Inquiry #1: For Section 87-19.02G(3) & 87-19.03G(3) of this contracts special provisions, will the fast setting concrete/cement backfill used for the micro-trench be required to have red pigment as well?
Inquiry submitted 01/05/2022

Response #1:Submitted for consideration.
Response posted 01/05/2022


Response #2:The micro-trench concrete/cement backfill Special Provisions do not specify pigmentation color. Please refer to section 87-19.03G regarding backfill material and bid per current contract documents.
Response posted 01/10/2022




Inquiry #2: Does Caltrans have a specific mix design that it wants for the micro-trench "Fast Setting Concrete Backfill" that it can share with the contractors?
Inquiry submitted 01/05/2022

Response #1:Submitted for consideration.
Response posted 01/05/2022


Response #2:Please refer to section 87-19.03G of the Special Provisions for Cement Backfill requirements.
Response posted 01/10/2022




Inquiry #3: Please confirm that the installation of the micro-duct HAS TO BE done by use of a Micro-trencher with a not-to-exceed trench width of two and a half inches and not a rockwheel or earthsaw that would open the trench up to four to six inches.
Inquiry submitted 01/07/2022

Response #1:Submitted for consideration.
Response posted 01/07/2022


Response #2:Please bid per the current contract documents. The successful Contractor may propose alternatives by submitting a Value Engineering Change Proposal (VECP), in accordance with Section 4-1.07, Value Engineering of the Revised Standard Specifications after contract award.
Response posted 01/07/2022




Inquiry #4: Regarding the department furnished controller cabinets, will a new foundation be required or will the controllers be going on existing foundations?
Inquiry submitted 01/25/2022

Response #1:Submitted for consideration.
Response posted 01/25/2022


Response #2:Please refer to Modifying Signal and Lighting System plan sheets and bid per current contract documents.
Response posted 01/27/2022




Inquiry #5: Regarding spec section 87-19.03F(1), Is a test station required for the tracer wire at each of the 6(E)(E)(T) pull boxes that are listed in the tables on E-19 through E-22?

Also, can the tracer wire be incorporated into the multiduct?

Inquiry submitted 01/25/2022

Response #1:Submitted for consideration.
Response posted 01/25/2022


Response #2:Please refer to section 87-19.03F:
- Yes a test station is required at each of the 6(E)(E)(T) pull boxes listed in the tables on E-19 through E-21.
- No the tracer wire cannot be incorporated into the multi duct.

Response posted 01/27/2022




Inquiry #6: Special Provisions for Contract No. 11-430564 replaces section 12-4-.02c(3)(E) and gives an extensive list of special events and venues some of which are beyond the ROW or influence of the project. Please clarify if all these events do not/may not have impacts on this project.
Inquiry submitted 01/28/2022

Response #1:Submitted for consideration.
Response posted 01/28/2022


Response #2:The 12-4.02C(3)(e) is a special provision specifications that we must provide in all Caltrans projects, however, if the work location is not in proximity within the events or venue listed in this specifications, then this specific specifications would not apply.


Response posted 02/01/2022




Inquiry #7: The Additive Item on the Bid Schedule has a quantity of 530 TN. Appears quantity should actually be 1 LS. Please change quantity or provide measurement and payment of the 530 TN.
Inquiry submitted 02/01/2022

Response #1:Submitted for consideration.
Response posted 02/01/2022


Response #2:Please refer to Addendum #2, submitted on February 1, 2022.
Response posted 02/01/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.