Viewing inquiries for 12-0N6604

Submit new inquiry for this project


Inquiry #1: Is it the State's intent that the work be performed for anchor blocks,concrete barrier,mbgr, drainage systems, etc day time hours or night time hours ?
If the intent is to work day time, there is not enough work area for equipment and concrete deliveries or trucks behind the temporary k-rail to perform the work. Adjacent lane closures are necessary.
If the intent is to work at night however, the allowable lane closure hours per chart is very short to perform any productive work.

Also, there are no charts for camp closures.
Example: There is no chart for Barranca Parkway on-ramp which must be closed to place k-rail.

Inquiry submitted 11/15/2019

Response #1:Pending
Response posted 11/15/2019


Response #2:Is it the State's intent that the work be performed for anchor blocks,concrete barrier,mbgr, drainage systems, etc day time hours or night time hours ?
Please bid per Contract documents

If the intent is to work day time, there is not enough work area for equipment and concrete deliveries or trucks behind the temporary k-rail to perform the work. Adjacent lane closures are necessary.
Please bid per Contract documents

If the intent is to work at night however, the allowable lane closure hours per chart is very short to perform any productive work.
Addendum pending

Also, there are no charts for camp closures. Example: There is no chart for Barranca Parkway on-ramp which must be closed to place k-rail.
Addendum pending

Response posted 11/25/2019


Response #3:See Addendum #2
Response posted 12/13/2019




Inquiry #2: Refer to Plan Sheet 292 (EQ-1). Please confirm the quantities represented on the sheets, there are several items that are substantially higher from the work shown on the individual plans.
Inquiry submitted 11/27/2019

Response #1:Pending
Response posted 11/27/2019


Response #2:Addendum pending
Response posted 12/03/2019


Response #3:See Addendum #2
Response posted 12/13/2019




Inquiry #3: Refer to Plan Sheets 50-51 (Details C-7 & C-8 for Type 60M and 60MF Concrete Barrier Installed as Guardrail). Please confirm where these details are referenced on the layout plans as they do not appear to be indicated on Plan Sheets 5-43 (L-1 to L-39).
Inquiry submitted 12/09/2019

Response #1:pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #4: Refer to Plan Sheet 24 (L-20), which indicates approximately 400’ of “REMOVE Conc BARRIER” on Line K-2. Please clarify how this item will be paid as the bid item list does not appear to have a pay item for this type of concrete barrier removal, only item 83 for Type K Concrete Barrier Removal.
Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #5: Refer to Plan Sheet 191 (Q-2) which indicates 12.7 CY of Anchor Block at L-17 Location 123, however Plan Sheet 21 (L-17) does not show anchor block at Location 123. Please confirm if this 12.7 CY is correct and the location of this approximate 74’+ of anchor block.
Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #6: Refer to Plan Sheet 190 (Q-1) which indicates 150’ of MGS at L-6 location 9 but does not indicate MGS on Line B at location 136. Plan Sheet 10 (L-6) seems to indicate approximately 769’ of MGS on B-Line ending at Rt “B” + 19.4. Please clarify if this MGS on B-Line is accurate and where it begins as it doesn’t have a beginning location shown on Plan Sheet 9 or 10.
Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #7: Refer to Plan Sheet 190 (Q-1) which indicates MGS Layout Type 12B at L-5 Location 137, however Plan Sheet 9 (L-5) shows Type 12A layout at this location. Please confirm which is correct.
Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #8: Refer to Plan Sheet 37 (L-33) which indicates “Beg SINGLE THRIE BEAM” on D-Line at 40.5’ Rt “N” + 59.00” but does not indicate where this Single Thrie Beam ends. Please clarify.

Similarly Plan Sheet 37 (L-33) does not indicate the Begin location for the Anchor Block On D-Line but does indicate “END ANCHOR BLOCK” on at 44’ Rt “N” +50.00”. Please clarify where the anchor block begins.


Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/09/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #9: Refer to Plan Sheet 37 (L-33) which indicates “END REMOVE GUARDRAIL” at 44’ Rt “N” +50.00, but doesn’t show the begin location. Please clarify the location the guardrail removal is to begin
Inquiry submitted 12/09/2019

Response #1:Pending
Response posted 12/10/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #10: Refer to Plan Sheet 4 (K-1) which indicates Plan Sheet WPC-7 for the work area associated with other plan sheets E-9, U-19, L-21, D-4, EC-21, and IP-2. I have not been able to locate this sheet, only plan sheets 59-64 WPC1-WPC6. Please clarify if there will be an addendum to include the mentioned sheet WPC-7.
Inquiry submitted 12/10/2019

Response #1:Pending
Response posted 12/11/2019


Response #2:See Addendum #2
Response posted 12/13/2019




Inquiry #11: Refer to Plan Sheet 27 (L-23) which indicates “END REMOVE AC DIKE” at 112’ Rt “J” +05.00 but does not indicate a begin location on Sheet 26 or Sheet 27. Please clarify the beginning location for removal of this AC Dike.
Inquiry submitted 12/11/2019

Response #1:Pending
Response posted 12/11/2019


Response #2:See Addendum #3
Response posted 12/20/2019




Inquiry #12: Refer to Plan Sheet 35 (L-31) at 4’ LT “M-2” +38.00 and clarify if a severe crash cushion will need to be installed at this location as the plan doesn’t specify but appears this would be needed.
Inquiry submitted 12/11/2019

Response #1:Pending
Response posted 12/11/2019


Response #2:See Addendum #3
Response posted 12/20/2019




Inquiry #13: Refer to Plan Sheet 37 (L-33) which indicates “END REMOVE AC DIKE” at 40.5’ Rt “N” + 59.00” but does not indicate a begin location on Sheet 36, 37, or 38. Please clarify the beginning location for removal of this AC Dike.
Inquiry submitted 12/11/2019

Response #1:Pending
Response posted 12/11/2019


Response #2:See Addendum #2
Response posted 12/20/2019




Inquiry #14: Please advise whether the contractor and his subcontractors will be exempt from toll fees levied by the Transportation Corridor Agencies. If not, please advise how those fees will be reimbursed/paid.
Inquiry submitted 12/11/2019

Response #1:Pending
Response posted 12/12/2019


Response #2:Please bid per the Contract documents. Caltrans does not reimburse nor are contractors exempt from toll fees.
Response posted 12/20/2019




Inquiry #15: Per Lay-out Sheet L-21, Location 46 shows 1 EA of Severe-Duty Crash Cushion and also on Lay-out Sheet L-30 there's also another one but does not have any location number. Both Severe-Duty Crash Cushions are not included on the Summary of Quantities and Bid Schedule, will this be added on a future addendum? Thanks
Inquiry submitted 12/12/2019

Response #1:Pending
Response posted 12/12/2019


Response #2:See Addendum #2 and #3
Response posted 12/20/2019




Inquiry #16: Didn't see any specifications for the Severe-Duty Crash Cushion, please provide one. Thanks
Inquiry submitted 12/26/2019

Response #1:Pending
Response posted 12/26/2019


Response #2:Please see Section 83-5.05 in the Special Provisions
Response posted 12/27/2019




Inquiry #17: Refer to Layout Plans and Contour Grading Plans. Supplemental info 12-0N6604XS Sheets 13-26 of 60 “C” Line Cross Sections and Sheets 27-46 of 60 “D” Line Cross Sections which seem to indicate earthwork/cut & fill locations but do not provide Stationing / Station Interval information. Please clarify the missing station information.
Inquiry submitted 12/27/2019

Response #1:Pending
Response posted 12/27/2019


Response #2:Please see sheets 13 - 46 for the revised Cross Sections with the correct station information.
Response posted 12/31/2019




Inquiry #18: Please reference 12/31/19 Response #2 to Inquiry #17, "Please see sheets 13 - 46 for the revised Cross Sections with the correct station information." Please clarify 1) the location of the "revised cross sections with the correct station information" as I have not found them in the documents available for download and 2) Will the incorrect sheets be deleted in a future addendum? Thank you

Inquiry submitted 12/31/2019

Response #1:Pending
Response posted 12/31/2019


Response #2:Please see addendum #4
Response posted 01/02/2020




Inquiry #19: Reference Special Provisions Page 24 Add to Section 19-7.02A, “Obtaining Imported Borrow Includes…Construct Access Road as Shown…” Please clarify the location of this “as shown” access road as I have not found this shown in the bid documents.

Inquiry submitted 01/02/2020

Response #1:Pending
Response posted 01/03/2020


Response #2:Please refer to quantity sheet Q-13 for the imported borrow quantities.


Response posted 01/03/2020




Inquiry #20: Refer to inquiry #2. While the addendum did address some of discrepancies, there are still some that remain. We can only assume the plans provide the accurate scope of work as shown and per plan sheet 292 "Notes" should a conflict exist, unless otherwise directed.
Inquiry submitted 01/07/2020

Response #1:Pending
Response posted 01/07/2020


Response #2:Please bid per plans
Response posted 01/07/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.