Inquiry #1: In order to properly bid this job, please provide the inertial profiler data in order to ensure that smoothness specifications will be met on the final surface.
Inquiry submitted 03/15/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 03/15/2018




Inquiry #2: When the construction is performed, the weather should be warm enough to pave asphalt. Please advise if it is acceptable to remove the WMA additive technology requirement from the special provision.
Thanks,

Inquiry submitted 03/22/2018

Response #1:It is not acceptable to remove the WMA additive technology requirement. Please bid as is.
Response posted 03/23/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.