Viewing inquiries for 11-419304

Submit new inquiry for this project


Inquiry #1: Please provide CAD Files for the contract Layout Drawings.
Inquiry submitted 08/14/2020

Response #1:Submitted for consideration.
Response posted 08/14/2020


Response #2:All required electronic files have been provided. The Department does not provide CAD layout files. If you need files please clearly state file type and reason why needed.
Response posted 08/20/2020




Inquiry #2: Regarding Item #8 (Temporary Striping); Is this temporary striping being placed on the new paving, during the paving operation? Could you please give us direction on this item. Cannot find in the plans where or when this temporary striping is to be placed.
Thank you

Inquiry submitted 08/19/2020

Response #1:Submitted for consideration.
Response posted 08/19/2020


Response #2:The temporary striping is needed to maintain existing striping and maintain open lanes to traffic during construction of the project per section 12-6.03 "CONSTRUCTION" of the Revised Standard Specifications.
Response posted 08/20/2020




Inquiry #3: Bid Item 28 "Hot Mix Asphalt - Type A" includes the HMA-A (Miscellaneous Areas) to be placed at the Curb Ramp locations. Does this material simply have to follow Standard Specification Section 39-2.01B(11) Miscellaneous Areas and Dikes, or is this material also intended to be the Large Stone Matrix mix?
Inquiry submitted 08/21/2020

Response #1:Submitted for consideration.
Response posted 08/21/2020


Response #2:Please refer to Addendum #1 dated August 27, 2020.
Response posted 08/27/2020




Inquiry #4: Please provide existing MRI PVP file for the Westbound direction.
Inquiry submitted 08/27/2020

Response #1:Submitted for consideration.
Response posted 08/27/2020


Response #2:The existing surface roughness for the Westbound direction is not applicable as it will be pulverized during the process. Please bid per the current contract documents.
Response posted 08/31/2020


Response #3:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #5: Good morning can you please provide a summary of the temporary striping quantities and details. The temporary striping quantities are higher then the permanent quantities we need to figure our materials out for this item we cant do this without details and quantities thank you!
Inquiry submitted 09/01/2020

Response #1:Submitted for consideration.
Response posted 09/01/2020


Response #2:Temporary striping quantities are summarized on Sheet Q-7. They are higher than permanent striping quantities, since temporary striping can be applied after the HOT MIX ASPHALT (TYPE A) (LARGE STONE MATRIX) and also after the RUBBERIZED HOT MIX ASPHALT (GAP GRADED). Refer to Revised Standard Specifications Section 12-6.03. Temporary striping should match existing striping, except that current standards apply.
Response posted 09/04/2020




Inquiry #6: We request review and consideration to modify Section 12-4.02C(7)(b) where it states that the maximum allowable closure length for one way reversing control is 0.25' miles. This restriction will create more starts and stops of the paving operation of .15' RHMA surface course effecting the ability to achieve smoothness.
Inquiry submitted 09/04/2020

Response #1:Submitted for consideration.
Response posted 09/04/2020


Response #2:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #7: Is the .15' surface course of RHMA required to be placed in the same shift as the .60' roadway excavation?
Inquiry submitted 09/04/2020

Response #1:Submitted for consideration.
Response posted 09/04/2020


Response #2:The 0.15' surface course of RHMA is not required to be placed in the same shift as the 0.60' roadway excavation.
Response posted 09/15/2020




Inquiry #8: Bid item 50 only addresses 7 Adjust manhole frame and cover (Utility). During site visit, more than 200 manholes, utility vaults, water valve cans, gas valve cans etc were identified in the roadway excavation and pavement areas. Under what bid item(s) will work to address these utilities be quantities and paid under?
Inquiry submitted 09/04/2020

Response #1:Submitted for consideration.
Response posted 09/04/2020


Response #2:The existing manholes are to be protected in place per Standard Specifications Sections 5-1.36, 7-1.05, and 7-1.06 . The new pavement is to be placed back to existing profile elevations. The 7 Adjust Manhole Frame and Cover locations are for the manholes located in sidewalks and curb ramps that will have different final grade elevations. Please refer to RSS Section 78-23.
Response posted 09/23/2020




Inquiry #9: Are all cross streets classified as intersections in determining what areas are not subject to smoothness measurement with the inertial profile?
Inquiry submitted 09/04/2020

Response #1:Submitted for consideration.
Response posted 09/04/2020


Response #2:Please refer to Special Provisions Section 36-3 Pavement Smoothness for areas excluded from pavement smoothness measurement with an inertial profiler.
Response posted 09/10/2020




Inquiry #10: Reference question and answer provided in Inquiry #4.
The special provisions, section 39-2.01A(4)(i)(iii)(C) Acceptance Criteria using Percent Improvement apply to this project as the existing 0.6' of HMA will be removed via cold planing and installation of the Large Stone Matrix in the same shift of work. The PROVal data of the existing road is needed to evaluate the pre-bid smoothness condition of all of the areas to received new HMA/RHMA in accordance with Section 36 of the Special Provisions. Upon the start of construction, the Contractor will then follow Section 36 of the specifications to obtain its own PROVal data to compare to the Prebid PRPVal data provided by Caltrans.

Please provide this data, both westbound and eastbound for all traveled lanes as it is a requirement of the contract and is needed to bid the project accurately.

Inquiry submitted 09/08/2020

Response #1:Submitted for consideration.
Response posted 09/08/2020


Response #2:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #11: Sheet Q-4 does not show a quantities for HMA-A Large Stone Matrix for layout sheet L-17. Please clarify.
Inquiry submitted 09/08/2020

Response #1:Submitted for consideration.
Response posted 09/09/2020


Response #2:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #12: Please provide location of laydown/yard space that will be made available by Caltrans for contractor's use on this project.
Inquiry submitted 09/09/2020

Response #1:Submitted for consideration.
Response posted 09/09/2020


Response #2:Contractors are responsible to arrange their own storage or equipment yard, materials and other items as needed.
Response posted 09/15/2020




Inquiry #13: In the list of Bid Items, there is no line item for Plant Establishment Work. On page 1, Notice to Bidders, there is no Plant Establishment working days.
On page 53 under Division 3, Earth Work and Landscape, it states: "... plants including transplanted trees have been satisfactorily maintained for at least 21 days after planting."
Is the 21 day referenced here, the Plant Establishment time period for Bid Item #25: SOD?

Inquiry submitted 09/09/2020

Response #1:Submitted for consideration.
Response posted 09/09/2020


Response #2:There is no bid item for plant establishment. Plants must be satisfactorily maintained for at least the number of days specified after planting. Bid per contract documents.
Response posted 09/10/2020




Inquiry #14: Some of the curb ramp locations call for RSC to be utilized for the sidewalk to be reconstructed. The same locations are able to be closed for 4-6 days per Section 12 of the Special Provisions. Why is rapid set concrete needed when the ramps are able to be closed for multiple days per the specifications? We recommend that the sidewalk in these locations be changed to normal concrete.
Inquiry submitted 09/09/2020

Response #1:Submitted for consideration.
Response posted 09/09/2020


Response #2:Rapid Strength Concrete (RSC) has been designated on sheets Q-2 & Q-3 for ramps with cross gutters so that they can be poured in one night and opened to traffic the following morning. Please bid per plan.
Response posted 09/10/2020




Inquiry #15: Contract documents show the existing structural sections throughout the entire project a to be [A] 0.60’ HMA over 0.65’ AB. It is very unlikely that there is this uniformity in the existing structural sections, however there in no information provided in the contract documents or visible through job site examination to determine otherwise. Please confirm all situations in which existing structural sections are encountered differing from what is shown on the plans will be treated as differing site conditions and adjustments in time and payment will be made.
Inquiry submitted 09/10/2020

Response #1:Submitted for consideration.
Response posted 09/10/2020


Response #2:Anticipate deviations in the existing HMA section equal to the tolerances for AB specified under section 26-1.03E of the Standard Specifications. Any other variations in the thickness of the existing HMA does not necessarily constitute a different site condition. Promptly notify the Engineer of any perceived different site condition encountered during construction as specified in Section 4-1.06 of the Standard Specifications.
Response posted 09/10/2020




Inquiry #16: The existing structural section shows .60’ of HMA over .65’ AB and Typical Section 3 requires the existing pavement to be replaced with .45’ HMA-A (Large Stone Matrix) and .15’ RHMA-G over the existing AB. Under item 21, Roadway Excavation(Section 19-2 Roadway Excavation includes Section 19-5.03B Relative Compaction(95 Percent)). Assuming Caltrans will require and perform daily compaction testing and acceptance of existing AB, please provide the time frame Caltrans will require to perform testing and return results during the production shift as lanes can not remain closed and paving operations can not begin until the State accepts the compaction of the AB. Due to the limited work windows and lack of staging ( k-rail ) all removals, grading, compaction and paving must be conducted in the same work shift prior to opening the lanes to traffic. An accurate time frame for the state's testing must be provided to allow the bidding contractors to estimate daily productions.
Inquiry submitted 09/10/2020

Response #1:Submitted for consideration.
Response posted 09/10/2020


Response #2:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #17: To follow up on bidders inquiry 15 and 16, the classification of the removal Item as Roadway Excavation seems incorrect. This work would be better represented as Cold Plane Asphalt Concrete Pavement or Replace AC Surfacing due to the lack of staging (k-rail) and the fact that the deign shows .60' of existing ac removal and replacement. Please clarify the intent of labeling this work as Roadway Excavation.
Inquiry submitted 09/10/2020

Response #1:Submitted for consideration.
Response posted 09/11/2020


Response #2:Please refer to Addendum No. 4 dated September 23, 2020.
Response posted 09/23/2020




Inquiry #18: Line item 46 Minor Concrete unit measure is in Theoretical calculated volume , is there is any way switching the unit price from CY SF for Sidewalk & LF for Curb if used, this will save a lot of disputes and claims down the road on any project
Inquiry submitted 09/11/2020

Response #1:Submitted for consideration.
Response posted 09/11/2020


Response #2:No. Please bid per the current contract documents.
Response posted 09/15/2020




Inquiry #19: Bid Item #72 - Vegetation Control (Minor Concrete) SQYD = 450:

Where is the location of this work?

What plan Sheet Pages are the words "Vegetation Control (Minor Concrete)" located?

Please specify the explanation of where the work is located on what Sheet pages?

Thank you.

Inquiry submitted 09/13/2020

Response #1:Submitted for consideration.
Response posted 09/14/2020


Response #2:Please see plan sheets C-1, C-93, C-94, C-95 and Q-7 for "Vegetation Control (Minor Concrete)" item location and quantity.
Response posted 09/14/2020


Response #3:Please see plan sheets C-1, C-93, C-94, C-95 and Q-7 for "Vegetation Control (Minor Concrete)" item location and quantity.
Response posted 09/14/2020




Inquiry #20: There are several Manhole and Valve Covers within the roadway improvement limits. What bid item number is intended for adjusting these manhole and valve covers?
Inquiry submitted 09/15/2020

Response #1:Submitted for consideration.
Response posted 09/15/2020


Response #2:Please refer to section 71-5.04 PAYMENT of the Standard Specifications.
Response posted 09/16/2020


Response #3:Please refer to the response to Bidder's Inquiry #8.
Response posted 09/23/2020




Inquiry #21: Reference is made to inquiry #20 and response. "Please refer to section 71-5.04 PAYMENT of the Standard Specifications." Section 71-5.04 is deleted in the revised standard specifications for this project. Please clarify what the departments answer is for this inquiry.
Inquiry submitted 09/16/2020

Response #1:Submitted for consideration.
Response posted 09/16/2020


Response #2:Please refer to the response to Bidder's Inquiry #8.
Response posted 09/16/2020




Inquiry #22: There are approximately 65 Each Manholes and 230 Each Valve Covers within the Roadway limits, which require lowering and raising as part of the roadway improvements.

Please confirm that cost associated with this work is considered Incidental Construction as part of Section 78 of the Project Special Provisions.

Inquiry submitted 09/16/2020

Response #1:Submitted for consideration.
Response posted 09/16/2020


Response #2:Please refer to the response to Bidder's Inquiry #8.
Response posted 09/23/2020




Inquiry #23: There is no item for Pre/Post Survey for the Ramps. Is the State providing it?
Inquiry submitted 09/28/2020

Response #1:Submitted for consideration.
Response posted 09/28/2020


Response #2:There will be no item for Pre/Post Survey for the constructed curb ramps. Please bid per project plans and specification. Please refer to section 73-3.03 of the project Special Provisions.
Response posted 09/28/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.