Submit new inquiry for this projectInquiry #1: With the Project being within close proximity of water ways, are we able to kick broom the loose screenings/sand to the side of the roadway or will pick up brooms be required?
Inquiry submitted 03/22/2021
Response #1:Your inquiry has been submitted for review.
Response posted 03/22/2021
Response #2:Attention is directed to Section 13-4.03F, "Sweeping" of the 2018 Standard Specifications, "Do no use mechanical kick brooms.†Attention is also directed to, Section 13-4.03E(7) "Paving, Sealing, Saw Cutting, Grooving, and Grinding Activities". Please place your bid in accordance with the current contract documents.
Response posted 03/23/2021
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.