Inquiry #1: Item 2. under the mitigation requirements for Species Protection Area 1 states:
"Biologist must be present at the onset of work."

The Monitoring Report schedule is stated as weekly, but this is done on CalTrans jobs with daily monitoring, as well.

Does this project require daily biologist monitoring or only weekly monitoring?


Inquiry submitted 09/30/2020

Response #1:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract bid documents.
Response posted 10/01/2020


Response #2:Please refer to Addendum #2
Response posted 10/09/2020




Inquiry #2: Please confirm total cubic yard quantity for item # 41 - note; (based on takeoff, retaining curb quantity looks high )


Inquiry submitted 10/01/2020

Response #1:Submitted for consideration
Response posted 10/02/2020


Response #2:Please bid per current contract documents.
Response posted 10/06/2020




Inquiry #3: Quantities sheet Q1 Plan sheet no. 301 as well as the layout drawings show a tapered edge. Please clarify how the contractor will be paid for the Roadway Excavation required to install the Tapered Edge.

The Standard Plans for Pavement Edge Treatments do not address a cold plane and overlay scenario. Please clarify.

Inquiry submitted 10/06/2020

Response #1:Submitted for consideration
Response posted 10/06/2020


Response #2:Please refer to Addendum #2
Response posted 10/09/2020




Inquiry #4: Can you please provide a list of Prime Bidders that attended the Pre-bid Meeting?
Inquiry submitted 10/06/2020

Response #1:Submitted for consideration
Response posted 10/06/2020


Response #2:The list is being electronically transmitted to all parties.


Response posted 10/07/2020




Inquiry #5: Inquiry #2 addressed an issue to Caltrans where the quantity of Minor Concrete Bid item #41 is overstated by +/- 75 percent. The response of "Please bid per current contract documents." is irresponsible and should to be addressed prior to the bid date.


Inquiry submitted 10/07/2020

Response #1:Submitted for consideration
Response posted 10/07/2020


Response #2:An independent check was performed of all the Minor Concrete (Curb, Sidewalk and Curb Ramp) bid item quantity related to the approximate 119 curb ramps. Based on the measurement, the review resulted in an additional 99 CY or, 3% increase in quantity in comparison to the quantity sheet.

In regards to the retaining curbs, they are located on the back of sidewalk, adjacent to the directional ramps and adjacent to the rock blanket. The minor concrete quantity for the retaining curb quantity is calculated assuming an average of 6" wide curb and 10" high (4" sidewalk/ramp thickness + 6" above sidewalk/ramp) irrespective of taper. Please bid per current contract documents.

Response posted 10/12/2020




Inquiry #6: In Special Provisions Section 14-6.03A, line 5 (Contract page 29), it states that temporary Desert Tortoise fencing may be installed by the Biologist. If the CSB proposes to install temporary Desert Tortoise fence, is the CSB required to have Union affiliation and/or a contractor license number?
Inquiry submitted 10/07/2020

Response #1:Submitted for consideration
Response posted 10/07/2020


Response #2:The CSB does not need to be in a union or licensed to do the Temporary Tortoise Fence. However, it will be assumed that the CSB is working under the Prime's license if installing temp Tortoise Fencing.
Response posted 10/08/2020




Inquiry #7: The project Bid Item List does not contain an item for Roadway Excavation which will be required for all areas receiving Bid Item 25 Class 2 Aggregate Base. Please clarify how the agency will compensate the contractor this scope of work. Furthermore the minor concrete at curb ramp locations will require excavation beyond the specified concrete removal depth in order meet the the new ADA finish surface elevation requirements. Please clarify how the agency will compensate the contractor for this additional excavation.
Inquiry submitted 10/08/2020

Response #1:Submitted for consideration
Response posted 10/08/2020


Response #2:Q. The project Bid Item List does not contain an item for Roadway Excavation which will be required for all areas receiving Bid Item 25 Class 2 Aggregate Base. Please clarify how the agency will compensate the contractor this scope of work.

A. Please refer to the 2018 Standard Specifications under Section 9-1.03 Payment Scope

Q. Furthermore the minor concrete at curb ramp locations will require excavation beyond the specified concrete removal depth in order meet the the new ADA finish surface elevation requirements. Please clarify how the agency will compensate the contractor for this additional excavation.

A. Existing curb ramps are being reconstructed to latest standards, any work involving minor excavation/grading as per site condition will be factored into the payment of items related to that work.

Response posted 10/13/2020




Inquiry #8: The response to Inquiry #3 Addendum 2 note that Tapered Edge is not a separate pay item does not address the question posed.

The project calls for cold plane and overlay of the existing pavement. In order to install the Tapered Edge the contractor will be required to excavate 1' beyond the edge of the existing pavement. How will the contractor be compensated for the required Roadway Excavation?

Furthermore the standard plans for pavement edge treatments do not address installing a tapered edge on a cold plane and overlay. Please clarify.

Inquiry submitted 10/09/2020

Response #1:Submitted for consideration
Response posted 10/09/2020


Response #2: For construction of the tapered edge please refer to Standard Plan P75 and the 2018 Standard Specifications under Section 39-2.01C(5) Pavement Edge Treatments.

- As per Std Plan P75, for Cold Plane overlay of 0.20' the Tapered Edge is Case C. Refer to table A and use Case C.
- Note #4 states, Grade existing ground to place tapered edge, 1' min. width.
- Also as per Specs 39-2.01C(5), grade the areas to receive the tapered edge as required and use the same type of HMA used for the adjacent lane or shoulder.

For cold plane overlay, the ground is just required to be graded as per the above notes and 'Roadway Excavation' is not required for this minimal quantity.


Response posted 10/12/2020




Inquiry #9: 12-4.02C(9)(a)(iv) states flaggers that are part of a traffic control system must be certified by an authorized flagger training provider. The authorized flagger training provider list is available at the Department's Division of Construction website.
Information on the Caltrans Authorized Safety Training Courses website (https://dot.ca.gov/programs/construction/safety-traffic/safety-training-courses) does not provide viable options for bidding contractors to have personal trained by an authorized training program(s) that meet the contract requirements.
Please advise how to proceed as it is not possible to responsibly bid the traffic control items in a manner that would meet the specification or to estimate the costs associated with meeting the requirements if viable training options are available in the future.

Inquiry submitted 10/09/2020

Response #1:Submitted for consideration
Response posted 10/09/2020


Response #2:The quoted website satisfying the Revised Standard Specification 12-4.02C(9)(a)(iv) for Quality Assurance is the only option available for contractors to get flaggers trained. Please bid per current contract documents
Response posted 10/12/2020




Inquiry #10: Layout pages do not appear to show fog seal application as referenced on quantity sheets. Please clarify where fog seal (Bid Item 26) is applied.
Inquiry submitted 10/09/2020

Response #1:Submitted for consideration
Response posted 10/09/2020


Response #2:Please refer to the 2018 Std Specifications under Section 84-8.03C, the fog seal coat is for the proposed Ground-In Rumble Strip placement for the project.


Response posted 10/12/2020




Inquiry #11: Per note #6 on sheet X-1 “Cold Plane and Overlay will be done after completion of digouts”. Please clarify if the Remove Asphalt concrete item Depth 0.3’ or 0.4’ is paid from existing finished grade followed by HMA-A placement back to existing finished grade.
Inquiry submitted 10/12/2020

Response #1:Q. Per note #6 on sheet X-1 “Cold Plane and Overlay will be done after completion of digouts”. Please clarify if the Remove Asphalt concrete item Depth 0.3’ or 0.4’ is paid from existing finished grade followed by HMA-A placement back to existing finished grade.

A. The first step is the digout process, where removal (0.3' or 0.4' depth) is paid for as REMOVE ASPHALT CONCRETE PAVEMENT (CY) from existing finished grade within the respective lane. The placement of proposed material (0.3' or 0.4' depth) is paid for as HMA (Type A) up to existing finished grade.

The next step is the cold plane & overlay process, where removal (0.2' depth) is paid for as COLD PLANE ASPHALT CONCRETE PAVEMENT and the placement of proposed material (0.2' depth) is paid for as RHMA-G up to existing finished grade.


Response posted 10/12/2020




Inquiry #12: Is the intent to remove new installed asphalt (Digouts) for a depth 0.2’ during the cold planning and RHMA placement. If not then clarify the Replace Asphalt as well as HMA-A payment zone and limit.
Inquiry submitted 10/12/2020

Response #1:Q. Is the intent to remove new installed asphalt (Digouts) for a depth 0.2’ during the cold planning and RHMA placement. If not then clarify the Replace Asphalt as well as HMA-A payment zone and limit.

A. The first step is the digout process, where removal (0.3' or 0.4' depth) is paid for as REMOVE ASPHALT CONCRETE PAVEMENT (CY) from existing finished grade within the respective lane and station limits as denoted on the layout plans. The placement of proposed material (0.3' or 0.4' depth) is paid for as HMA (Type A) up to existing finished grade.

The next step is the cold plane & overlay process, where removal (0.2' depth) is paid for as COLD PLANE ASPHALT CONCRETE PAVEMENT and the placement of proposed material (0.2' depth) is paid for as RHMA-G up to existing finished grade. The cold plane and overlay will be performed over the entire asphalt pavement as denoted on the layout plans.


Response posted 10/12/2020




Inquiry #13: 1. Per note #6 on sheet X-1 “Cold Plane and Overlay will be done after completion of digouts”. Please clarify if the Remove Asphalt concrete item Depth 0.3’ or 0.4’ is paid from existing finished grade followed by HMA-A placement back to existing finished grade.
2. Is the intent to remove new installed asphalt (Digouts) for a depth 0.2’ during the cold planning and RHMA placement. If not then clarify the Replace Asphalt as well as HMA-A payment zone and limit

Inquiry submitted 10/12/2020

Response #1:Q. 1.Per note #6 on sheet X-1 “Cold Plane and Overlay will be done after completion of digouts”. Please clarify if the Remove Asphalt concrete item Depth 0.3’ or 0.4’ is paid from existing finished grade followed by HMA-A placement back to existing finished grade.

A. The first step is the digout process, where removal (0.3' or 0.4' depth) is paid for as REMOVE ASPHALT CONCRETE PAVEMENT (CY) from existing finished grade within the respective lane and station limits as denoted on the layout plans. The placement of proposed material (0.3' or 0.4' depth) is paid for as HMA (Type A) up to existing finished grade.

Q. 2.Is the intent to remove new installed asphalt (Digouts) for a depth 0.2’ during the cold planning and RHMA placement. If not then clarify the Replace Asphalt as well as HMA-A payment zone and limit

A. The next step is the cold plane & overlay process, where removal (0.2' depth) is paid for as COLD PLANE ASPHALT CONCRETE PAVEMENT and the placement of proposed material (0.2' depth) is paid for as RHMA-G up to existing finished grade. The cold plane and overlay will be performed over the entire asphalt pavement as denoted on the layout plans. The newly placed HMA (Type A) will be removed in this operation.

Response posted 10/12/2020




Inquiry #14: On the sheet#301, Q-1, there is no tonnage for Asphalt Dike. Please verify if the QTY for bid item#27 HMA is to be revised to include the HMA for the Dike.
Inquiry submitted 10/13/2020

Response #1:Please bid per current contract documents.
Response posted 10/14/2020




Inquiry #15: Regarding Bid Item 46: Temporary Desert Tortoise Fence: can the linear foot unit-based price include both cost of materials and labor for installation/removal of materials? Or does the unit-based price refer exclusively to the cost of materials?
Inquiry submitted 10/13/2020

Response #1:For Bid Item 46: Temporary Desert Tortoise Fence, the unit price cost includes both labor and material cost.
Response posted 10/14/2020




Inquiry #16: There are more than 100 ADA ramps. However there are only 33 ea of pre/post survey for item#43. Please clarify for the bid quantity.
Inquiry submitted 10/13/2020

Response #1:The proposed curb ramps, that are designed in compliance with Caltrans conservative ADA standards (e.g. max 7.5% slope), permit a degree of construction tolerance, and do not require pre/post construction surveys. Of the total curb ramps, there are 33 curb ramps that are designed per Federal ADA standards (e.g. max 8.33% slope) due to site constraints. Given the reduced presence of construction tolerances and the need to conform to dimension and slope standards, pre/post construction surveys are required for these.
Response posted 10/14/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.