Inquiry #1: For bid item 39 item number 205035 wood mulch 5,400 CY is Caltrans 2018 standard spec section 20-5.03A(3)(c) Treatment of Soil required for installation of the wood mulch on this project? The special provisions don't mention if it is required.
Inquiry submitted 10/29/2020

Response #1:Your inquiry has been submitted for review.
Response posted 10/29/2020


Response #2:No. Bid per current contract documents.
Response posted 11/02/2020




Inquiry #2: For Bid Items 50, 51 and 52 Approach Slab work could the State please tell us how the removal of the existing structures will be paid for? It currently appears that the removal is paid for under Bid Item 36 Roadway Excavation. Please confirm that is correct.
Inquiry submitted 11/02/2020

Response #1:Submitted for consideration.
Response posted 11/03/2020


Response #2:The quantity is included in roadway excavation. Removal of the existing structures is paid for under the Standard Specifications, section 51-5.03D, Type R approach slab, not under Bid Item 36, roadway excavation. Refer to the Standard Specifications, section 51-5.03D(2) for removal requirements. Bid per current contract documents.
Response posted 11/03/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.