Viewing inquiries for 06-0V9104

Submit new inquiry for this project


Inquiry #1: There is no Item to remove irrigation facilities? Plan sheet ID-1 shows an air relief valve, flush valve, and pipe to be removed. Please advise as to if we are responsible with that portion of work.
Inquiry submitted 08/26/2019

Response #1:Submitted for consideration.
Response posted 08/26/2019


Response #2:Refer to Addendum No. 1, dated August 29, 2019 and section 17-2.01 of the special provisions for removal of irrigation within clearing and grubbing limits.
Response posted 08/30/2019




Inquiry #2: Please confirm the department will pay all fees related to SCE and PG&E installation services required by this contract. Is there an estimated duration the bidders should anticipate in the overall schedule to complete? It is our experience these utility companies have very long lead times.
Inquiry submitted 09/04/2019

Response #1:The contractor should refer to section 87-1.03L(1) of the standard specifications and the project plans for work pertaining to service connections. The contractor should also refer to section 8 and page 1 of the Special Provisions for the contract duration.
Response posted 09/04/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.