Inquiry #1: What is the expected number of work days for contractor supplied biologists? Will they work once a week, twice a week, once a month, etc.?
Inquiry submitted 09/10/2020

Response #1:Submitted for consideration
Response posted 09/11/2020


Response #2:Submitted for consideration
Response posted 09/14/2020


Response #3:Please refer to the 1602 Permit in the package. The requirement calls for daily monitoring.


Response posted 09/16/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.