Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 07-312004

Submit new inquiry for this project


Inquiry #1: Sheet E-19 (page 172 of 473): Conduit it to be installed across Bridge #53-1527 (BNSF UC).
There are no Structural Plans available in the bid documents. How are the conduits to be installed?

Inquiry submitted 10/09/2019

Response #1:BNSF UC (Bridge No. 53-1527) in sheet E-19 is actually West Watson OH (Bridge No. 53-0967) shown in structure plans sheets No. 440 and 441.

Caltrans has agreement with the Railroad companies for working at this location. The contractor may need railroad insurance. Contact the Railroad companies for further requirements.

Response posted 10/09/2019




Inquiry #2: Sheet E-19 (page 172 of 473): Conduit it to be installed across Bridge #53-1527 (BNSF UC).
It appears that conduit will be installed across an active railroad - will a BNSF permit need to be obtained by Caltrans and will railroad insurance be required by the bidder?

Inquiry submitted 10/09/2019

Response #1:BNSF UC (Bridge No. 53-1527) in sheet E-19 is actually West Watson OH (Bridge No. 53-0967) shown in structure plans sheets No. 440 and 441.

Caltrans has agreement with the Railroad companies for working at this location. The contractor may need railroad insurance. Contact the Railroad companies for further requirements.

Response posted 10/09/2019




Inquiry #3: Sheet E-65 (page 218 of 473): Conduit it to be installed across Bridge #53-911 (Slauson Ave UC).
There are no Structural Plans available in the bid documents. How are the conduits to be installed?

Inquiry submitted 10/12/2019

Response #1:The 4-inch conduit across Slauson Ave UC is existing and will be reused for installing new fiber optic cables. Two pull boxes at both ends of the existing conduit will be new. Reference to see structure plan (Note 6) and conduit type 1 (Note 12) should be removed for Slauson Ave UC. The conduit symbol should show as weigh 1 instead of weigh 3.
Response posted 10/14/2019




Inquiry #4: The bid express bid system for this contract does not have a section to list DBE subcontractors. There is a section to list ALL subcontractors but no where to indicate if they are being used as DBE participation. Just want to verify that I am not missing something. Please confirm. Thank you.
Inquiry submitted 10/14/2019

Response #1:The DBE Commitment and other related forms are included in the "Forms for BID" for this particular project in the "Contractor's Corner" under Caltrans website. Thanks
Response posted 10/14/2019




Inquiry #5: A follow up question in regards to Response #2:
It is this contractor's opinion that the Bidding Contractor does not time or have the responsibility to contact Railroad companies about their requirements. In an effort to maintain a "level playing field" between all bidders, would Caltrans consider all costs borne by the contractor for permits, insurances etc from the Railroad Companies be considered a force account change order at the beginning of the project?


Inquiry submitted 10/22/2019

Response #1:Please bid per plans and specifications as you see it.
Response posted 10/22/2019




Inquiry #6: Sheet E-18 (page 171 of 473): Conduit it to be installed across Bridge #53-1527 (Oil Well UC).
There are no Structural Plans available in the bid documents. How are the conduits to be installed?

Inquiry submitted 10/22/2019

Response #1:The conduit is installed in the shoulder along the bridge. Notes no. 3 and 4 should be replaced with note no. 2.
Response posted 10/22/2019




Inquiry #7: It appears on the following sheets, that conduit is to be installed through existing soundwalls/retaining walls/barriers:

E-12
E-14
E-15
E-26
E-74
E-93
E-95
E-151
E-152
E-163
E-165
E-168
E-178
E-179
E-183
E-186
Question #1A:
Is this the case? Does conduit need to go through these structures?

Question #1B:
Is there an approved method of core drilling (or another preferred method) to get conduit through the structure? If so, please provide.

Question #1C
Also, there seems to be instances where conduit needs to brought down from the structure down to new grade to conduit the conduit run. Is it possible for conduit to be strapped to side of the structure or is there another preferred method)?






Inquiry submitted 10/28/2019

Response #1:Please Bid Per Contract Plans and Specifications.
Response posted 10/28/2019




Inquiry #8: Conduit Bore Runs: It appears that there is limited access to bring a bore rig to install these bores on Sheets listed below:

E-11
E-13
E-53
E-59
E-74
E-77
E-95
E-121
E-127
E-133
E-151
E-152
E-165
E-169
E-178
E-179
E-181
E-183
E-192
E-193

On most shots, there is very limit shoulder space, and there are existing Soundwalls/Retaining Walls/Concrete Barriers/Guard Rail/Steep Slopes that leave limited space to setup bore rigs. In this contractor's opinion, the "spud pits' will most likely end up in the middle of the slow lane. Furthermore, the conduit from the "spud pit" back to the edge of the shoulder most likely will need to be trenched in. That would then require extensive freeway lane and shoulder restoration.

Question: What is the preferred boring method and restoration method of these conduit runs in tight spaces that may need extensive restoration?

Inquiry submitted 10/28/2019

Response #1:Please Bid Per Contract Plans and Specifications.
Response posted 10/28/2019




Inquiry #9: On the following Sheets
E-11,E-13,E-53,E-77,E-95,E-121,E-127,E-133,E-151,E-152,E-165,E-192,E-193,E-169,E-178,E-179,E-181,E-183 - there are bore shots shown on the plans listed above that provide difficult access for bore rigs. There are existing sound walls, retaining walls, concrete barriers, guard rails, and steep slopes that attribute to this difficulty. In this contractor's opinion, the setup for the boring rig is such that the "spud pit" may have to be the middle of the slow lane (or even the 2nd lane). This leaves restoration/safety issues. Additionally, the balance of the run back (from the spud pit back to the shoulder) will need to be trenched in - which will need extensive restoration of the freeway lanes and shoulder.

Question: What is conduit boring installation and restoration method for those conduit bore shots with difficult access for rigs?

Inquiry submitted 10/28/2019

Response #1:Please Bid Per Contract Plans and Specifications.
Response posted 10/28/2019




Inquiry #10: On sheets E-12, E-13, E-14, E-15, E-26, E-74, E-93, E-95, E-151,E-152,E-165,E-168,E-178,E-179,E-183,E-186, it appears that conduit needs to go through existing structures (sound walls, retaining walls, concrete barriers) to get conduit from one side of the structure to the other. What is the conduit installation method in these instances? Core drilling? Is there a standard detail to use? Please advise.





Inquiry submitted 10/28/2019

Response #1:Please Bid Per Contract Plans and Specifications.
Response posted 10/28/2019




Inquiry #11: Along Pipeline Road UC (E-8), there is conduit to be installed on the side of the bridges but there is an existing barrier going along the whole bridge. What is Caltrans' preferred method of getting the conduit from the shoulder area to the outside of the bridge? Does the barrier need to be removed? Please advise.
Inquiry submitted 10/28/2019

Response #1:Please Bid Per Contract Plans and Specifications.
Response posted 10/28/2019




Inquiry #12: Is there rebar in some areas of the concrete shoulders? If so, how will the "trenching in pavement"
conduit installation be performed if rebar is encountered?

Inquiry submitted 11/01/2019

Response #1:There is no rebar in existing concrete shoulders.


Response posted 11/01/2019




Inquiry #13: Insurance Requirements for Subcontractors:
It is clear that the limits for the Bidder need to adhere to the Liability Limits table shown in Section 7-1.06D.
But what about the subcontractors? Are subcontractors held to the same limits? Please advise

Inquiry submitted 11/01/2019

Response #1:Please refer to Section 7-1.06D, "Liability Insurance," of the 2018 Standard Specifications.
Response posted 11/01/2019




Inquiry #14: Per addendum 1 plan sheet 414 of 473, key note 1 states, "Install new 2-4" conduits (bridge) on existing hanger. See Roadway Plans," however, there are no roadway plans indicated anywhere. Please advise on how Caltrans would like us to proceed.
Inquiry submitted 11/05/2019

Response #1:Please construct per Addendum 1.
Response posted 11/12/2019




Inquiry #15: Will dowels be required to be installed when performing "trenching in pavement" method?
Inquiry submitted 11/11/2019

Response #1:Dowels are not required for trenching in pavement.
Response posted 11/12/2019




Inquiry #16: A large part of this contract is to install new CCTV cameras. However, there is no specification for the cameras in the special provisions. Please tell us the type of camera that is required.
Inquiry submitted 11/13/2019

Response #1:The camera must be compatible with existing Caltrans communication protocol.
Response posted 11/13/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.