Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 08-1C5904

Submit new inquiry for this project


Inquiry #1: What is the anticipated contract issuance and start date for this project?


Inquiry submitted 09/06/2019

Response #1:submitted for consideration
Response posted 09/09/2019


Response #2:Award is anticipated on November 18, 2019 and approval to commence construction is expected on December 9, 2019. These dates are tentative.
Response posted 09/09/2019




Inquiry #2: On plan pg ECL-1 - erosion control application it states a single application of wood fiber and tackifier at 2500 lbs/ac. There is no breakdown of how much of each to use. Do we use 2300 lb/ac of wood and 200 lb/ac of binder or is it refering to a bonded fiber matrix?
Inquiry submitted 09/10/2019

Response #1:Submitted for consideration
Response posted 09/10/2019


Response #2:Q: On plan pg ECL-1 - erosion control application it states a single application of wood fiber and tackifier at 2500 lbs/ac. There is no breakdown of how much of each to use. Do we use 2300 lb/ac of wood and 200 lb/ac of binder

A: The correct procedure is to use the applications stated under Section 13-5.031I of the 2018 Standard Specifications

Q: or is it referring to a bonded fiber matrix?
A: There is no Bonded Fiber Matrix.

Response posted 09/11/2019




Inquiry #3: Please confirm that gravel mulch is to be 6 inches deep after compaction.
Inquiry submitted 09/12/2019

Response #1:Submitted for consideration
Response posted 09/13/2019


Response #2:Gravel mulch is to be 6" deep after compaction
Response posted 09/13/2019




Inquiry #4: Please confirm that the insurance requirements for this project are the ones stated in CALTRANS 2018 Standard Specifications. Thank you.
Inquiry submitted 09/13/2019

Response #1:Submitted for consideration
Response posted 09/13/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.