Inquiry #1: Is the existing smoothness data available for this project?
Inquiry submitted 03/04/2021

Response #1:Submitted for consideration
Response posted 03/04/2021


Response #2:Please refer to 2-1.06B of the special provisions and the information handout for pavement profile smoot data.
Response posted 03/05/2021




Inquiry #2: What is the purpose of bid item 8, temporary concrete washout?

Would the State consider adding a pay item for mobilization?

Inquiry submitted 03/04/2021

Response #1:Submitted for consideration
Response posted 03/04/2021


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract bid documents.
Response posted 03/05/2021


Response #3:This issue regarding temporary concrete washout will be addressed under an upcoming addendum. Regarding mobilization, this item will not be added to this contract.
Response posted 03/09/2021




Inquiry #3: In regard to the striping and recessed pavement markers (items 13 and 14); the totals are not correct. The yellow detail 22 must be doubled, as well as the type "D" recessed pavement markers; they also must be doubled. Item # 13 should be 3,044 each, and Item # 14 should be 140,114 lineal feet. The striping on this project is "Extruded Thermoplastic" (Enhanced Wet Night Visibility) which is measured and paid for as 6" stripe. Double Stripes are measured as two stripes.
Thank you.

Inquiry submitted 03/08/2021

Response #1:This issue will be addressed under an upcoming addendum.


Response posted 03/09/2021




Inquiry #4: The typical cross section shown on X-2 for PM 38.3 to PM 38.5 shows a material layer above the .20'HMA section, part of a .30' cold plane and above the rumble strip. What is this layer?
Inquiry submitted 03/08/2021

Response #1:This layer is existing Hot Mix Asphalt. 0.3' of cold plane existing with 0.20' HMA overlay is needed, please bid per current contract documents.
Response posted 03/11/2021




Inquiry #5: The smoothness data provided in the information handout has no information on the IRI roughness of the roadway. Without IRI, a smoothness analysis cannot be done. Can Caltrans provide the PPF files for this roadway?
Inquiry submitted 03/12/2021

Response #1:Bid per current contract documents.
Response posted 03/16/2021




Inquiry #6: Can the existing smoothness data be made available in PPF format for evaluation in the ProVal smoothness software?
Inquiry submitted 03/16/2021

Response #1:Bid per current contract documents.
Response posted 03/16/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.