Inquiry #1: Why doesn't Caltrans have nighttime work hours from PM 47.6 to 51.3? Only 7.5 daytime work hours in that section would make the work very expensive.
Inquiry submitted 01/07/2019

Response #1:Submitted for consideration.
Response posted 01/07/2019


Response #2:Residential housing nearby restricts the nighttime work hours. Bid per current contract documents.
Response posted 01/08/2019




Inquiry #2: Would Caltrans be able to allow 2 shifts between grinding and paving? The specification for grinding and paving the same shift would not be possible with detector loop installation the same day also.
Inquiry submitted 01/07/2019

Response #1:Submitted for consideration.
Response posted 01/07/2019


Response #2:Refer to Addendum No. 1, dated January 15, 2019.
Response posted 01/15/2019




Inquiry #3: Would Caltrans allow for the specified flex start by July 15, 2019 instead of June 10, 2019? The specification for a July 15th start would allow 25 work days to complete the work in the PM 47.6 to PM 51.3 section.
Inquiry submitted 01/07/2019

Response #1:Submitted for consideration.
Response posted 01/07/2019


Response #2:Refer to Addendum No. 1, dated January 15, 2019.
Response posted 01/15/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.