Inquiry #1: CRCP requires adequate access parallel with lane for placer and trucks. How did the department determine the staging plan would accommodate CRCP placement of #2 lane?

Please consider modifying the staging plans to put both NB and SB traffic on one side of the road to accommodate construction of the # 2 lanes.

This restaging concept will reduce K rail demand, improve efficiency, eliminate the need to temporarily build up outside shoulders (if allowable), and save overall time to construct.

Inquiry submitted 02/06/2019

Response #1:Submitted for consideration.
Response posted 02/06/2019


Response #2:Bid per the current contract documents.
Response posted 02/07/2019




Inquiry #2: Will the department allow the contractor to place a detour to accommodate both NB and SB traffic on current NB or SB section of roadway, eliminating all traffic from the other direction, allowing complete width of roadway to be constructed as one stage?
Inquiry submitted 02/10/2019

Response #1:Submitted for consideration.
Response posted 02/11/2019


Response #2:Use of a median crossover for staging will not be permitted. Bid per the current contract documents.
Response posted 02/11/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.