrans for this Bid Item.
Inquiry submitted 07/19/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/20/2022


Response #2:The limits of precast concrete panels are shown on sheet 337 of 375 (Retaining Wall No.2 - Typical Section). The quantity is correct. Please bid per current contract documents.
Response posted 07/21/2022




Inquiry #58: Bid item 204's quantity needs to be changed. Summary of quantities sheet Q-3 shows the limits of concrete barrier on the left from station 282+73.44 to station 291+50.00 as a total of 354 LF which should be 877 LF. Please clarify.
Inquiry submitted 07/20/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/20/2022


Response #2:
Response posted 07/24/2022


Response #3:Please place your bid in accordance with the current bid documents.
Response posted 08/08/2022




Inquiry #59: Plan Sheets 368 &369 of 375 show Pilasters "A" & "B" of which there are 8 ea. "A"s and 4 ea. "B"s. In what Bid Item are these reinforced concrete pilasters to be paid? Are they part of Bid Item 198 - Pedestrian Railing (Type A) or are they paid with the Structure Concrete, Retaining Wall, Bid Item 112. Also Special Provision section 83-3.01C refers to "integrally colored concrete" so are these Pilasters to be cast using colored concrete? If "integrally colored concrete" is to be used for the Pilasters is the 12" x 12" concrete curb on top of Retaining Wall "S" & "N" also constructed using "integrally colored concrete"?
Inquiry submitted 07/20/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/20/2022


Response #2:Reference plan sheets 368, 369, and 370 of 375. Reference special provisions section 83-2.10 Pedestrian Railing and Whale Cutouts. The pilasters or portions of the pilasters shown within the limits of Pedestrian Railing (Type A) or Pedestrian Railing (Type B ) are included with Pedestrian Railing bid items. Pilasters for pedestrian railing are not described to be integrally colored.
Response posted 07/21/2022




Inquiry #60: Bid Item #14-PCMS shows a quantity of 1 each , which is not what is depicted on the plans, verfiy.
Inquiry submitted 07/20/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/20/2022


Response #2:Bid Item #14 was deleted per addendum 3. item #243 "PORTABLE CHANGEABLE MESSAGE SIGN (LS)" was added per addendum 3.
Response posted 07/29/2022




Inquiry #61: Per section 83-3.01A of the special provisions "Adding integrally colored concrete", does this pertain to all concrete barrier types?
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:All of the concrete barriers have integrally colored concrete.
Response posted 07/29/2022




Inquiry #62: Item 200 Whale Cutouts - are we installing the 26' long in one piece or we can install it in 2 section and also the cut out A,B, D & G.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Reference plan sheet 373. Reference revised special provision 83-2.10 in Addendum No. 5 dated August 4, 2022.
Response posted 07/24/2022




Inquiry #63: Refer to bid item list , bid item #82 indicates 2 1/2" plastic pipe Schedule 40. However, refer to irrigation quantity table on sheet IQ-1, 2 1/2" plastic pipe is Class 315. Please clarify.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Attention is directed to addendum #3 dated July 22, 2022
Response posted 07/24/2022




Inquiry #64: Refer to irrigation quantity table on sheet IQ-1, size of flow sensor is 2" . However, refer to callout on sheet IP-7, flow sensor size is shown as 1 1/2". Please clarify.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #65: Clarify what bid item is supposed to cover the cost of 2" electrical conduit installed in barrier as shown on sheet IP-2 & IP-3.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Bid Item #206560 includes the cost of the 2” electrical conduit installed in the barrier as shown on sheets IP-2 & IP-3.
Response posted 08/01/2022




Inquiry #66: Refer to sheet IP-7, (80 LF) of 8" corrugated HDPE pipe needs to be installed under existing street. However, the corrugated pipe can not be installed by directional boring or jack and drill as required per related specification. Please clarify.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Please place your bid in accordance with the current bid documents.
Response posted 08/01/2022




Inquiry #67: Refer to bid item list, item #78, irrigation controller shall be Wall-mounted. However, per Irrigation quantity table on sheet IQ-1, pedestal mounted is specified. Please clarify.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #68: No size is provided for combination air release valves assembly. Please clarify.
Inquiry submitted 07/21/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/21/2022


Response #2:Comply to Section 20-2.13A.
Response posted 08/01/2022




Inquiry #69: In Addendum #3, the revised Bid Schedule and Plan Sheet IP-7 now shows Bid Item #82 2 1/2" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LINE) removed from this project bid. Please clarify if Bid Item #84 - 8" CORRUGATED HIGH DENSITY POLYETHYLENE PIPE CONDUIT will also be removed from this project bid since the supply line is no longer needed?
Inquiry submitted 07/23/2022

Response #1:Your inquiry is under review. However, due to the limited time between the inquiry submittal and the bid opening date, a response may not be provided. If a response is not provided, please bid per current contract documents.
Response posted 07/24/2022


Response #2:Bid item #84 - 8" CORRUGATED HIGH-DENSITY POLYETHYLENE PIPE CONDUIT will not be removed from this project. A supply line is still required for this project. The supply line will be 2 ½” PLASTIC PIPE (CLASS 315) (SUPPLY LINE). Please refer to inquiry bid #63.
Response posted 08/04/2022




Inquiry #70: Please refer to plan sheets for Retaining Wall 2 and details related to pile cover plate, and precast panel. Section K-K, and L-L on plan sheet 339 indicate that a ½” x 18” x 18” cover plate is to be shop welded (each flange and both sides of web) to the top of each soldier pile. Plan sheet 337 shows the top plate to receive undercoat and finish coat of paint to all surfaces. Section C-C on plan sheet 338 indicates the precast panels are 10” wide and the top elevation the precast panels is the bottom of the concrete barrier slab. We have the following questions/ comments:
1. Based on the dimensions of the precast panels provided on plan sheet 338, the panels must be placed between the soldier pile beams from the top. This is not possible with the top cover plate shop installed. Can these plates be field welded?
2. The cover plate is shown to be welded on both the flanges and each side of the web. If the cover plate is field welded, there is insufficient room to weld the plate to the web, and to also paint the underside of plate as access is blocked by the precast panel. Can the requirement of welding the plate to the web be removed?
3. Please clarify Note 1 on plan sheet 338. If the top panel is less than the minimum height of 1’-11”, then is the contractor to just add the value to a lower panel? For example the precast panel height between piles 13 and 14 is 9’ – 4 ½”. Does this result in two 3’-11” panels plus one panel that is 1’ – 6 ½”? Or is it one panel 3’-11” and one panel 5’ – 5 ½”?

Inquiry submitted 07/24/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022


Response #3:To clarify, for item 3: Reference plan sheet 338 of Addendum No. 03 dated July 22, 2022. Reference Note 1 on plan sheet 338. Of the panel height options cited in the bidder inquiry, a 3’-11” top panel and a 5’-5.5” next lower panel complies with the current bid documents.
Response posted 08/05/2022




Inquiry #71: Bid item #84, 8" Corrugated High Density Polyethylene Pipe has a table for Concrete Backfill on Sheet Q-4 – Irrigation Conduit.  Please provide a Trench Detail or clarify if contractors will use the same trench detail shown for Concrete Backfill on DD-1.  Also, quantities for Concrete Backfill for the CHDPE on Q-4 do not reflect actual backfill for any typical trench for an 8” pipe – please confirm quantity shown on table  Q-4 – Irrigation Conduit. 
Inquiry submitted 07/24/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #72: addendum 3 deleted item 27, temporary inlet protection, and 28 Temporary straw waddle. Is the state going to perform this work? These 2 items are great examples of DBE work you just deleted, goal of 27%. Every job we bid has these 2 items of work, but now for what ever reason you delete it, please clarify!
Inquiry submitted 07/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #73: Upon review of Addendum 3, it is apparent there is still an error with the bid quantity for Bid Item 133) Concrete Backfill (Pipe Trench). The Engineer’s estimated quantity is 440 CY. The actual theoretical quantity (based on the detail on sheet DD-1 and the Summary of Quantities sheet Q-4) is actually 1,140 CY. This is a Final Pay Item that has been erroneously misrepresented; please rectify.
Inquiry submitted 07/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #74: Plan sheet DD-5 shows details for Junction Structures (JS) No. 1 & No. 3. Drainage Profile sheets DP-6 & DP-8 call out Std Plans D91A for the JS. Please clarify what details we are to use for Bid Item 115) Structure Concrete, Junction Structure. Note: The Engineer’s estimated quantity is 10 CY; it is Final Pay. If we use Std Plans D91A, then the theoretical quantity is actually 27.5 CY.
Inquiry submitted 07/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #75: Please refer to plan sheets for Retaining Wall 2 and details related to pile cover plate, and precast panel. Section K-K, and L-L on plan sheet 339 indicate that a ½” x 18” x 18” cover plate is to be shop welded (each flange and both sides of web) to the top of each soldier pile. Plan sheet 337 shows the top plate to receive undercoat and finish coat of paint to all surfaces. Section C-C on plan sheet 338 indicates the precast panels are 10” wide and the top elevation the precast panels is the bottom of the concrete barrier slab. We have the following questions/ comments:
1. Based on the dimensions of the precast panels provided on plan sheet 338, the panels must be placed between the soldier pile beams from the top. This is not possible with the top cover plate shop installed. Can these plates be field welded?
2. The cover plate is shown to be welded on both the flanges and each side of the web. If the cover plate is field welded, there is insufficient room to weld the plate to the web, and to also paint the underside of plate as access is blocked by the precast panel. Can the requirement of welding the plate to the web be removed?
3. Please clarify Note 1 on plan sheet 338. If the top panel is less than the minimum height of 1’-11”, then is the contractor to just add the value to a lower panel? For example the precast panel height between piles 13 and 14 is 9’ – 4 ½”. Does this result in two 3’-11” panels plus one panel that is 1’ – 6 ½”? Or is it one panel 3’-11” and one panel 5’ – 5 ½”?

Inquiry submitted 07/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Duplicate of inquiry #70.
Response posted 08/02/2022




Inquiry #76: Bid item #84, 8" Corrugated High Density Polyethylene Pipe has a table for Concrete Backfill on Sheet Q-4 – Irrigation Conduit.  Please provide a Trench Detail or clarify if contractors will use the same trench detail shown for Concrete Backfill on DD-1.  Also, quantities for Concrete Backfill for the CHDPE on Q-4 do not reflect actual backfill for any typical trench for an 8” pipe – please confirm quantity shown on table  Q-4 – Irrigation Conduit. 
Inquiry submitted 07/25/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/25/2022


Response #2:Duplicate of inquiry #71.
Response posted 08/02/2022




Inquiry #77: Inquiry #41 still has not been answered? Need to know if Walkways are required on the overhead sign structures or not?

Inquiry submitted 07/26/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/26/2022


Response #2:Walkways are not required on the overhead sign structure.
Response posted 07/28/2022




Inquiry #78: Please verify if all rebar on the concrete barriers including the roadway barrier to be epoxy coated as stated in special provision section 83-3.02C

Inquiry submitted 07/26/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/26/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #79: Refer to sheet L-5, There are multiple callouts for concrete barrier on “C” line just below the main “K” line, but the lines connected to the callouts do not lead anywhere. Clarification needs to be given about the exact location of the barrier as they are listed incorrectly on the summary of quantities as well. Approximate stationing for the inquiry is (“K”) 312+50 to 317+50; and 321+00; all below mainline.
Inquiry submitted 07/26/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/26/2022


Response #2:Attention is directed to addendum #5 dated August 4, 2022.
Response posted 08/04/2022




Inquiry #80: On sheet C-25 a Barrier detail is given titled “CB (type 60M) at right shoulder”. The state needs to clarify the specific location this detail applies to by adding exact station numbers.
Inquiry submitted 07/26/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/26/2022


Response #2:The locations are shown on L-3 and Q-3 sheets.
Response posted 08/01/2022




Inquiry #81: 1) On sheet 175 Sound Wall Quantities is calls for 3391 sq.ft. but on the Plans sheet 173 it shows the wall to be 450ft. long and 8 ft. Tall which is 3600 sq.ft. Which is accurate as this is a Final pay Item?
2) Are we to use the 2018 Revised Standard Plans B15-3 for all rebar layout?
3)The Aesthetics on sheet 174 are for a 12ft. Tall Wall and this wall is only 8ft. Tall.
Should we eliminate the bottom 7 coursces?

Inquiry submitted 07/26/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/27/2022


Response #2:1. See revised sheet 175
2. Yes, B15-3 is included in Ad5.
3. Please place your bid in accordance with the current bid documents.
Response posted 08/08/2022




Inquiry #82: Does Caltrans have a source of water avaialble to the contractor for this project? The local water agency charges $50.56 per 1,000 gallons which is very expensive for construction water.

Inquiry submitted 07/27/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/27/2022


Response #2:Contractor to supply water for this project.
Response posted 07/29/2022




Inquiry #83: Due to the magnitude of Addendum 3 issued July 22nd, we appreciate the Department’s decision to postpone the bid date from July 27th to August 10th via Addendum 4 issued July 26th. However, in addition to the extensive amount of information provided in Addendum 3, approximately 20 bidder inquiries remain unanswered at this time. Additionally, there are multiple, very large projects bidding August 10th and August 11th. Would the Department please consider postponing the bid date one additional week to August 17th

Inquiry submitted 07/27/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 07/27/2022


Response #2:There is no plan to postpone Bid Opening.

Please place your bid in accordance with the current bid documents

Response posted 07/29/2022




Inquiry #84: Inquiry #20: Item Code 610103 AND 610108: 12" and 18" Alternative Pipe Culvert. What is the Allowable material and gauge if required. Previously sent RFI on 7/12/2022 #20.
Inquiry submitted 08/01/2022

Response #1:Duplicate question. See response to #20, once posted.
Response posted 08/02/2022




Inquiry #85: Please clarify which item is the master valve per your response to inquiry 22.

Inquiry submitted 08/09/2022

Response #1:Given the late submittal of this inquiry, a response is not possible by bid opening today.
Response posted 08/10/2022


Response #2:The 2" master valve is accounted for under "2" remote control valve (#206565).
Response posted 08/10/2022




Inquiry #86: The planting legend does not show soil amendment being use. However, the planting area quantities shows soil amendment for the cultivation area. Yet, no cultivation is shown anywhere else in the plants.
Please clarify under what item is cultivation being paid. What areas get cultivated?

Inquiry submitted 08/10/2022

Response #1:Given the late submittal of this inquiry, a response is not possible by bid opening today.
Response posted 08/10/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.