Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 12-0H0474

Submit new inquiry for this project


Inquiry #1: There are only ProVal supplemental information given for Locations 1 through 3. Since no ProVal supplemental information was not given for Locations 4 through 8 will the pavement smoothness specification not apply for the locations?
Inquiry submitted 08/27/2021

Response #1:Pending
Response posted 08/27/2021


Response #2:The ProVal supplemental information for the Locations 4 through 8 will be included in an upcoming Addendum.
Response posted 08/31/2021




Inquiry #2: On Project Plan Sheet U-3 shows a water line running parallel to drainage system 10 shown on project plan sheet D-9. Need to know how far the water line travels north as project plan utilities sheets doesn’t show where waterline continues.
Inquiry submitted 08/31/2021

Response #1:Pending
Response posted 08/31/2021


Response #2:Please see plan sheet U-3
Response posted 09/06/2021




Inquiry #3: From Sta. 532+52.8 to 555+02.9 the plans call for a Drainage System 6 to be constructed in median of Route 241. The traffic handling plans do not address this scope specifically. Our questions are as follows:
Will the shoulder closures be allowed during this work so that we can plate our trenches?
Will trench plates be allowed on the shoulder or on the mainline after the Route is opened to traffic?
Will the State allow and pay for the use of K-rail in this area to protect the work?
Will the State consider any full closure to complete this drainage system?
For this drainage system, can the State confirm that the existing barrier is not in conflict with the proposed drainage system?

Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:No full closures are permitted, please refer to the LRC in the Project SSP file for closure information. Trench plates are not permitted. Please refer to the Traffic Handling plans for K-rail locations. The proposed drainage system is not in conflict with the existing barrier, please see the revised plans in the upcoming Addendum for this clarification
Response posted 09/08/2021




Inquiry #4: There is not a soils report or geotechnical data that provides us with enough information to understand the risk associated with the trench excavation.

For bidding purposes, can the State confirm that the Contractor will not be responsible for groundwater if encountered, and rock excavation greater then 12" in diameter?

Or will the State provide an adequate soils report that we can reference?

Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:Due to the absence of a project soils report, the Contractor should bid assuming the possibility of encountering groundwater and rocks larger than 12" in diameter
Response posted 09/08/2021




Inquiry #5: Will the Contractor be responsible to pay for tolls or will the Contractor be exempt from paying tolls while working on the project?
Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:State will pay for tolls for contractor’s trucks only and not personal cars while working on this project
Response posted 09/08/2021




Inquiry #6: When paving the #2 lane, will the State allow traffic to run on the shoulders so that a safety barrier between the workers and live traffic can be established?

Or will the Contractor be allowed to pave 1 and 1/2 lane widths so that a safety barrier between the workers and live traffic can be established?

Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:Either option is permitted as long as safety standards are followed in concurrence with the Resident Engineer
Response posted 09/08/2021




Inquiry #7: Can the State confirm that the excavation required to complete bid item 36 (6" perforated plastic pipe underdrain) is paid for in bid item 22, trench excavation?

Trench excavation is measured and paid by the CY? If soils condition require the Contractor to dig a wider trench, or for safety reasons the Contractor uses a wider trench, will the State confirm that the additional excavation will be paid at the unit price for Trench excavation, bid item 22?

Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:Correct, excavation for Bid Item 36: 6" Perforated Plastic Pipe Underdrain is paid for in Bid Item 22: Trench Excavation. Trench excavation is paid by CY. If the Contractor needs to dig a wider trench for a legitimate reason and receives prior approval from the State via a CCO, then the Contractor is entitled to get paid for the additional trench excavation based on the unit price for Bid Item 22: Trench Excavation
Response posted 09/08/2021




Inquiry #8: Per the lane closure charts there are no full freeway closures allowed. When we grind and pave the variable asphalt level courses we will have elevation differentials at the lane lines, which is a safety concern. In order to pave the level courses safely we would need full freeway closures in order to pave the full width of the freeway each shift. Please advise.
Inquiry submitted 09/01/2021

Response #1:Pending
Response posted 09/01/2021


Response #2:"Refer to LRC in SSPs, no full closures are permitted. Uneven pavement may result, but appropriate safety standards need to be followed in concurrence with the Resident Engineer."
Response posted 09/07/2021




Inquiry #9: Is there a pre-bid meeting or jobwalk for this project? If so, when is it and is it mandatory?
Inquiry submitted 09/07/2021

Response #1:Pending
Response posted 09/07/2021


Response #2:Pending
Response posted 09/07/2021


Response #3:No pre-bid meeting or job walk scheduled for the project
Response posted 09/07/2021




Inquiry #10: Is this project subject to the Davis-Bacon Act?
Inquiry submitted 09/14/2021

Response #1:Pending
Response posted 09/14/2021


Response #2:Yes it does.
Response posted 09/14/2021




Inquiry #11: Per addendum # 2, pavement section note # 2 has been revised to show a .20' cold mill with the installation of a variable HMA up to 1.15'. This would mean that there will be a longitudinal lane elevation differential of up to .95'. Per Caltrans safety guidelines it is physically impossible to install this pavement section without a full closure of the freeway. Per addendum # 2 there have been no adjustments to the lane closure charts. Please advise how Caltrans plans on installing this pavement section with the current lane requirements.
Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:Variable depth overlays have to meet the allowed vertical longitudinal joint differential per Section 39-2.01C(4). Staging for the pavement overlay work is up to the Contractor. No full closures of the SR-241 are permitted on the project per the LRC.


Response posted 10/01/2021




Inquiry #12: Addendum No. 2: Added Bid item 75 - Relocate Concrete Barrier (Type K) - 11,200 LF. Where is this being relocated to?
Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:"The concrete barrier (type K) relocation is a small temporary shift to allow for pavement work in the median underneath the K-rail (refer to layout sheets L-1 through L-10 for limits of K-rail relocation). The K-rail will be placed back at the same original location once the median area is paved."
Response posted 10/04/2021




Inquiry #13: Reference Structural Section Type 2 and the Typical Cross Sections shown in the project plans. No paving is shown to be done in the shoulders (i.e. outside ETW). When Pavement Section Type 2 is complete, there will be a vertical drop off between the traffic lane and shoulder from 0.15’ to 0.95’. Please clarify the work required in the shoulder to address this safety issue.
Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:"Please refer to Note 3 on sheet L-1."
Response posted 10/04/2021




Inquiry #14: What is the maximum length of stationary lane closure allowed for this project?
Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:The maximum length of the work area inside a closure is 2 miles, but a traffic delay of 30 minutes or more is not permitted.
Response posted 10/04/2021




Inquiry #15: Per Addendum No. 2, a bid item (75) was added to RELOCATE CONCRETE BARRIER (TYPE K). Is the Existing K-RAIL pinned into to the existing pavement? Will the Contractor be required to pin the K-RAIL to the new pavement? For Bidding Purposes will any patching, painting or replacement of K-RAIL pins be required?

Will the State allow the K-Rail to be shifted and left in the median between work shifts, or is the K-Rail to be returned to it's original location at the end of each shift?




Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:"Existing K-rail is currently pinned into the existing pavement. After the paving work in the median area is completed, the contractor will be required to pinned to the new pavement in the same original location. Patching, painting, and replacement of K-rail pins should be included in the bid.

The K-rail needs to be pinned back in the original location at the end of each shift."

Response posted 10/04/2021




Inquiry #16: The typical section that were included in Addendum 2 are not consistent with the location of the asphalt pavement that is shown on the layout drawings. Can the State please confirm that the proposed cold plane and asphalt overlay extends thru the existing center median as represented on the layout drawings and that the typical section are not accurate and should be disregarded.
Inquiry submitted 10/01/2021

Response #1:Pending
Response posted 10/01/2021


Response #2:Please follow layout sheets L-1 through L-10
Response posted 10/04/2021




Inquiry #17: Regarding Bid Item 36 (addendum 2), it is difficult to tell from the plans if the proposed drain is located beneath the existing pavement on the shoulder or in an unpaved area of the shoulder. To assist us in preparing the estimate can the State explain what percent of the drain is located beneath a paved area of the shoulder? Our concern is how much saw cutting and trench restoration will be required? If the information needed to answerer this question is not available, will the State consider adding a bid item for saw-cutting asphalt pavement, and an item for Trench Restoration?
Inquiry submitted 10/02/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:Please bid per plans
Response posted 10/04/2021




Inquiry #18: Is the intent for the drainage work to be completed during the day behind K-Rail or is this work to be completed at night?

We are not sure if there will be enough room to perform the Drainage work behind the K-Rail. For bidding purposes, can the State inform us of how much space will will have from the center of the proposed temporary K-Rail to the center of the proposed trench, bid item 36, Add #2.

Inquiry submitted 10/02/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:Intent is for the drainage work to be completed at night. Bid per plans
Response posted 10/04/2021




Inquiry #19: Addendum 2 included an ADL Report, but the Contract does not have a bid item for disposal of lead impacted soil. How will the disposal of lead contaminated soil be paid?
Inquiry submitted 10/02/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:Per the ADL Report, the soil is suitable for onsite reuse or offsite disposal without restriction with respect to lead content
Response posted 10/04/2021




Inquiry #20: Will right of way be available for the Contractor to stage within the work limits at no additional cost to the contractor? Can the State provide the approximate location of the available ROW that we can use for Staging.
Inquiry submitted 10/04/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:The approximate location of R/W lines are shown on the layout sheets
Response posted 10/04/2021




Inquiry #21: Based on the additional cross sections provided on Addendum #2 will cold planning be required prior to placing the leveling course (HMA Type A) that is more than 0.30FT in depth?
Inquiry submitted 10/04/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:Please refer to X-1 for cold plane location and depth
Response posted 10/04/2021




Inquiry #22: There is not a lane closure chart for the 133 and the 261 connectors. Based on the location of the proposed work, we anticipate that traffic controls measures will be required on these connectors. Please advise.
Inquiry submitted 10/04/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:There is no work at the 241/133 connector. Lane Requirement Chart No. I1 includes lane closure information for the 261/241 connectors
Response posted 10/04/2021




Inquiry #23: There is not a bid item for temporary striping. Will temporary striping be required by the State and if so, how will temporary striping be paid?


Inquiry submitted 10/04/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:If temporary striping is needed, it will be paid under Bid Items 65 and 66
Response posted 10/04/2021




Inquiry #24: Per Note 3 of L-1 there will be shoulder backing as required. What bid item does shoulder backing get paid in?
Inquiry submitted 10/04/2021

Response #1:Pending
Response posted 10/04/2021


Response #2:The quantity for shoulder backing was included in Bid Item 25
Response posted 10/04/2021




Inquiry #25: Referring to the response provided to bidder’s inquiry #24, does the State intend to classify the HMA safety edge as shoulder backing and therefore the use of the materials specified in section 19-9.02 will not be required? Please advise.
Inquiry submitted 10/05/2021

Response #1:Pending
Response posted 10/05/2021


Response #2:HMA is used for both the safety edge and shoulder backing. The HMA quantity for the shoulder backing shown in standard plan P75 is included in Bid Item 25
Response posted 10/05/2021




Inquiry #26: Paving the structural section 2 for this job per the closure charts will create an unsafe situation when returning to live traffic. A full freeway closure needs to be allowed to properly pave and make it safe.
Inquiry submitted 10/05/2021

Response #1:Pending
Response posted 10/05/2021


Response #2:"No full freeway closures are permitted per the LRC. Bid per plans."
Response posted 10/05/2021




Inquiry #27: Please refer to section 6-1.06 of the special provisions. Please clarify the electrical materials (poles, conduit, fixtures and etc.) that would need to be complaint to that section. Currently vendors are stating manufacturers are unable to meet that requirement to incorporate their products into the work.
Inquiry submitted 10/06/2021

Response #1:Pending
Response posted 10/06/2021


Response #2:Special Provision Section 6-1.06 was deleted as part of Addendum #2
Response posted 10/06/2021


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.