Inquiry #1: Is the invasive plant management work to be completed during the 230 working days excluding plant establishment? Or is it to be through the 980 working days of the entire contract? Please advise.
Inquiry submitted 08/28/2019

Response #1:Section 20-6 includes specifications for controlling invasive plants. Work for invasive plant management begins within 30 working days of contract approval and continues for the life of the contract.

Response posted 08/29/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.