Viewing inquiries for 06-0W1704

Submit new inquiry for this project


Inquiry #1: Hello:

On Sheet No. 83 of the project plans, the sound wall aesthetics are provided. Please indicate if Split-face texture for the CMU sound walls are required on both sides or only one side of the wall.


Inquiry submitted 08/31/2022

Response #1:Attention is direct to plan sheet "Sound Wall Details" SW-2 (83 of 239). Reference the schedule with the heading "Block texture (Both Sides)".
Response posted 09/01/2022




Inquiry #2: Hello:

On Sheet No. 82 of the project plans, the sound wall profiles are provided. After reviewing the expansion joint spacing there's a problem with this spacing not being modular for 16" long (1.33') CMU. On masonry sound walls, aesthetically it looks best to have expansion joints use full 16" CMU units between each other, to provide a masonry wall without any slivers or 2"-3" pieces.

An expansion joint of 48'-0" provides (36) equal blocks between, but when you introduce an expansion joint spacing of 37'-0", which is out of modular, it creates a (27 and 3/4") blocks spacing. In other words you have a unit 4" shorter and the unit below that in a running bond will be a 4" sliver.

This wall is 976.02 L.F., which roughly about (732) full size 16" units long. Please consider re-adjusting the expansion joints spacing so that the finished CMU wall looks aesthetically correct. There might be miters needed at the angle points, but those can done in the field.

Thanks.


Inquiry submitted 08/31/2022

Response #1:Your inquiry has been submitted for review.
Response posted 09/01/2022


Response #2:Attention is directed to Addendum No.1 dated September 23, 2022. Please place your bid in accordance with the current bid documents.
Response posted 09/23/2022




Inquiry #3: On sheet #83 of the project plans, the schedule and section call for Block Type "A" to be a 12"x8"x16" Split-face-2Sided 3-Scored CMU. Is this the intention of the designer?

On most of the Caltrans projects we've built an 8"x8"X16" Split-face-2Sided 3-scored block is usually used to top off the wall. A 12"x8"x16" is a massive unit, and with a required 8" core, could clock in at about 90lbs per unit.

A typical 8"x8"X16" Split-face-2Sided 3-scored on top of a regular 8"x8"x16" Split-Face-2Sided units will provide a overhang of about 1-1/4" on each side. While a 12"x8"x16" Split-Face-2Sided 3score unit will provide 3" of overhang on each side. Again a 12" version is a massive unit.

Please provide an email address and I can provide photos from the manufacturer to send over to the state for a comparison.

Thanks.

jonathan@reyes-reycon.com


Inquiry submitted 09/09/2022

Response #1:Your inquiry has been submitted for review.
Caltrans bidder inquiry email address: cr.bidders.questions@dot.ca.gov
Response posted 09/09/2022


Response #2:Please place your bid in accordance with the current bid documents. Thank you
Response posted 09/20/2022




Inquiry #4: The notice to bidders states:
"Complete the work, excluding plant establishment work, within 370 working days.
Complete the work, including plant establishment work, within 370 working days.
Complete the plant establishment work within 250 working days."

Please clarify, how many working days are allowed excluding plant establishment work?

Inquiry submitted 09/15/2022

Response #1:Your inquiry has been submitted for review.
Response posted 09/19/2022


Response #2:Attention is directed to Addendum No.1 dated September 23, 2022. Please place your bid in accordance with the current bid documents.
Response posted 09/23/2022




Inquiry #5: Per Inquiry Question #3 response......."Response #2:Please place your bid in accordance with the current bid documents. Thank you"

I just got off the phone with both of the (2) largest and closest block Manufacturers to Fresno, Baslite Concrete Products out of Selma, CA and Angelus Block Co. Bakersfield, CA. This massive unit, a 12"x8"x16" 4Scored-2Sided Split-2Sided with an 8" CORES does not exist. They do not have the mold or parts to assemble or create it. They both mentioned it would require a custom molds & parts that could range anywhere between $12,000 to $20,000 per configuration and could take about 10+ months to even aquire the mold if approved. This is only the mold cost, which this project would have to absorb and that does not even include the cost of the unit itself. There's also bondbeams and 8" Halves that would have to be made. The total amount of 4Scored units required for this project would only be about 2,300 units.

Please reconsider your statement and if need be I can provide you the phone numbers of both of the manufacturers if you need to confirm the information. You can also reach out to me if you have questions or need clarification.

Thanks,

Jonathan Reyes
REYCON CONSTRUCTION, INC.
(805) 525-5256
jonathan@reyes-reycon.com

Inquiry submitted 09/21/2022

Response #1:The Department has determined this block is available. Allow time for shipment in your schedule.

Please place your bid in accordance with the current contract documents. Thank you.
Response posted 09/23/2022




Inquiry #6: Per section 19-15.01C(7), it states that the Contractor must submit inertial profile smoothness reports prior to work, for each month of the project by the 5th day of the month, and after the work has completed. This is in relation to the trenchless construction work.

It also repeats this requirement in 19-15.01D(5)(b).

Will the state please confirm IP smoothness reports are required to be submitted as stated above?

Inquiry submitted 09/23/2022

Response #1:Pavement smoothness is required for this contract. Please place your bid in accordance with the current bid documents.
Response posted 09/27/2022




Inquiry #7: Will the State please provide the Annual Average Daily Traffic volume for this project?
Inquiry submitted 09/23/2022

Response #1:Annual Average Daily Traffic is abbreviated in the bid documents as ADT. The Annual Average Daily Traffic volume is 165,500 as shown in the Design Designation table shown on plan sheet X-1 (sheet no. 2 of 239)
Response posted 09/27/2022




Inquiry #8: The layout plans don't show any tree removal. Does Caltrans expect all trees to remain in place? If not how many trees can the contractor expect to remove?
Inquiry submitted 09/28/2022

Response #1:Your inquiry has been submitted for review.
Response posted 09/28/2022


Response #2:See Note 2 on Sheet L-1 which directs the contractor to the construction detail sheets for tree removal details. Specifically the tree removal is shown on construction detail sheets C-5 through C-7.
Response posted 09/28/2022




Inquiry #9: Irrigation quantities IQ-1 has a table for minor concrete (Misc Construction)? It shows concrete for IP-2, IP-3, and IP-4, please advise if this is for concrete collars around valve boxes or what?
Inquiry submitted 09/29/2022

Response #1:The minor concrete (miscellaneous construction) quantity shown in the table on IQ-1 is for the concrete collars around the valve boxes.
Response posted 10/02/2022




Inquiry #10: What type of joint (Isolation or Tied) will be required between the existing ETW and the new Auxiliary JPCP lane? If an Isolation joint is required, will Caltrans please add a bid item for this work?
Inquiry submitted 09/30/2022

Response #1:The joint will be contain tie bars. Attention is directed to Standard Plan Sheet P3B & the associated notes for the condition.
Response posted 10/02/2022




Inquiry #11: What type of joint (Isolation or Tied) will be required between the existing ETW and the new Auxiliary JPCP lane? If an Isolation joint is required, will Caltrans please add a bid item for this work?
Inquiry submitted 09/30/2022

Response #1:Duplicate Question -
Response posted 10/02/2022




Inquiry #12: Please detail the configuration of the wall drains and the Shotcrete (Pipe through wall detail on Sheet 37). When is it anticipated that the installation of the pipe and Minor Concrete Backfill would be performed as it is behind and under the plane of the Shotcrete?
Inquiry submitted 10/03/2022

Response #1:Your inquiry has been submitted for review.
Response posted 10/07/2022


Response #2:Attention is directed to Addendum No. 4 dated October 17, 2022. Please place your bid in accordance with the current bid documents.
Response posted 10/17/2022




Inquiry #13: It is anticipated that the Soil Nails will miss the Sign Structure Foundations? The Sign Structure piles are 60" diameter and the Soil Nail spacing is 5'. This does not leave much room for construction tolerances.

Inquiry submitted 10/03/2022

Response #1:Yes, refer to the Developed Mirrored Elevation (Soil Nail Wall) on sheets 175 and 217 of 239 for the soil nail spacings near the sign foundation. Please bid per the current contract plans.
Response posted 10/07/2022




Inquiry #14: Additional excavation and backfill below the grading plane is necessary for construction of the soil nail retaining wall. Will Caltrans add additional quantity of Roadway Excavation for this necessary work (approximately 6,500 CY)?
Inquiry submitted 10/03/2022

Response #1:There is no additional payment for excavation required below the retaining wall. Attention is directed to the the Retaining Wall plan details "Limits of Excavation and Backfill" of the contract plans, & sections 5-1.01, "General", & 9-1.03, "Payment Scope" of the Standard Specifications. Please place your bid in accordance with the current contract documents.

Response posted 10/07/2022




Inquiry #15: Will Caltrans allow the use of a form liner for bid item 76 “Concrete Surface Texture (Ripped Reinforcing Bar)”?
The special provisions under section 51-1.03G(1) state the “texture must simulate the appearance of concrete with embedded reinforcing bars and adhering concrete ripped from it. Bar imprints must be from no.5 or 6 deformed bars….”
This would seem to allow the use of a form liner. However the plans indicate on sheet 236 a very specific detail for the layout and placement of the #6 Rebars to be ripped out. Will Caltrans allow a form liner for Item 76?

Inquiry submitted 10/03/2022

Response #1:No a form liner is not allowed for this application. The detail shown in Retaining Wall No. 3 Architectural Treatment Details apply. Please place your bid in accordance with the current bid documents.
Response posted 10/04/2022


Response #2:Your inquiry is has been resubmitted for review.
Response posted 10/07/2022


Response #3:Attention is directed to Addendum No. 4 dated October 17, 2022. Please place your bid in accordance with the current bid documents.
Response posted 10/17/2022




Inquiry #16: The Information Handout part 5 page 74 note (a) includes notes to add to the specifications. In particular it notes to shotcrete the excavation facing within 24 hours after soil nails or ground anchors have been installed. And it states to Not leave excavation facing open for more than 24 hours. The special provisions are ‘silent’ on this. The standards state if stability testing is not performed, apply shotcrete facing during the same work shift that the excavation is performed. Will Caltrans allow the contractor to place shotcrete the next shift but within 24 hours of excavation similar to the Information Handout?
Inquiry submitted 10/03/2022

Response #1:Refer to the 2nd sentence in the 4th paragraph of section 19-3.03K of the standard specifications.
Response posted 10/07/2022




Inquiry #17: Clarify the type of irrigation controllers, no.456 on sheet IP-1 and no.458 on sheet IP-4. Are these controllers conventional or two-wire system?
Inquiry submitted 10/03/2022

Response #1:Your inquiry has been submitted for review.
Response posted 10/07/2022


Response #2:Attention is directed to Addendum No. 4 dated October 17, 2022. Please place your bid in accordance with the current bid documents.
Response posted 10/17/2022




Inquiry #18: Confirm that maintain existing planted areas scope of work, line item no.41 is limited to those existing plants shown on planting plans only. Otherwise, provide the limit or boundary for the existing planted areas needs to be maintained.
Inquiry submitted 10/03/2022

Response #1:The "Maintain Existing Planted Areas" are shown on the plans. Please place your bid in accordance with the current bid documents.
Response posted 10/05/2022




Inquiry #19: Plan sheet C-4 shows rock blanket over a concrete and rebar footing and it looks like the cobble is imbedded in the footings concrete. Is this the case or is the rock blanket put on after the footing is complete? If the rock blanket is separate how thick is it and what size is the cobble?
Inquiry submitted 10/12/2022

Response #1:Your inquiry has been submitted for review.
Response posted 10/14/2022


Response #2:Attention is directed to Addendum No. 4 dated October 17, 2022. Please place your bid in accordance with the current bid documents.
Response posted 10/17/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.