Viewing inquiries for 05-1G7504

Submit new inquiry for this project


Inquiry #1: Currently the material procurement for poles are approximately 20-22 weeks. The project does not have sufficient time to procure the materials. Please advise.
Inquiry submitted 03/12/2019

Response #1:Refer to special provisions notice to bidders for number of working days and section 8 prosecution and progress. Bid per special provisions.
Response posted 03/13/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.