Viewing inquiries for 10-0P5404

Submit new inquiry for this project


Inquiry #1: We'd like to request a one week postponement of the bid date.
Inquiry submitted 09/22/2021

Response #1:Submitted for consideration.
Response posted 09/22/2021


Response #2:Unless an addendum is issued please bid per current contract documents.
Response posted 09/29/2021




Inquiry #2: Bid Item #54 for RECONSTRUCT FENCE needs clarification on what height and type of fence is to be reconstructed. We could not find any information, drawing or picture of the fence that is to be reconstructed. Please clarify the height and type of fence that is to be reconstructed.
Inquiry submitted 09/22/2021

Response #1:Submitted for consideration.
Response posted 09/22/2021


Response #2:Please refer to standard specification 2-1.07 “Job Site Examination” and standard specification 80-15.02 “Reconstruct Fences” as well as the details on the project plans.
Response posted 09/29/2021




Inquiry #3: Quantities of 689 LF for Drill and Bond Dowels, bid item 42 are shown on sheet 111/123. However, per the plans sheets there are approximately 1,280 dowels for the diaphragm bolsters, approximately 830 dowels for inside overhang and approximately 1,320 dowels for the haunch at the existing wing walls. Please clarify which dowels are paid under item 42.
Inquiry submitted 10/05/2021

Response #1:Submitted for consideration.
Response posted 10/05/2021


Response #2:Bid item no. 42 Drill and Bond Dowel includes the drill and bond work shown on sheets 116 and 119 for overhangs and wingwalls. Bid item no. 42 Drill and Bond Dowel does not include the drill and bond work shown on sheet 115 for diaphragm bolsters. This drill and bond work is included in the bid item no. 41 Diaphragm Bolster. Refer to sections 1-1.01 and 9-1.03 of the Standard Specifications and section 51-1.03E(11) of the special provisions.

Response posted 10/06/2021




Inquiry #4: ITEM #67 CONCRETE BARRIER, TYPE 60MG MODIFIED:
This Barrier is of variable height. I find no information in the Plans & Specs with which to determine the variable offsets. This is necessary to calculate quantities of concrete & rebar, and production durations. Please provide pavement elevations at the toe-of-Barrier on each side, X-sections, or some method of determining the variable offsets.

Inquiry submitted 10/05/2021

Response #1:Submitted for consideration.
Response posted 10/06/2021


Response #2:Bid per the current contract documents. Refer to details for Type 60MG Modified concrete barrier shown on plan sheets 110, 116, 120 of 123, A76D and A76E of the Standard Plans, and as-built drawings.
Response posted 10/07/2021




Inquiry #5: For the Chain Link Railing (Type 7 Modified) there are to two different bridges having two different heights for the chain link fabric. Please confirm that the Chain Link Railing (Type 7 Modified) at both bridges are to have a galvanized finish.
Inquiry submitted 10/12/2021

Response #1:Submitted for consideration.
Response posted 10/12/2021


Response #2:The chain link fence at both locations is galvanized.
Response posted 10/12/2021




Inquiry #6: Per instruction to bidder there is no DVBE goal on this project, but there is a DVBE incentive. In order to claim the incentive, the Certified DVBE Summary form DES-OE-0102.5 is to be submitted with the electronic bid package, and the back up information to be submitted 4 business day later.
Is this the intention of Caltrans in order to create equal fair bidding to all bidders by requesting that the form need to be submitted at bid time?

Inquiry submitted 10/12/2021

Response #1:Submitted for consideration.
Response posted 10/12/2021


Response #2:Yes, the specification requirements are transparent to all the bidders, creating an equal and fair bidding field.
Response posted 10/12/2021




Inquiry #7: The plans have West Modesto Overhead listed as bridge #38-0083. The barrier on the bridge has 38-0085 painted on it. Just checking, are they the same bridge?
Inquiry submitted 10/15/2021

Response #1:Submitted for consideration.
Response posted 10/15/2021


Response #2:Bid per the current contract bid documents.
Response posted 10/15/2021




Inquiry #8: Please confirm that the State will be responsible for all Railroad costs/expenses including all work indicated on "Exhibit C" (page 31 of Information Handout) and that the language in "Exhibit E-Article 4" (page 43 of Information Handout) will not apply.
Inquiry submitted 10/15/2021

Response #1:Submitted for consideration.
Response posted 10/15/2021


Response #2:The Contractor should obtain insurance policies, binders, certificates and/or endorsements to be able to work within the railroad right of way. Please refer to the Information Handout.
Response posted 10/18/2021




Inquiry #9: What access to the Abutment 1 Slope will be afforded the Contractor for constructing the Slope Paving? Will all of the work have to done from the top or will the City/Railroad allow access off of a City street (Blue Gum Avenue)?
Inquiry submitted 10/18/2021

Response #1:Submitted for consideration.
Response posted 10/18/2021


Response #2:Access from Blue Gum Ave is allowed for Abutment 1 Slope.
Response posted 10/19/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.