Viewing inquiries for 09-363404

Submit new inquiry for this project


Inquiry #1: On Plan Sheet 5 of 31. Temporary Water Pollution Control.
The plan shows temp sheet piling or equivalent. Is this plan for De-watering the ground water, where expected at 1' below surface?
The Plan also show an pump to pump up to 4 CFS is this per minute?

Can Caltrans provide an detail for the Minor Concrete (Backfill) looking at the profile sheets.
1. Is Minor Concrete Backfill concrete pavement?
2. If it is concrete pavement. Will you require dowel baskets?
3. If it is concrete pavement . Can you provide an thickness for concrete pavement?
4. On Drainage Plan and Profile sheet you show the Minor concrete (Backfill) extending out onto the slope. Is this slope paving? If so how thick is the minor concrete?

Inquiry submitted 06/23/2020

Response #1:Yes Sheet piling is for dewatering.
CFS = cubic feet per second

Minor Concrete Backfill Inquiries
1. Yes
2. N/A
3. N/A
4. Yes this is slope paving. Thickness is variable.
Response posted 06/25/2020




Inquiry #2: On plan sheet 12 of 31 (SC-1) The plans show placing 0.25' HMA (type A) Over 0.50 Class 2 Base. on the north side of Route 178.
On plan sheet 15 of 31 (SC-4) The plans show removing the north half of Route 178.
Question is why are you placing 0.25 HMA over 0.50 Class 2 base on stage 1 on the north side of Route 178? Should it be place at the end of Stage 2. So you can switch traffic to the north side of Route 178?

Inquiry submitted 06/25/2020

Response #1:Bid as per plan
Response posted 06/25/2020




Inquiry #3: Can you provide a new bid item list.
Inquiry submitted 06/25/2020

Response #1:No changes will be made to the current bid item list at this time.
Response posted 06/26/2020




Inquiry #4: Is there a Geotechnical Report for this project?
Inquiry submitted 06/26/2020

Response #1:No, there is not a Geotechnical Report for this project.
Response posted 06/26/2020




Inquiry #5: Is there any Liquidated Damages?
If there is how much?

Inquiry submitted 06/29/2020

Response #1:Refer to Standard Specifications Section 8-1.10
Response posted 06/29/2020




Inquiry #6: Shoshone Caltrans 09-363404 project. I see the box culverts are listed as a precast item, and the portion of RCB called end treatment is the only part that will be cast in place.
I see bid item #30 is for the RCB. And Bid item #31 is for the end treatment.
Bid item #30 has estimated quantity of 1,510 LB, I have come up with 16,700 LB, just the cutoff walls for drainage system 1 & 2 RCB’s come to over 1,400 LB.
My question is, am I missing something or is the bid schedule wrong?
The detail on sheet C-1 / page 3 mentions “a” bars the same as the RCB. The RCB is precast and has wire not rebar, so I have to use a Caltrans D80 detail for a 5’W x 2’H RCB, the “a” bar would be a #7, then incorporate the additional rebar called out in the detail.
Do you have any information that will help me figure this out?

Inquiry submitted 07/02/2020

Response #1:An addendum will be issued to address this inquiry.
Response posted 07/07/2020




Inquiry #7: Is Caltrans going to require a hot drop mix design verification? For 190 Tons of HMA it seems an unnecessary cost to the state.
Inquiry submitted 07/09/2020

Response #1:Bid per specifications
Response posted 07/09/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.