Viewing inquiries for 06-0X8904

Submit new inquiry for this project


Inquiry #1: Project plans show existing open grade asphalt inside existing rumble strip (PM 8.2 to 11.5). However, based on site visit, the existing rumble strip is actually ground through open grade asphalt. If we grind to remove all existing open grade, the rumble strip will be removed. Please provide direction how to bid/proceed.
Inquiry submitted 02/14/2019

Response #1:Submitted for consideration.
Response posted 02/15/2019


Response #2:Centerline rumble strip will be removed and replaced per current contract documents.
Response posted 02/22/2019




Inquiry #2: Plans show cold planing 0.10-ft of existing open grade asphalt. Based upon site visit, it appears that existing open grade asphalt is thicker than 0.10-ft. How will the contractor be compensated for removal of thicker open grade asphalt?
Inquiry submitted 02/14/2019

Response #1:Submitted for consideration.
Response posted 02/15/2019


Response #2:Bid per current contract documents. If additional work is needed at time of construction,it would be as directed by The Engineer and paid for as described in Section 4-1.05 changes and Extra Work of the 2018 Standard Specifications.
Response posted 02/15/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.