Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 07-304104

Submit new inquiry for this project


Inquiry #1: Please clarify Plant Establishment time period to complete work. Specials state "Complete the plant establishment work within 365 working days." Do you mean 365 calendar days? Or 250 working days?
Inquiry submitted 08/15/2019

Response #1:250 Working Days.
Response posted 08/15/2019




Inquiry #2: Per irrigation plans sheets IPP-1, IPP-2 and IPP_3, new remote control valves shown to be connected with new conductors to the existing controllers N, O and L, which required to be trenched through the existing landscaped areas. Since there are more existing remote control valves shown to be removed at each one of the specified controllers, please confirm if new remote control valves can be re-connected to the existing conductors.

If new conductors required, please confirm if there are existing crossovers and conduits for those locations that new conductors will be crossed under existing hardscape areas?

Inquiry submitted 08/19/2019

Response #1:1) If conductors can pass a conductivity test they can be used. 2) See irrigation plans.
Response posted 08/19/2019




Inquiry #3: Please confirm if the existing trees within clearing and grubbing areas with no callout for removal are to remain and need to be protected during construction.
Inquiry submitted 08/19/2019

Response #1:Please refer to the standard specifications for clearing and grubbing.
Response posted 08/19/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.