Submit new inquiry for this projectInquiry #1: It appears that the PPF, PVP, and PDF smoothness files that were shared were for a different portion of Hwy 1 than this project entails. The smoothness files shared are from Stations 186+75 to 231+05 and from Stations 266+61 to 455+20. Also, the naming convention of the files indicated that they are for a different project. Can Caltrans please share the correct smoothness files that apply to this project?
Inquiry submitted 11/23/2020
Response #1:Pending
Response posted 11/23/2020
Response #2:Addendum pending
Response posted 12/08/2020
Response #3:See Add #3 issued 12/21/20
Response posted 12/24/2020
Inquiry #2: Per Section 39-3.04A, please confirm that street is to be cold planed and paved in the same working day, i.e. no ground surface open to traffic at end of day.
Inquiry submitted 11/30/2020
Response #1:Pending
Response posted 11/30/2020
Response #2: Ref Section 39-3.04A on page 47 of the SP book.
UPDATE: Bid per the current contract document
Response posted 12/08/2020
Inquiry #3: What method for drainage inlet protection is expected for this project?
Inquiry submitted 12/01/2020
Response #1:Pending
Response posted 12/01/2020
Response #2: Most inlets in this project limit are curb inlets without grate, T64-6B should be used for those inlets. There are a few grate inlets with curbside opening, T62-3A should be used for those inlets. The project specifications include Std. Plans (T61, T62, T63, & T64). Please bid per the current contract documents
Response posted 12/08/2020
Inquiry #4: Please confirm bid item 17, Remove Tree, is for the removal of 2 trees and not the removal of one tree and a relocation of the second tree as stated in C-129.
Inquiry submitted 12/14/2020
Response #1:Pending
Response posted 12/14/2020
Response #2:Please bid per current contract document
Response posted 12/15/2020
Inquiry #5: Please advise on addendum status per Response #2 to Inquiry #1. Will the bid be postponed?
Inquiry submitted 12/15/2020
Response #1:BI #1 Response #2 is same: Addendum pending
REF Addendum #2 dated 12/15/20 for new BO date
Response posted 12/15/2020
Inquiry #6: What bid Item are Construction Area Signs (sheets CS-1, MI-1) covered under? Usually there is a CAS bid item.
In addition, Item #08 Channelizer (surface mount) these would typically be used when traffic control is left in place. However per the lane charts the contractor is supposed to open up the full travel when construction is not actively in progress or rather at the end of the work shift. Can regular 28" cones be used instead?
Inquiry submitted 12/28/2020
Response #1:Pending
Response posted 12/28/2020
Response #2:Response to both parts: Please bid per the current contract documents
Response posted 12/29/2020
Inquiry #7: In regards to my previous question, what is the quantity of T64-6B inlets and the quantity of T62-3A inlets?
Inquiry submitted 12/29/2020
Response #1:Please bid per the current contract documents
Response posted 12/29/2020
Inquiry #8: There is no bid item for Construction Area Signs. How does it get compensated?
Inquiry submitted 01/04/2021
Response #1:Please bid per the current contract documents
Response posted 01/05/2021
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.