Viewing inquiries for 06-0Y0804

Submit new inquiry for this project


Inquiry #1: Should there be a pay item for Asphaltic Emulsion (Bonded Wearing Course)?
Inquiry submitted 02/26/2020

Response #1:Submitted for consideration.
Response posted 02/28/2020


Response #2:Refer to Addendum No. 2, dated March 4, 2020.
Response posted 03/04/2020




Inquiry #2: Is the Bonded Wearing Course Emulsion incidental to Item #14 or will there be a bid item added to address this quantity needed on the project?
Inquiry submitted 02/28/2020

Response #1:Submitted for consideration.
Response posted 02/28/2020


Response #2:Refer to Addendum No. 2, dated March 4, 2020.
Response posted 03/04/2020




Inquiry #3: After Review of the PPF files and Partial Width Segment Corrections on this job, it is my understanding that Cal Trans plans perform Partial width Segment Correction in the SB lanes on the .25 Cold Plane area from 0.00 to 1.0. Was this your intention? This is concluded by your SB run. The SB PPF file starts at PM 0.00, but in reality that is PM 6.04 correct? Can you please confirm that the partial width segment corrections specified in the quantity sheets do not include the cold plane area, and if so is Cal Trans still considering Partial Width Segment Correction in this area prior to the cold plane?
Inquiry submitted 03/05/2020

Response #1:Submitted for consideration.
Response posted 03/08/2020


Response #2:The full width segment correction and partial width segment corrections are provided on the Summary of Quantities plan sheet under the “Prepaving Corrections” table. Segment corrections provided in the “Prepaving Corrections” table are not included in the cold plane area.
Response posted 03/09/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.