Viewing inquiries for 06-0Q3204

Submit new inquiry for this project


Inquiry #1: Per spec section 19-7.04 "The payment quantity for imported borrow paid by theoretical volume basis is the volume determined from the planned or authorized cross section for embankments and the measured ground surface adjusted by subtracting the theoretical quantities of material from excavations." This clearly defines how the import borrow is paid, however it does not clearly state if quantities are based per stage or at completion. As this project has 2 stages, will the state please determine if the imported borrow pay quantity is per stage or at completion of the project?
Inquiry submitted 02/14/2018

Response #1:Submitted for consideration.
Response posted 02/15/2018


Response #2:Contractor's attention is directed to the Stage Construction Sheets SC-1 and SC-2 as well as the roadway quantities table on Quantity Sheet Q-1, for location and staging of imported borrow. The final imported borrow pay quantity is at completion of the project.
Response posted 02/20/2018




Inquiry #2: This project requires much more import than is stated in the import quantity in Phase 1. Phase 2 does not need any import therefore the required import in phase 1 should match the Bid Quantity. Can the state please adjust this Bid Item.
Inquiry submitted 02/21/2018

Response #1:Submitted for consideration.
Response posted 02/21/2018


Response #2:Refer to Addendum No. 3, dated March 8, 2018.
Response posted 03/08/2018




Inquiry #3: We would like some Clarification on Bid item No. 66 Remove Chain Link Fence. I noticed that the fence that is to be removed appears to be an existing bared wire fence. Please confirm that the existing barbed wire fence, is the fence that is to be removed under bid item No. 66.
Inquiry submitted 02/22/2018

Response #1:Submitted for consideration.
Response posted 02/22/2018


Response #2:Refer to Addendum No. 3, dated March 8, 2018.
Response posted 03/08/2018




Inquiry #4: The twenty five days to build stage 2 seems completely unreasonable unless the project is double shifted with overtime. Considering the contract is 75 days and the contractor has 50 days to build the smaller stage of the project and only 25 days to build the larger stage and that includes cure on the JCPC, which could be the entire stage 2 duration. There is also curb & gutter and sidewalk, which also make take close to the entire stage 2 duration Is it the intent of Caltrans to force the extra costs and manpower to complete stage 2 in 25 days???
Inquiry submitted 02/24/2018

Response #1:Submitted for consideration.
Response posted 02/26/2018


Response #2:Refer to Addendum No. 3, dated March 8, 2018.
Response posted 03/08/2018




Inquiry #5: With the current staging of the contract Caltrans has seemed to create a project that requires import, but also requires export. Is that Caltrans' intent regarding the building of this contract??
Inquiry submitted 02/24/2018

Response #1:Submitted for consideration.
Response posted 02/26/2018


Response #2:Refer to Addendum No. 3, dated March 8, 2018.
Response posted 03/08/2018




Inquiry #6: On sheet L-2 there is a fill line shown on the North end of the page. After referring to the cross sections provided, it appears that line should be a Cut line, as there is supposed to be a drainage ditch running along the North side of the round about. Can the State please confirm if the Layout sheet or the Cross section is correct?
Inquiry submitted 02/27/2018

Response #1:Submitted for consideration.
Response posted 02/28/2018


Response #2:Refer to Plan Sheets X-1, 2, and 3 provided for the locations of the ditch flowline and catch points. Supplemental cross sections provide additional details.
Response posted 03/08/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.