Viewing inquiries for 12-0K0214

Submit new inquiry for this project


Inquiry #1: The DBE goal set by the Department on this Project is unrealistic based on the available DBE capacity in the market. Attempting to reach the goal, if attainable at all, will require significant premium costs to the bids. Please revise the goal to 11% to ensure meaningful DBE participation without causing the Department to pay excessive premium costs.
Inquiry submitted 08/28/2019

Response #1:Pending
Response posted 08/29/2019


Response #2:Please bid per the current contract documents. Refer to Section 2-1.04 of the 2018 Standard Specifications for mandatory prebid meeting requirements.
Response posted 09/05/2019




Inquiry #2: Due to a $150 million project bidding on October 2 for SBCTA, we respectfully request a bid postponement of three weeks.
Inquiry submitted 08/29/2019

Response #1:Pending
Response posted 08/29/2019


Response #2: Bid opening will remain 2019-10-15 per contract documents.
Response posted 08/30/2019


Response #3:Reference BI #2
Response posted 09/26/2019




Inquiry #3: Can the State please provide the information stated in section 2-1.06B that includes cross sections, alignment data, original ground data, and proposed final elevations to help with earthwork takeoffs?
Inquiry submitted 09/05/2019

Response #1:Pending
Response posted 09/05/2019


Response #2:See Addendum #1 dated 09 25 2019
Response posted 09/26/2019




Inquiry #4: On the Notice to Bidders it states that there are 1,110 Working Days to complete the work excluding plant establishment. On the Notice to Bidders it also indicates 250 Working Days to complete plant establishment, but states that there are 1,110 to complete the work including plant establishment. Please clarify which is correct.
Inquiry submitted 09/11/2019

Response #1:Pending
Response posted 09/11/2019


Response #2:Reference SP page 14, "Notice to Bidders"

Complete the work, both contract work and PECE work, within 1,110 working days

Complete PECE work within 250 working days

Response posted 09/26/2019




Inquiry #5: Please confirm method of payment for PCC isolation joint.
Inquiry submitted 09/13/2019

Response #1:Submitted for consideration.
Response posted 09/16/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #6: Please respond to Inquiry #3, so we can schedule time for takeoff.
Inquiry submitted 09/18/2019

Response #1:Pending
Response posted 09/19/2019


Response #2:See Addendum #1 dated 09 25 2019
Response posted 09/26/2019




Inquiry #7: How do we change the email address in the primes seeking assistance posting. Thank you
Inquiry submitted 09/20/2019

Response #1:Pending
Response posted 09/20/2019


Response #2:Log in to Caltrans Bidding Connect and update the email address
Response posted 09/24/2019




Inquiry #8: We respectfully request that the bid date be extended a minimum of three weeks. There are currently multiple public works projects bidding, including a large project ($150M) that is scheduled to bid within 1 business day of this project. Prime Contractors and subcontractors will have limited resources to pursue these bid opportunities. A bid extension would allow sufficient time for Prime Contractors and subcontractors to provide complete and competitive estimates for the projects currently advertised.
Inquiry submitted 09/20/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:Reference BI #2
Response posted 09/26/2019




Inquiry #9: Drainage Quantities table shown on sheet DQ-39 states the removal of the existing RCB as 359 LF. Does sheet D-15 clearly define the limits of this removal?
Inquiry submitted 09/24/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:Bid in accordance with Sheet D-15
Response posted 09/27/2019




Inquiry #10: Drainage Quantities table shown on sheet DQ-52 show installation of a new DBL 5x3 RCB. Drainage sheet D-16 state removal of existing 5x3 RCB Culvert from SP 10+00 to SP10+43.78. Which pay item is the excavation and removal of this existing RCB, and which pay item is for the removal of the existing spillway?
Inquiry submitted 09/24/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #11: Drainage Quantities table shown on sheet DQ-58 show installation of a new 4x2 RCB for drainage system, also shown on Drainage sheets D-7 and D-9. Can you verify that the quantity shown on DQ-58 is correct?
Inquiry submitted 09/24/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #12: Does the Structure Excavation and Backfill for Box Culverts get paid under item No 128(F) Structural Concrete, Box Culvert ?
Inquiry submitted 09/24/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:In accordance with Section 9-1.03, "Payment Scope" of the SS, Structure Excavation and Backfill for Box Culvert work will be paid under No. 128 (F) Structural Concrete, Box Culvert.
Response posted 09/27/2019




Inquiry #13: Please provide more detailed information for the work performed under Item No. 180 Remove Culvert. Specifically, the drainage tables and plans do not show all the culvert sizes, with no inverts or grades provided. Without this information the contractor cannot provide an accurate price for removal.
Inquiry submitted 09/24/2019

Response #1:Pending
Response posted 09/24/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #14: We respectfully ask for a 4-week bid date extension. Subcontractors who are interested in this project do not have the resources and time to provide quotes for this project and other regional projects which are currently bidding within weeks of each other.
Inquiry submitted 09/25/2019

Response #1:Pending
Response posted 09/25/2019


Response #2:Reference BI #2
Response posted 09/26/2019




Inquiry #15: Due to SBCTA’s postponement of the 150 million dollar SR-210 project from October 2, 2019 to October 16, 2019, Please consider postponement of this project a minimum of 3-4 weeks. DBE subcontractors are finding It difficult and unrealistic to provide quotes for both projects in the given time frame.
Inquiry submitted 09/27/2019

Response #1:Pending
Response posted 09/27/2019


Response #2:Reference BI #2
Response posted 10/02/2019




Inquiry #16: Please clarify which items the contractor is responsible for providing Quality Control services.
Inquiry submitted 09/30/2019

Response #1:Pending
Response posted 09/30/2019


Response #2:Bid per the Contract documents, please refer to the Standard Specifications
Response posted 10/08/2019




Inquiry #17: Refer to sheet no 364 (contract drawing DQ-95). there is a column for 'REMOVE CONCRETE (MISCELLANEOUS)' with a quantity of 2,402 SF. Under which pay item does this work belong?
Inquiry submitted 10/01/2019

Response #1:Pending
Response posted 10/02/2019


Response #2:Refer to Item 39, paid under bid item 153248 "REMOVE CONCRETE (MISCELLANEOUS) (SQFT)"
Response posted 10/08/2019




Inquiry #18: Under what pay item will the Communication Hub rebar be paid under?
Inquiry submitted 10/02/2019

Response #1:Pending
Response posted 10/02/2019


Response #2:The communication hub rebar is paid under item 281, Building Work. Please refer to section 99 of the special provisions.
Response posted 10/11/2019




Inquiry #19: Retaining Wall 734 uses soldier piles placed in 36" drilled holes. It is stated on the Plans that the holes are to be back filled with concrete after the piles are in place. Does this include the top portion of the hole where the timber lagging is eventually installed?
Inquiry submitted 10/02/2019

Response #1:Pending
Response posted 10/02/2019


Response #2:The limits of the concrete backfill and lean concrete backfill are shown on the plan. See “Typical Section” detail on plan sheets 1256 and 1257 of 1351.
Response posted 10/11/2019




Inquiry #20: Special Provisions Section 12-4.02C(3)(d) states that the Contractor may close Avery Parkway during the hours shown on Chart No. L1-L2. These charts are not included in the special provisions. Please provide referenced charts.
Inquiry submitted 10/02/2019

Response #1:Pending
Response posted 10/02/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #21: Is Caltrans anticipating another addendum for this project prior to the bid? If so will this addendum postpone the bid date?
Inquiry submitted 10/02/2019

Response #1:Pending
Response posted 10/02/2019


Response #2:
Addendum #2 will be issued October 8, 2019

Reference BI #2

Response posted 10/04/2019




Inquiry #22: Section 19-8.01E discusses installing settlement hubs at walls 734 and 748. Survey and adjustment of the hubs must be performed by a licensed surveyor. Will Caltrans be providing the surveyor or is the contractor responsible for providing the survey?
Inquiry submitted 10/03/2019

Response #1:Pending
Response posted 10/04/2019


Response #2:Please refer to the 9th paragraph of section 1.01 of Standard Specifications and section 19-8.01E of the special provisions.
Response posted 10/11/2019




Inquiry #23: We have a significantly lower quantity for BI 159 - 12" Plastic Pipe. Please confirm the bid item quantity is correct.
Inquiry submitted 10/03/2019

Response #1:Pending
Response posted 10/04/2019


Response #2:Please bid per the Contract documents
Response posted 10/08/2019




Inquiry #24: Sheet 204 (D-16) shows removal of RCB Culvert at DS 62, however it is not captured on the drainage quantity sheets. Please confirm there is RCB removal at DS 62, and if so, please update quantities accordingly.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/07/2019


Response #2:See Addendum #2 dated 10 08 2019
Response posted 10/08/2019




Inquiry #25: RSP is called out at several locations, however details were only provided for DS 10c. Please provide similar information for all locations.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/07/2019


Response #2:See Addendum #3 dated 10 10 2019
Response posted 10/10/2019




Inquiry #26: Spec Section 19-3.03B(1) requires the excavation and construction of RW 748 in 1/4 length segments. This is highly unconventional for Type 1 and Type 7 walls and will add significant cost for mobilizations of pile driving equipment, excavation crews, etc., as well as construction duration. Please confirm this spec is relevant to this project and this location.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/07/2019


Response #2:Please bid per the Contract documents
Response posted 10/11/2019




Inquiry #27: Spec Section 19-3.03B(1) requires the excavation and construction of RW 748 in 1/4 length segments. If the Contractor choses to shore this location, does this spec still apply?
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/07/2019


Response #2:Please bid per the Contract documents
Response posted 10/11/2019




Inquiry #28: Section 5-1.32 mentions Freeway Lease Area that is not available to the contractor. Does the State have any areas that are designated as available to the contractor? This is a very tight stretch of freeway and contractors will need room to stockpile material, equipment, etc..
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Please bid per the Contract documents
Response posted 10/08/2019




Inquiry #29: Section 7.102k states that material along Rte 5 and within 4' of finish grade be stockpiled at an authorized location. Please provide this authorized location so that contractors can include the appropriate cost of hauling the material to and from the stockpile.

Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Please bid per the Contract documents
Response posted 10/09/2019




Inquiry #30: Please confirm that the State will be responsible for performing all lead testing of the material at the stockpile location.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Please bid per the Contract documents
Response posted 10/09/2019




Inquiry #31: Section 14-6.03A states that exclusion devices may need to be installed. If the OCTA biologist directs the installation of these devices, will the contractor be compensated via Change Order?
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Bid in accordance with Sections 14-6.03A and 14-6.03B of the SP and SS
Response posted 10/09/2019




Inquiry #32: Will the State be responsible for any permits and costs associated with performing the work of abandoning existing ground monitoring wells?
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Please comply with the requirements of Section 5-1.32 in the Special Provisions.
Response posted 10/16/2019




Inquiry #33: SCD Drawings appear to show temporary railing with pins into existing pavement. Please clarify that the standard plans will govern where pinning temporary railing is required versus what is shown in the SCD drawings.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:Bid in accordance with the Contract plans and Standard Plans
Response posted 10/09/2019




Inquiry #34: The bid quantity for Remove Concrete Barrier is significantly less than as shown on the plans, will the State revise the bid quantity to match that is shown?
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:See Addendum #3 dated 10 10 2019
Response posted 10/10/2019




Inquiry #35: Curb Type B4 is shown on the plans but not on the Minor Concrete Summary Sheets. Please advise.
Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:See Addendum #3 dated 10 10 2019
Response posted 10/10/2019




Inquiry #36: The Summary of Quantities/ Bid Item Schedule shows only 56 CY Minor Concrete (Textured Paving), however much more Textured Paving is shown as the Gore Area in the Layout pages. Please Advise.

Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:See Addendum #3 dated 10 10 2019
Response posted 10/10/2019




Inquiry #37: After performing a takeoff on Drainage System 62 unit B (Concrete Channel (Spillway)), the concrete quantity significantly exceeds the quantity listed on the summary of quantities. Please verify the summary of quantities for drainage system 62 unit B

Inquiry submitted 10/07/2019

Response #1:Pending
Response posted 10/08/2019


Response #2:See Addendum #3 dated 10 10 2019
Response posted 10/10/2019




Inquiry #38: Due to the changes made in addendum 2 and unanswered questions still pending will Caltrans consider pushing the bid date to allow time for the review of these changes? These changes and open questions affect many different trades and subcontractors.
Inquiry submitted 10/08/2019

Response #1:Addendum #3 will be issued October 10, 2019

Reference BI #2
Response posted 10/08/2019




Inquiry #39: The ADL report provided for this project states that excavated soils are classified as non-hazardous and not restricted for use on site. It further states that surplus soil can be disposed of as non-hazardous waste at a Class III landfill. Special Provisions state that material must be stockpiled before disposal. If disposal site accepts material based on the ADL report provided in the Informational Handout, is stockpiling still required?

Inquiry submitted 10/10/2019

Response #1:Pending
Response posted 10/10/2019


Response #2:Please bid per the Contract documents
Response posted 10/10/2019




Inquiry #40: Please provide a link to the mandatory pre-bid sign in sheet.
Inquiry submitted 10/10/2019

Response #1:Pending
Response posted 10/10/2019


Response #2:Mandatory pre-bid sign in sheet will be made available to all bidders after bid opening
Response posted 10/11/2019




Inquiry #41: 1. Notice to bidder page 20 only indicate the duration for erosion control establishment
work. Please confirm this duration is also the duration for entire project.
2. Please provide us Riser type VI detail for all irrigation heads per sheet ISS-1 Irrigation
sprinkler schedule.
3. Please verify the location of item 79(F) 6" PLASTIC PIPE (SCHEDULE 40) (SUPPLY
LINE). This item was not shown on plans.
4. Please confirm Irrigation valve A-2 (1’’) shown on sheet IP-3 is new valve or existing
valve. Its symbol shown as existing but called out as new valve.

Inquiry submitted 10/11/2019

Response #1:1. Reference BI #4

Pending 2, 3, 4
Response posted 10/11/2019


Response #2:2 & 4 Please bid per the Contract documents

3 Bid in accordance with Sheets IP-6 through IP-9
Response posted 10/14/2019




Inquiry #42: Please confirm the quantity for BI 11 - Portable CMS is correct. Is the contractor expected to have 60 ea CMS boards on site at all times?

Inquiry submitted 10/11/2019

Response #1:Pending
Response posted 10/11/2019


Response #2:Please bid per the Contract documents
Response posted 10/14/2019




Inquiry #43: There is not a Section 39 segment included in the special provisions. Can you clarify what type of asphalt material you intend to use for this project?
Inquiry submitted 10/11/2019

Response #1:Submitted for consideration.
Response posted 10/11/2019


Response #2:Please bid per the Contract documents
Response posted 10/14/2019




Inquiry #44: In reference to Bid Inquiry #40 - By not providing a link to the mandatory pre-bid sign in sheet, Caltrans is preventing subcontractors and suppliers (including DBE firms) from sending quotes to all qualified General Contractors. Please provide a link to the mandatory pre-bid sign in sheet so subcontractors can send quotes to the General Contractors who attended the mandatory pre-bid.
Inquiry submitted 10/14/2019

Response #1:Reference BI #40
Response posted 10/14/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.