Viewing inquiries for 05-1F9204

Submit new inquiry for this project


Inquiry #1: In light of the unprecedented fires throughout California and California’s emphasis to build “resilient” infrastructure, will Caltrans follow its own High Design Manual Section 850-34 dated December 30th 2015 which warns against installing plastic pipe in areas with a potential for fire? This project lists Alternative Pipe Culvert in the Bid Schedule which includes plastic pipe as an acceptable product.
Inquiry submitted 12/03/2020

Response #1:Submitted for consideration.
Response posted 12/03/2020


Response #2:Submitted for consideration.
Response posted 12/03/2020


Response #3:Please place your bid in accordance with the current contract documents and specifications.
Response posted 12/10/2020




Inquiry #2: There are bid items for Type C and S drainage piping which is single and double wall pipe, however, the plans call for butt-fused HDPE. Please clarify which pipe is correct.
Inquiry submitted 12/21/2020

Response #1:Your inquiry has been submitted for review.
Response posted 12/21/2020


Response #2:Please place your bid in accordance with the current contract documents.
Response posted 01/04/2021




Inquiry #3: How is the concrete barrier removal and replacement being paid for (where drainage lines go underneath)?
Inquiry submitted 12/23/2020

Response #1:Your inquiry has been submitted for review.
Response posted 12/23/2020


Response #2:Attention is directed to 5-1.01 GENERAL of the Standard Specifications. Barrier removal is not required.
Response posted 12/24/2020




Inquiry #4: For the AC replacement of trenched areas, what is the existing road section? I don't see that indicated on shts X1 thru X6.
Inquiry submitted 12/29/2020

Response #1:The existing AC structural section in all areas of the excavation is 0.85' Asphalt Concrete.
Response posted 12/30/2020




Inquiry #5: This project is located in a [moderate to high] Fire Hazard Severity Zones in State Responsibility Area (SRA) adopted by CalFire on November 7, 2007 (reference: fhsz_map44). Plastic pipe, specifically HDPE, is selected as drainage pipe material, are the most susceptible to damage from fire according to Highway Design Manual section 855.5 . Furthermore, Santa Cruz County experienced the Santa Cruz CZU Fire (2020) that burned and melted multiple HDPE culverts.

Will bid items No. 34, 35, 36 remain as plastic pipe or specified reinforced concrete pipe?

Inquiry submitted 12/29/2020

Response #1:Please place your bid in accordance to the current contract documents
Response posted 12/30/2020




Inquiry #6: The DR determines the thickness and weight of fusible HDPE pipe. In the past this information is located on the Q sheets. The standard specifications do not provide this information. What is the DR requirement for the HDPE Pipe?
Inquiry submitted 12/30/2020

Response #1:Your inquiry has been submitted for review.
Response posted 12/30/2020


Response #2:With respect to the Dimension Ratio, Attention is directed to section 64, "Plastic Pipe" of the contract specifications and the referenced ASTM & AASHTO standards.
Response posted 12/31/2020




Inquiry #7: Can the State please postpone this bid by at least 1 week? Additional clarification will be needed regarding the pipe material.
Inquiry submitted 01/04/2021

Response #1:Your inquiry has been submitted for review.
Response posted 01/04/2021


Response #2:Please place your bid in accordance with the contract documents. The bid opening will not be delayed.
Response posted 01/04/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.